Resolved – (1) That Lydiard be established as a single cost centre, including house, park, visitor centre cafe and conference centre under a single "Cost Centre Manager" reporting to the Chief Executive from April 2005. (2) That a further progress report, covering Stage 2 funding in partnerships, be submitted to the Lead Member in December 2004 prior to the Council's forthcoming submission to the Heritage Lottery Fund. (3) That the proposal for future service provision at Lydiard and, specifically, the renewal of the HTS Management Centre contract, be referred to the Procurement Board for consideration. (4) That a further report be submitted to the Cabinet meeting in January 2005 setting out the detail of the Business and Financial Plan for Lydiard Park from 1 st April, 2005. (5) That, in preparing the Business and Financial Plans referred to in (4) above, the Unions be assured that their views will be sought as part of that process. (LM: FF)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
2.1That Lydiard be established as a single cost centre, including House, Park, Visitor Centre Café, and Conference Centre, under a single “cost centre manager” reporting to the Chief Executive from April 2005.
2.2That a further progress report, covering Stage 2 funding and partnerships, be submitted to the Lead Member in December 2004 prior to the Council’s forthcoming submission to the Heritage Lottery Fund.
3 Financial and Procurement Implications 3.1 The capital funding for the development stage of the project currently being undertaken is £573,000 for which 100% funding is secured. This comes via a Heritage Lottery Fund Award of £430,000 (75%), Corporate partnership funds from RWEnpower (formerly Innogy) of £70,000, contributions from other organisations and volunteer labour £28,000 and £45,000 from Swindon Council. The project is progressing within budget.
3.2The Development Stage of the project has attracted additional funding, including an award of £30,000 from Arts and Business South West, the largest grant to be distributed by them in Britain, to support the pioneering Lydiard Park/RWEnpower partnership.
3.3Members of The Lydiard Park Project Core Management Team, Alan Smith (seconded from RWEnpower) and Sarah Finch-Crisp are currently engaged in discussions with local business re future support and involvement in Lydiard Park and the restoration works. This will be the subject of a further report in December 2004. £80k is already committed by RWEnpower.
3.4The Team is also seeking financial contributions from a variety of grant funding organisations for the Stage 2 restoration works. To date two Countryside Stewardship Agreements schemes have been signed with Department for Environment, Food and Rural Affairs (September 2004) which will release £150k for restoration works in the wider parkland. This is £100k more than budgeted and a significant additional contribution to the project.
4 Social, Environmental, Staffing, Legal/Human Rights, Risk and Other Implications 4.1 Social Implications
There are significant social implications related to the Lydiard Project and these are summarised in the body of this report.
4.2Environmental Implications
There are significant environmental implications related to the Lydiard Project and these are summarised in the body of this report.
4.3Staffing Implications
Any staffing implications arising from the proposed changes will be the subject of appropriate consultation.
4.4Legal/Human Rights Implications
There are no identified legal or human rights implications.
4.5All other Risk Implications
Engineering and other design risks are being addressed as part of the project by specialist engineers. Risk management is addressed as part of the project management plan.
4.6Links to Corporate Plan
The project reflects the Council’s Corporate Plan (Vision and Values) for: i. A Learning and Creative Place ii. An Environmentally Friendly Place iii. An Economically Prosperous Place. 5 Detail
5.1The Stage 1 restoration development work currently being undertaken will underpin the long term strategy for the historic parkland, improving and sustaining the historic and natural environment. The work is supported by The Countryside Agency and English Heritage, both of which are partners in the scheme and regard it as a key national pilot project and exemplar.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.