Resolved – (1) That Cabinet agrees that it would not be feasible for the Council to undertake a strategic environmental assessment of the Swindon Borough Local Plan 2011, in view of the state that the Plan has now reached, the effect of the transitional provisions in the Planning and Compulsory Act, 2004, and the prejudiced to good administration of the Planning system. (2) That the Director of Environment and Property be authorised to carry out the necessary procedures set out in paragraph 5.7 of the report to notify the public of the decision at (1) above. (LM: MB)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
By: Director of Environment and Parish/Ward: All Property and Director of Law and Corporate Governance
Swindon Borough Local Plan 2011 – Environmental Assessment of Plans and Programmes Regulations, 2004. Regulation 6(2) Notice 1 Purpose To inform Cabinet of the requirements of the Environmental Assessment of Plans and Programmes Regulations, 2004 which will impact on the emerging Swindon Borough Local Plan. 2 Recommendations
2.1.1 The Cabinet is recommended to agree that;
(1) it would not be feasible for the Council to undertake a Strategic Environmental Assessment of the Swindon Borough Local Plan, 2011, in view of the stage that the Plan has now reached; the effect of the transitional provisions in the Planning and Compulsory Purchase Act, 2004; and the prejudice to good administration of the planning system.
(2) the Director of Environment and Property be authorised to carry out the necessary procedures set out in paragraph 5.7 of this report to notify the public of the decision set out in paragraph 2.1.1 (1) above.
3 Financial and Procurement Implications
3.1The Council must comply with the Environmental Assessment of Plans and Programmes Regulations, 2004 so that the possibility of a legal challenge to adoption is reduced. Any legal challenge would have a significant cost to the Borough both financially and in terms of staff resources.
3.2The Regulations require notification to be given by an authority where a plan in production is not to be subject to Strategic Environmental Assessment. It is expected that there will be a small cost to the Borough Council regarding notification, though this can be covered by existing Local Policy budgets. 4 Social, Environmental, Staffing and Legal/Human Rights, Risk and Other Implications
4.1Social Implications
4.1.1 Although the Local Plan addresses land use planning aspects relating to social issues, there are no direct social implications arising from this report.
4.2Environmental Implications
4.2.1 The Environmental Assessment of Plans and Programmes Regulations, 2004 place a duty on those authorities preparing plans and strategies to consider fully the environmental impacts of their policies and proposals. Although it is not now feasible for the Local Plan to be subjected to Strategic Environmental Assessment, it has been assessed through a rigorous sustainability appraisal at both Deposit stages, ensuring that environmental impacts of policies and proposals have been fully and appropriately considered.
4.3Staffing Implications
4.3.1 There are no staffing implications directly arising from this report. However, resourcing any legal challenge, - the possibility of which could be enhanced without appropriate adherence to the Regulations, - would inevitably place pressure on existing staff.
4.4Legal/Human Rights Implications
4.4.1 The detailed legal implications of this legislation as it affects local policy production are detailed in the report. It is not considered that the content of this report has any implications for human rights.
4.4.2 The Environmental Assessment of Plans and Programmes Regulations came into force on July 20th 2004. Relevant details of these regulations are set out in the body of this report. Cabinet must consider the question of whether the requirement of an Environmental Assessment under the Regulations is not feasible with regard to the Swindon Borough Local Plan, 2011.
4.5Risk and Other Implications
4.5.1 If the Regulations are followed, the risk of a legal challenge is diminished. Any legal challenge would be costly to the Council and would hold up adoption of the Local Plan.
4.6Links to the Corporate Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.