Resolved that: 1) The transfers between schemes and the revised budgets for schemes in 2024/25 be approved. 2) The budget proposals for 2025/26-2028/29 be approved. 3) Those individual schemes detailed in Appendix B of the report which are programmed over the 4-year period as described in the report be approved and committed and their financial implications for funding over 4-years also be approved.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Section 151 Officer & the Director of Place
Cabinet – 20 February 2025
Housing Revenue Account – Capital Budget & Programme 2024/25 – 2028/29 Purpose: This report proposes a revised capital budget for 2024/25 and a capital budget for 2025/26 – 2028/29.
Policy Framework: More Homes Delivery Programme 2021-2031 Local Housing Strategy 2020
Consultation: Cabinet Member, Legal, Finance & Access to Services
Recommendation(s): It is recommended that Cabinet:
1) Approves the transfers between schemes and the revised budgets for schemes in 2024/25
2) Approves the budget proposals for 2025/26 – 2028/29.
3) Approves those individual schemes in Appendix B which are programmed over the 4-year period as described in this report, are committed and that their financial implications for funding over 4 years are approved.
Report Author: Dave Bratley
Finance Officer: Ben Smith
Legal Officer: Adrian Jeremiah
Access to Services Officer: Rhian Millar
1. Introduction
1.1This report is to meet financial procedure rules and sets out the revised Housing Revenue Account (HRA) capital expenditure and financing arrangements for 2024/25 and the HRA Capital budgets and financing proposals in 2025/26 – 2028/29. 1.2. The budget proposals are further detailed in the appendices to the report as follows:
• Appendix A: Summary of the revised budget for 2024/25 and a budget for 2025/26 – 2028/29 • Appendix B: Detailed breakdown of the revised budget for 2024/25 and a budget for 2025/26 – 2028/29 • Appendix C: Welsh Housing Quality Standard (WHQS) and More Homes scheme descriptions
2. Capital Budget
2.1The revised programme for the current year is £53.5m from an original budget of £55.059m. The projected outturn is £49.7m with £3.8m slippage into 2025/26 against the revised budget.
2.2Capital investment over the next 4 years is £219m.
2.3Slippage from 2024/25 into 2025/26 has occurred in some work areas due to insufficient specialist design resource or complex projects requiring greater level of investigation and design leading to the schemes taking longer to reach the delivery stage. Also, some projects have encountered on-site delays due to managing ecology issues as well as performance by statutory bodies leading to contracts having to extend into the new financial year.
2.4Over the term of the new proposed 4-year capital programme there is insufficient funding available to deliver the full WHQS 2023 requirements and all the More Homes projects. This is in part due to Welsh Government’s rent setting policy which is lower than had been forecast for 2025, increasing demands on the revenue repairs’ budget and limited grant claiming opportunities. Coupled to this are building and capital maintenance costs which continue to rise and therefore the programme has required significant revisions. The proposed four-year capital programme is developed in line with the HRA Business Plan and remains affordable, however due to the increasing costs, represents an overall reduction in activity and delivery on the ground.
2.5The revised More Homes Delivery Programme includes a continuing budget for the Right to Buy acquisition programme, where the focus has been on purchasing former council properties as part of the response to rapidly increase the supply of affordable housing to deal with the continuing high levels of demand. Budget has also been allocated for the acquisition of new properties via s106 planning agreements and funding is in place to bring forward a “Package Deal” option with a private developer. Masterplans for larger new build development sites are being developed. In order to provide a manageable level of spend for the HRA Business Plan, some scheme start dates have been deferred. 3. Proposed 4 Year HRA Capital Programme
Welsh Housing Quality Standard 2023 (WHQS 2023)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.