Financial Procedure Rule 19.1c and FPR7 - Authorisation for Alteration and Conversion of Bay Studios, Fabian Way, Swansea into a 1000 Bed Surge Hospital on Behalf of the Swansea Bay University Health Board.
ApprovedExecutive1 paper
Cabinet approved this item on Monday 27 April 2020. Below is the council's own wording, with the papers it was decided on.
Resolved that: 1) The project led by the Council on behalf of Swansea Bay University Health Board to convert the Elba Building, Bay Studios into a surge hospital together with the associated financial implications be approved and added to the capital programme (to comply with FPR7 – addition to capital programme); 2) Authority be delegated to the Director of Place in conjunction with the Leader of the Council, Chief Finance Officer and Chief Legal Officer to approve the final project cost and to enter into any agreements necessary (based on the draft collaboration agreement included in Appendix A of the report) to ensure the delivery of the project and to protect the Council’s interests; 3) The Director of Place and Chief Finance Officer be authorised to recover all expenditure associated with the delivery of the project from Swansea Bay University Heath Board in the first instance and if necessary from Welsh Government.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Leader and Cabinet Member for Economy and Strategy
Special Cabinet - 27 April 2020
Financial Procedure Rule 19.1c and FPR7. Authorisation for Alteration and Conversion of Bay Studios, Fabian Way, Swansea into an 1000 Bed Surge Hospital on Behalf of the Swansea Bay University Health Board Reason for Urgency: Covid-19 emergency build of hospital for handover to Swansea Bay University Health Board week commencing 27 April 2020.
Purpose: To enable the delivery on behalf of the Swansea Bay University Health Board of the conversion of Elba Building, Bay Studios, Fabian Way, Swansea into an 1000 bed surge hospital and to approve the project in line with FPR7 and FPR 19.1c.
Policy Framework: Council Constitution:- Financial Procedure Rules FPR19.1c (emergency – danger to life) and FPR 7 Capital Programme
Recommendation(s): It is recommended that:
1) The project led by the Council on behalf of Swansea Bay University Health Board to convert the Elba Building, Bay Studios into a surge hospital together with the associated financial implications is approved and added to the capital programme (to comply with FPR7 – addition to capital programme);
2) Authority is delegated to the Director of Place in conjunction with the Leader, Chief Finance Officer and Chief Legal Officer to approve the final project cost and to enter into any agreements necessary (based on the draft collaboration agreement included in Appendix A) to ensure the delivery of the project and to protect the Council’s interests:
3) The Director of Place and Chief Finance Officer are authorised to recover all expenditure associated with the delivery of the project from Swansea Bay University Heath Board in the first instance and if necessary from Welsh Government. Report Author: Martin Nicholls
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
1. Introduction
1.1Due to the unprecedented impact of Covid 19 on the population it is essential that additional hospital beds are provided in the event that hospitals within Swansea and Neath Port Talbot are unable to deal with any surge in admissions. Similar steps are being undertaken by other Local Authorities in the UK with Welsh Government identifying a shortage of 10,000 and Swansea Bay University Health Board identifying a requirement of a minimum of 1300 addition beds. The actual occupation as a field hospital will be dealt with by Swansea Bay University Health Board and the Council will have no liability in this regard.
1.2As such the Council has been requested by The Swansea Bay University Health Board to urgently undertake on its behalf alterations and conversion works to the Bay Studios, Fabian Way, Swansea to provide a 1000+ bed surge hospital. The works have commenced on an emergency basis and will last approximately eight weeks.
1.3As the project is being undertaken and managed by the Council on behalf of the Health Board, it has been agreed that the Council’s Building Services Department will be appointed as Principal Contractor under a cost reimbursable NEC3 Option E contract to deliver and manage the works. The specification for and the design of the works has been undertaken by the Health Board who will be the ultimate occupiers and operators of the site.
1.4Due to time constraints arising from the urgent requirement of this facility it was not possible for the Council to undertake a tendering exercise to appoint suitably experienced contractors to undertake the works and so two contractors from the South West Wales Regional Contractor’s Framework 2020 (SWWRCF 2020) were approached to confirm capacity to carry out the works. These awards will be dealt with separately.
2. Site Identification Process
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Financial Procedure Rule 19.1c and FPR7: Authorisation for Alteration and Conversion of Bay Studios, Fabian Way, Swansea into a 1000 Bed Surge Hospital on Behalf of the Swansea Bay University Health Board.Report
191Financial Procedure Rule 19.1c and FPR7 - Authorisation for Alteration and Conversion of Bay Studios, Fabian Way, Swansea into a 1000 Bed Surge Hospital on Behalf of the Swansea Bay University Health Board.This decision
Financial Procedure Rule 19.1c and FPR7 - Authorisation for Alteration and Conversion of Bay Studios, Fabian Way, Swansea into a 1000 Bed Surge Hospital on Behalf of the Swansea Bay University Health Board.This decision
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.