Resolved – (1) That the report be noted. (2) That the representatives of the Audit Commission and RSM Robson Rhodes be thanked for attending the meeting and for their useful and informative presentation of the detail of the Audit and Inspection Plan and the work that was proposed to be undertaken in 2006/07.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Audit 2006-2007 External audit is an essential element in the process of accountability for public money and makes an important contribution to the stewardship of public resources and the corporate governance of public services. Audit in the public sector is underpinned by three fundamental principles: • auditors are appointed independently from the bodies being audited; • the scope of auditors' work is extended to cover not only the audit of financial statements but also value for money and the conduct of public business; and • auditors may report aspects of their work widely to the public and other key stakeholders. The duties and powers of auditors appointed by the Audit Commission are set out in the Audit Commission Act 1998 and the Local Government Act 1999 and the Commission's statutory Code of Audit Practice. Under the Code of Audit Practice, appointed auditors are also required to comply with the current professional standards issued by the independent Auditing Practices Board. Appointed auditors act quite separately from the Commission and in meeting their statutory responsibilities are required to exercise their professional judgement independently of both the Commission and the audited body.
Status of our reports to the Council The Statement of Responsibilities of Auditors and Audited Bodies issued by the Audit Commission explains the respective responsibilities of auditors and of the audited body. Reports prepared by appointed auditors are addressed to members or officers. They are prepared for the sole use of the audited body. Auditors accept no responsibility to: • any member or officer in their individual capacity; or • any third party. Copies of this report If you require further copies of this report, or a copy in large print, in Braille, on tape, or in a language other than English, please call 0845 056 0566.
Summary of key audit risks 7 Value for money in the Use of Resources conclusion 7 Use of Resources judgement 8 Performance information 9 Best value performance plan 9 Financial statements 9 Whole of government accounts 11
Certification of claims and returns 12
Voluntary improvement work 13
Other information 14 Outputs from the audit and inspection plan 14 The team 14
Future audit plans 15
Appendix 1 – Audit and inspection fee 16 Specific audit risk factors 17 Assumptions 17 Process for agreeing any changes in audit fees 18
Appendix 2 – Criteria to inform the auditor’s conclusion on proper arrangements for securing economy, efficiency and effectiveness in the use of resources 19
Appendix 3 – Planned outputs 21
Appendix 4 - The Audit Commission’s requirements in respect of independence and objectivity 23 Audit and Inspection Plan │ Introduction 4
Introduction 1 This plan sets out the audit and inspection work that we propose to undertake in 2006/07. The plan has been drawn up from our risk-based approach to audit planning and the requirements of the new Comprehensive Performance Assessment CPA – the Harder Test. It reflects: • our responsibilities under the Code of Audit Practice; • audit and inspection work specified by the Audit Commission for 2006/07; • your local risks and improvement priorities; and • current national risks relevant to your local circumstances. 2 Your relationship manager will continue to help ensure further integration and co-ordination with the work of other inspectorates.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Risk Management UpdateThat (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a furth...
Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.