Commitment of Capital Funding for the Contractor Appointment and Construction at Ysgol Gyfun Gymraeg Bryn Tawe as part of the Sustainable Communities for Learning Programme.

Decided Executive 1 paper

AI summarySwansea Council Cabinet commits £32,045,402 of capital funding for construction of Ysgol Gyfun Gymraeg Bryn Tawe under the Sustainable Communities for Learning Programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecided£32,045,402 approved for school construction
Money£32,045,402Total capital programme commitment including internal fees £32.45m
What happens nextContract award report being preparedBy building services for the works contract
Who it affectsYsgol Gyfun Gymraeg Bryn TaweWelsh-medium secondary school construction project

What was decided

The Cabinet committed £32,045,402 to the capital programme for the contractor appointment and construction of Ysgol Gyfun Gymraeg Bryn Tawe.

The total capital commitment including all internal fees totals £32.45m and sits within the reprofiled approved education and schools programme. Report P2

Why

The funding is needed to deliver the school construction under the Welsh Government's Sustainable Communities for Learning Programme. Report P9

Delivering the programme will help the council meet its obligations under the Equality Act 2010 and the Well-being of Future Generations (Wales) Act 2015. Report P6

All works, goods and services contracts must be procured under the council's Contract Procedure Rules and relevant procurement legislation. Report P5

What happens next

A contract award report is being prepared by building services for the award of the construction contract. Report P7

The capital spend is profiled across 2024/25 to 2029/30, with the main construction costs falling in 2026/27, 2027/28 and 2028/29. Report P11

The council will need to comply with the terms and conditions of any Welsh Government grant funding. Report P5

The money

  • £32,045,402 Capital programme commitment for YGG Bryn Tawe main scheme Report P11
  • £32.45m Total capital commitment including all internal fees Report P2
  • £19,485 Welsh Government rolling programme funding (£'000) Report P12
  • £1,494 Welsh Government WM funding (£'000) Report P12
  • £575 Welsh Government NZC funding (£'000) Report P12
  • £10,491 Local authority unsupported borrowing (£'000) Report P12
  • £403 Estimated expenditure 2024/25 (£'000) Report P11
  • £6,514 Estimated expenditure 2026/27 (£'000) Report P11
  • £15,218 Estimated expenditure 2027/28 (£'000) Report P11
  • £8,694 Estimated expenditure 2028/29 (£'000) Report P11

Implications

  • Legal: The council must comply with Welsh Government grant terms and procurement legislation, with contractual liabilities covered by individual contracts. Report P5
  • Equalities: Delivery will assist the council in meeting its Equality Act 2010 and Well-being of Future Generations (Wales) Act 2015 obligations. Report P6
  • Financial: The capital commitment sits within the reprofiled approved education and schools programme. Report P2

Who and where

  • Pupils and staff of Ysgol Gyfun Gymraeg Bryn Tawe
  • Swansea Council as commissioner and contract holder Report P5
  • Future contractors appointed to deliver the construction Report P5, P7
  • Welsh Government as grant funder Report P5, P12

Plain English for the jargon

  • Sustainable Communities for Learning Programme: A Welsh Government programme referenced as the framework for this school investment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item136

Resolved

Resolved that: 1) The sum of £32,045,402 be committed to the capital programme.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Education & Learning

Cabinet – 19 February 2026

Commitment of Capital Funding for the Contractor Appointment and Construction of Ysgol Gyfun Gymraeg Bryn Tawe as part of the Sustainable Communities for Learning Programme

Executive Summary Purpose of Report: The report is seeking authorisation to commit funding to the capital programme and appoint a contractor to progress the stage 2 construction phase work at YGG Bryn Tawe.

To comply with Financial Procedure Rule No 7 (Capital Programming and Appraisals) to commit the sum of £32,045,402 in line with expected expenditure.

Recommendation(s). It is recommended that: 1) The sum of £32,045,402 is committed to the capital programme

Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☒ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why Specify the exact paragraphs from the Council Constitution. Financial Procedure Rule No 7 (Capital Programming and Appraisals) Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☒ Education & Skills ☒ Tackling Poverty & Enabling Communities ☒ Economy & Infrastructure ☒ Transformation & Financial Resilience ☒ Nature Recovery & Climate Change ☒ All ☒ Safeguarding ☐ Not Applicable

Relevance to Corporate Plan Wellbeing Objectives:

The award of contract for the demolition aligns with; 1. Improving Education and Skills - so that everyone in Swansea gains the skills and qualifications they need to succeed in life. 2. Transforming our Economy and Infrastructure - so that Swansea has a thriving mixed use city centre and a local economy that will support the prosperity of our citizens.

Reviewed and approved by: Access to Services, Finance, Legal & Cabinet Member.

Report Author & Job Louise Herbert-Evans - Team Manager Capital Title:

1. Introduction

2. The council’s approved Capital Budget & Programme 2024/25 – 2029/30 includes the new rolling Sustainable Communities for Learning Programme.

3. Included within the first phase of priority projects is the increase of capacity at YGG Bryn Tawe.

4. The Outline Business Case (OBC) received approval in principle in December 2021 allowing the project to progress to pre-construction design stage.

5. A competitive tendering exercise for the pre-construction design phase was undertaken between 9 April and 31 May 2024, following which Andrew Scott Construction Ltd were appointed in October 2024. The project is now being developed to RIBA Stage 4 and the associated planning processes are in progress.

6. The Full Business Case (FBC) was submitted to Welsh Government on 31 December 2025 for consideration at the Education Investment Panel on 26 February 2026.

7. Subject to WG approval of the FBC, contract award approval will be sought under delegated authority to award the contract in accordance with Contract Procedure Rule 18.

8. To facilitate the progression of the project and appointment of the contractor, this report seeks approval to commit a total of £32,045,402 to the capital programme for this project.

9. If this funding is not committed to the capital programme for this project, then the project will not be able to proceed, and the opportunities of the school site development will not be realised.

10. Timescales

11. Subject to contract award the construction period which will take a planned phased approach is anticipated to commence in June 2026 and will be completed by April 2028

12. Stakeholder Participation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Commitment of Capital Funding for the Contractor Appointment and Construction at Ysgol Gyfun Gymraeg Bryn Tawe as part of the Sustainable Communities for Learning Programme.Report 162 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 28 attended
CA
Cyril AndersonCommittee Member, present
AA
Alyson AnthonyCommittee Member, present
JD
Jeffrey DongOfficer, expected
HE
Huw EvansOfficer, present
PF
Patrick FletcherOfficer, expected
RF
Rebecca FogartyCommittee Member, present
LG
Louise GibbardCommittee Member, present
HG
Hayley GwilliamCommittee Member, present
AW
Andrea WilliamsCommittee Member, present
DH
David HopkinsCommittee Member, present
DH
David HowesOfficer, expected
RJ
Rhodri JonesOfficer, expected

All 28 on the meeting page

On this subject at Swansea

Search all
  1. Commitment of Capital Funding for the Contractor Appointment and Construction at Ysgol Gyfun Gymraeg Bryn Tawe as part of the Sustainable Communities for Learning Programme.This decision
  2. Capital Programme Authorisation for the Commitment of Capital Grant Funding Awarded to Support Learners with Additional Learning NeedsDecided
  3. Capital Programme Authorisation for the Commitment of Capital Grant Funding Awarded for Community Focused Schools Projects.Decided
  4. Commitment of Capital Funding for the Contractor Appointment and Design Development of the New Build Special School.Approved
  5. Capital Programme Authorisation for the Commitment of Capital Grant Funding Awarded to the Authority’s Traveller Site and Authorisation to Move Capital Funding Into The Traveller Site Budget.Approved
  6. Capital Programme Authorisation for the Commitment of Capital Grant Funding Awarded to Support Learners with Additional Learning Needs.Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies