Resolved that: 1) The Council accepts and utilises a UK Government grant for the development of a Detailed Program Design for a district heat network. 2) The progress made to date for the management of land around SA1 (including Tir John) in support of the broader Blue Eden development be noted.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Service Transformation
Cabinet – 18 April 2024
District Heat Network Feasibility Purpose: To gain approval for grant application and acceptance, for monies to undertake more detailed design work around the potential for the provision of a district heat network in parallel with Blue Eden developments.
Policy Framework: Well-being of Future Generation Act & Swansea Council Corporate Plan Financial Procedure Rules
Consultation: Legal, Finance, Access to Services.
Recommendation(s): It is recommended that Cabinet:
1. Agrees that the Council accepts and utilises a UK Government grant for the development of a Detailed Program Design for a district heat network.
2. Notes the progress made to date for the management of land around SA1 (including Tir John) in support of the broader Blue Eden development.
Report Author: Geoff Bacon
Legal Officer Debbie Smith
Finance Officer: Ben Smith
Access to Services Officer: Catherine Window
1. Introduction
This report sets out the potential for the provision of a district heat network in parallel with the Blue Eden development. It covers progress on this front to date and seeks Cabinet approval to accept a UK Government grant to further this work. 2. Background
2.1The continuing development of the land to the South of Fabian Way, which hosts the Swansea University Bay Campus, and will host housing and hotel accommodation, and elements of a renewable energy project (referred to as Blue Eden), offers the potential for the introduction of a District Heat Network (DHN).
2.2In May 2023, Cabinet approved and delegated to officers the power to agree Heads of Terms and conclude documentation for the disposal/occupation of sites, by way of lease in support of the Blue Eden development.
To update briefly on that position:
• Fabian Way Park and Ride expansion site: The current proposal includes the main Park and Ride site only, the overflow site is still linked to TfW proposals. • Site of closed Tir John proposed for Solar Farm: Heads of Terms have been agreed in principle with more detailed terms, including negative controls, currently being reviewed. • Part of Former Morrissey Site in SA1: As above, Heads of Terms have been agreed in principle with more detailed terms, including negative controls, currently being reviewed. • Burrows Yard: Council involvement in the acquisition of Burrows Yard is no longer required and DST Innovations, who are leading the Blue Eden development, are in direct negotiations with Network Rail.
2.3The development and operation of the Blue Eden energy projects will have significant energy demands but also have the potential to provide a heat source for a heat network (waste heat from the proposed data centre could be utilised).
2.4Given the short timescales involved, it was not practical to inform Cabinet of the bid being prepared to submit to the UK government prior to the bid submission date. This paper updates members on progress to date and seeks retrospective approval for the Council’s applications.
3. Works to Date
3.1In December 2022 the Council received a high level feasibility study (funded by the Community Renewal Fund (CRF)) which considered the possible introduction of a heat network in Swansea.
3.2This study looked at current and future demand opportunities within an area which broadly covers the area between the University campus on Fabian Way and the Civic Centre on Oystermouth Road, encompassing HMP Swansea, Swansea Museum, the Technium buildings and other developments in the docks/SA1 area. This area outline can be seen below as Figure1.
Figure 1: Potential coverage of a heat network
3.3The report concluded favourably that there was significant opportunity for the development of a city-scale carbon heat network and whilst there was no certainty of financial viability, a detailed feasibility study should be considered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.