Corporate Risk Management Update

Decided Finance 2 papers

AI summaryAudit Committee endorses Swindon's Corporate Risk Register with 22 open risks, and asks for a further report in six months.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedApproach and escalated risks in Corporate Risk Register endorsed
MoneyNot stated
What happens nextFurther report in 6 monthsAudit Committee to receive another risk update
Who it affectsCouncil-wideAll directorates and services across the council

What was decided

The Audit Committee endorsed the risk management approach and the risks escalated in the Corporate Risk Register. Report 2.1

The Committee asked for a further risk management report in six months' time.

Why

Financial sustainability remains the highest-rated risk at 25, with related pressures in Children's services and transformation savings. Report 3.8, P13

Several IT, systems and data quality risks affect the council's ability to manage services and frontline support. Report 3.9, P19

Statutory requirement risks persist around the 20-week Education, Health and Care Plan target and tenant safety compliance. Report 3.10, P13

What happens next

Officers will bring a further risk management update to the Audit Committee in six months.

Future reports will be amended once the new Risk Management Policy approved by Cabinet on 4 March 2026 is embedded. Report 3.11

Options considered

  • Rejected: Alternative options. The report states alternative options are not applicable. Report 4.1

Implications

  • Legal: Sound risk management arrangements are a statutory requirement under the Accounts and Audit Regulations 2015. Report 5.2, P26
  • Financial: Costs of risk management activity are funded from existing council budgets. Report 5.1, P24
  • Climate: Any corporate climate change risks are included within the Corporate Risk Register. Report 5.3, P28
  • Equalities: No equalities impact assessment completed, as the report proposes no service changes; service-level assessments can be carried out where needed. Report 5.2, P32

Who and where

  • All Swindon Borough Council services, with risks owned by Directors Report 3.2
  • Vulnerable residents reliant on the Homeline response service Report P15
  • Children and young people with Education, Health and Care Plans and SEND needs Report P13, P15
  • Council tenants (safety, disrepair, damp and mould) Report P13, P15

Timeline

  • 4 March 2026: New Risk Management Policy approved by Cabinet Report 3.11
  • 30 April 2026: End of quarter four, basis of the Corporate Risk Register snapshot Report 3.1
  • 23 June 2026: Audit Committee considered the Corporate Risk Management Update
  • Six months from the meeting: Further risk management report to be brought back to the Audit Committee

Plain English for the jargon

  • EHCP: Education, Health and Care Plan, a statutory plan for children and young people with special educational needs and disabilities.
  • DSG HNB: Dedicated Schools Grant High Needs Block, funding for SEND and high needs pupils.
  • NEC Housing Management Operating system: The council's housing management IT system.
  • AMHP: Approved Mental Health Practitioner, a role in the Emergency Duty Service.
  • SEND: Special Educational Needs and Disabilities.
  • SBC: Swindon Borough Council.
  • OFSTED: Office for Standards in Education, the schools and children's services inspectorate.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

That (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a further report be brought to the committee in 6 months time .
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Audit Committee, 5 pages

Recommendations

The Committee is recommended to:

2.1Review and endorse the risk management approach and the risks escalated in the Corporate Risk Register.

3. Detail

Risk register escalations: May 2026

3.1Over the last six months, there have been regular amendments to risks within the Corporate Risk Register. Appendix one provides the full detail from the Corporate Risk Register as at the end of quarter four, 30 April 2026 and is the basis of the summary for this report.

3.2Corporate risks are escalated based on risks identified at Directorate and service level and reviewed by the Corporate Management Team. The Corporate Risk Register focuses on the most significant strategic risks, particularly where there is a risk of council-wide impact. All risks are owned by a Director which reinforces accountability for risk.

3.3There is close alignment between Internal Audit and risk management where the risk registers inform audits conducted. Audit findings are then captured in service risk registers where there are risks identified and escalated to the Corporate Risk Register where the risk is significant.

Further information on the subject of this report can be obtained from Katie Flint, Head of Policy, Performance and Insights, [email protected] Corporate Risk Management Update Audit Committee Date: 23 June 2026

3.4Table 1 shows each risk in the Corporate Risk Register and its revised risk rating after mitigations. Appendix one provides more detail on each risk including mitigations and actions, and changes in risk rating over time. Table 1 also shows any change since the last report (November 2025), including closed risks and new risks.

3.5Risks are scored based on their likelihood and impact, resulting in a scoring thresholds: 1-3 low risk, 4-6 moderate risk, 8-12 high risk and 15-25 extreme risk.

3.6Table 1 shows 22 risks open on the Corporate Risk Register. This includes one newly escalated risk. Three risks have been deescalated from the Corporate Risk Register since the last report, to be managed at directorate level.

3.7Table 1: Corporate Risk Register ratings

October 2025 April 2026 Change since Risk Title Revised Risk Revised Risk last report Rating Rating Financial Sustainability 25 25 0 Timeliness against 20-week performance for 25 20 0 EHCP's Failure to implement the NEC Housing 20 20 0 Management Operating system Lack of management information due to 20 20 0 systems and reporting Dedicated Schools Grant (DSG) High Needs 16 20 +4 Block (HNB) Failure to comply with statutory 12 16 +4 requirements for tenant safety Ineffective Case Management Systems – 20 16 -5 system configuration Council cannot transform at appropriate pace leading to the Council becoming 16 16 0 financially unviable Non-delivery of statutory duties relating to 16 Closed De-escalated Early Years and Childcare Audit of concern: Building Statutory 16 16 0 Compliance (Corporate) Synergy system for education (Lack of 16 Closed De-escalated effective system implementation) Failure to deliver the required improvements for Children's Services 16 16 0 demonstrated in July 2023 OFSTED rating of inadequate

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Overview of Corporate Risk Register Apr-26Appendix 1 32 pages Download
PDF
Corporate Risk Management UpdateReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Corporate Risk Management UpdateThis decision
  2. Corporate Risk RegisterDecided
  3. Corporate Risk RegisterDecided
  4. Corporate risk registerDecided
  5. Corporate Risk Register ReviewDecided
  6. Corporate Risk Management UpdateDecided

More from Swindon Audit Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 MinutesThat the minutes of the previous meeting held on 17 March 2026 be confirmed as true record and signed by the Chairman Decided Open
23 Jun 2026 Audit Committee Annual ReportThat the report be noted Noted Open
23 Jun 2026 Head of Internal Audit Annual Report 2025/26 and OpinionThat the report be noted Noted Open
23 Jun 2026 Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib... Approved Open
23 Jun 2026 Treasury Management Performance 2025/26That, (i) The Treasury Management Performance Plan 2025/26 (Appendix 1) be noted, (ii) The Prudential Indicators (App... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies