Resolved that the following be recommended to Council for approval: 1) The transfers between schemes and the revised budgets for schemes in 2022-2023 be approved. 2) The budget proposals for 2023-2024 – 2026-2027 be approved. 3) Where individual schemes in Appendix B are programmed over the 4-year period described in the report, then these be committed and approved and their financial implications for funding over the 4 years also be approved.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Purpose: This report proposes a revised capital budget for 2022/23 and a capital budget for 2023/24 – 2026/27
Policy Framework: None
Consultation: Cabinet Member, Legal, Finance & Access to Services
Recommendation(s): It is recommended that Cabinet:
1) Approves the transfers between schemes and the revised budgets for schemes in 2022/23.
2) Approves the budget proposals for 2023/24 – 2026/27.
3) Approves those individual schemes in Appendix B which are programmed over the 4 year period as described in this report, are committed and that their financial implications for funding over 4 years are approved.
Report Author(s): Ben Smith / Carol Morgan
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Officer: Rhian Millar
1.0Introduction
1.1This report details:
Revised Housing Revenue Account (HRA) capital expenditure and financing proposals in 2022/23 HRA Capital expenditure and financing proposals in 2023/24 – 2026/27 1.2 The budget proposals are further detailed in the appendices to this report as follows:
Appendix A: Summary of the revised budget for 2022/23 and a budget for 2023/24 – 2026/27 Appendix B: Detailed breakdown of the revised budget for 2022/23 and a budget for 2023/24 – 2026/27 Appendix C: Welsh Housing Quality Standard (WHQS) and More Homes scheme descriptions
2.0Capital Budget
2.1The revised programme for the current year is £37.046m i.e. an original budget of £58.2m plus carry-forward from 2021/22 of £2.7m, additional More Homes Schemes of £4.4m less slippage into 2023/24 of £27.3m and other budget adjustments of £0.95m.
2.2Slippage from 2022/23 into 2023/24 has occurred for a number of reasons. Post pandemic buoyancy in the building industry across the region and shortage of building industry skills has led to restricted programme delivery across a number of work streams. This has been further compounded by high demands for core building materials which has affected the supply chain. Programme delays have also occurred due to limited renewable energy design specialists to design, specify and integrate these elements into a number of wind and weatherproofing schemes.
2.3The revised More Homes programme for 2022/23 includes increased budget for the acquisition programme, where the focus has been on purchasing ex- council properties that were sold under the Right to Buy as part of the response to rapidly increase the supply of affordable housing to deal with the continuing high levels of demand. Two schemes to convert former District Housing Offices into accommodation were also brought into the programme in response to the WG TACP (Transitional Accommodation Capital Programme) to address the immediate need for accommodation to relieve pressure on homelessness. Masterplans for larger development sites have also been developed.
2.4The proposed four-year capital programme and the priorities of the various schemes have been developed in line with the HRA Business Plan. They are designed to maintain the Welsh Housing Quality Standard as well as increase the supply of council housing. The investment set out in 2023/24 will ensure remaining 2022/23 commitments will be met and new 2023/24 work-streams have been developed to ensure they are deliverable. Transfers and changes to the 2022/23 budget are set out in appendix B.
3.0Welsh Housing Quality Standard (WHQS)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.