Resolved – (1) That the proposed additions to and drawings from the Corporate Contingency Fund recommended by the Council’s Corporate Board, as set out in Table 1 to the joint report, and the virements set out in Appendix 3 to that report, be approved. (2) That the current projected outturn for Revenue, as set out in Table 2 to the joint report, and the forecast level of General Reserves as at 31 st March 2009, be noted. (3) That the freeze on non-essential expenditure, introduced by the Council’s Corporate Board, in order to help reduce expenditure back to the budgeted level, be endorsed, and the measures being put in place to monitor its effectiveness be supported. The reasons for the decision and any alternative options considered are as set out in the report to ... view the full minutes text for item 79. (CM: NM)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Resources and Director of Finance
Purpose • This report presents the 2008/09 Revenue forecast out-turn at the end of October 2008 including activity data for high-risk Budget areas.
Recommendation That Cabinet: • Agrees the proposed additions to and drawings from the Corporate Contingency Fund recommended by Corporate Board as set out in Table 1 and the virements set out in Appendix 3; • Notes the current projected outturn for revenue as set out in Table 2 and the forecast level of General Reserves as at 31st March 2009; • Supports the freeze on non-essential expenditure introduced by Corporate Board in order to help reduce expenditure back to the budgeted level and the measures being put in place to monitor its effectiveness.
1 Reasons General Fund Revenue Account 1.1 To update Cabinet on the current forecast position of the Council’s Revenue Budgets. The forecasts are based on data as at the end of October 2008 and include changes since the August monitoring report was reported to Cabinet on 22 October 2008. 2 Detail 2.1 An overspend of £0.510m against the approved budget of £123.478m was predicted when the 2008/09 revenue budget position was last reported to Cabinet at its October meeting. Following that meeting, it became apparent that the impact of the economic downturn was starting to be felt in a number of areas and predicted income shortfalls totalling £1.025m were reported in the September monitoring within Commercial Rents, Planning, Land Charges and Building Control fees plus on the resale of recycled paper and card. 2.2 In the context of a significant increase in the predicted overspend, a detailed review was undertaken of available budgets with a view to supplementing the contingency fund wherever possible to enable funding to be released to help mitigate the pressures being experienced. 2.3 Table 1 below shows the proposed movements through the contingency fund which, if agreed, will reduce the projected
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2008/09
Cabinet Date: 10th December 2008
overspend across the Council by just over £1m, while remaining unallocated sums in the contingency and Transformation Fund would total £596k. However, the Cabinet is reminded that future unforeseen costs may well arise during the next five months; for example there is a high degree of risk around the budgeted £250k dividend from Thamesdown Transport which has been affected by the high fuel prices in the first half of the year. Members are requested to approve the following proposed additions to and drawings from the Fund. Table 1 – Proposed Contingency Fund Movements £’000 Balance on Contingency Fund following October Cabinet 616 Shaw Tip – expected tipping fees resulting from the Capital +200 Project Pay award – removing difference between budgeted provision +300 of 3% and actual award of 2.45% from Group budgets Transformation Fund – release of part of £500k budget +250 provision not yet committed against Updated Contingency Available 1,366 Allocation towards Shaw Tip Leachate Removal Costs (up to -200 level of income realised from tipping)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.