Resolved that: 1) The additional capital allocation of £1m to the community budget dedicated to specific changing room improvement schemes outlined in the report be approved. 2) The additional capital allocation of £1m to the community budget to support wider community improvements. Authority is delegated to the Cabinet member for Economy, Finance & Strategy, the Cabinet Member for Investment, Regeneration, Events & Tourism, and the Director of Place to determine eligibility for each scheme. In the event of a scheme being submitted in one of the wards of those Cabinet Members with delegated authority, the decision would be made instead by the Deputy Leader in conjunction with the Director of Place be approved .
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Economy, Finance & Strategy and the Cabinet Member for Investment, Regeneration, Events & Tourism
Cabinet – 18 April 2024
Financial Procedural Rule 7 Additional Community Budget Capital 2024-2025 Purpose: 1. To commit and authorise capital schemes approved for changing room improvements at a total value of £1m. 2. To commit an additional £1m community budget to support wider community improvements.
Policy Framework: Community Budget and Council Constitution - Financial Procedure Rule 7.3
Consultation: Access to Services, Finance, Legal. Recommendation(s): It is recommended that Cabinet:
1) Approves the additional capital allocation of £1m to the community budget dedicated to specific changing room improvement schemes outlined in the report.
2) Approves the additional capital allocation of £1m to the community budget to support wider community improvements. Authority is delegated to the Cabinet member for Economy, Finance & Strategy, the Cabinet Member for Investment, Regeneration, Events & Tourism and the Director of Place to determine eligibility for each scheme. In the event of a scheme being submitted in one of the wards of those Cabinet Members with delegated authority, the decision would be made instead by the Deputy Leader in conjunction with the Director of Place.
Report Author: Geoff Bacon Finance Officer: Ben Smith Legal Officer: Tracey Meredith Access to Services Officer: Rhian Millar 1. Introduction
1.1Council approved the Capital Budget & Programme 2023/24-2028/29, on 6th March 2024. The following budgets were proposed, and approval recorded.
2. Changing Room Improvement Scheme – Capital Value £1m
2.1.1 An initial review of the condition surveys for sports changing rooms (located primarily with parks/sports fields) has been undertaken by the Building Services department.
2.1.2 An indicative shortlist of facilities that would benefit from investment has been developed at this stage. It is anticipated that following further review, it is likely that the list may need to be refined according to demand and budget available. However, it must be noted that the list which has been informed by high level estimated costs at this stage is not finalised or exhaustive.
Key criteria to consider in developing individual specifications and cost plans for each site will focus of the following areas, as a principle; • Demand from local clubs • Re-enabling building to be safely used/prevent falling into disrepair. • Modernising of internal facilities inline with governing body guidelines • Encourage/enable use by women and girls • Future financial Sustainability through self-management/lease to enable further direct funding. • Energy efficiency improvements
2.1.3 The indicative example shortlist will be informed through more detailed surveys to inform the cost plan with an intention to prioritise assets are supported for improvement works as part of a rolling programme: e.g. Cwm Level Changing rooms Tir Canol Changing rooms Bonymaen Park Changing rooms Ynystawe Park Changing Rooms Cadle Mill Trallwyn
2.1.4 Following further reviews and final cost estimates, the Director of Place in consultation with relevant Departments and Cabinet member, will determine package of works, costs and sites.
2.1.5 This programme falls outside the wider community budget spend criteria and will be managed internally by Building Services. 3. Additional Community Budget Fund – Capital Value £1m
3.1Capital Allocation
As part of the 2024-25 budget setting process Council has identified a specific capital allocation of £1m to form part of the overall community budget scheme. The following principles will apply:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.