Resolved – (1) That the Corporate Risk Register Status Report be noted, and the actions being taken by the Chief Executive, Group Directors and Directors to mitigate the risks highlighted within the Corporate Risk Register, be endorsed. (2) That the Director of Partnership, Policy and Communications be requested to submit a revised Risk Management Strategy to the Cabinet early in 2009. The reasons for the decision and any alternative options considered are as set out in the report to the meeting. (CM: FF)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Corporate Risk Register Status Report CABINET Date: 10th December 2008
Author: Cabinet Member for Corporate Affairs, and the Director, Policy, Performance and Communications
Parish / Wards Affected: All
Purpose • To present the Cabinet with a report on Swindon Borough Council’s Corporate Risk Register, the risks faced by the Council and the mitigating actions being applied to control them.
Recommendation Cabinet is requested to • Note the Corporate Risk Register Status report and endorse the actions being taken by the Chief Executive, Group Directors and Directors to mitigate the risks highlighted within the Corporate Risk Register. • Note that a revised Risk Management Strategy will be submitted to the Cabinet at its meeting on 21st January 2009.
1. Reasons 1.1 As part of Swindon’s Corporate Governance arrangements the Corporate Board will give the Cabinet a bi-annual status report of the Council’s significant risks that are held on the Corporate Risk Register and managed through the Performance Framework.
1.2This is to ensure that the Council manages risk effectively through its Risk Management Strategy and considers strategic risks affecting the Council’s promises and objectives. Also for the Corporate Board to give personal declarations on Risk Management Assurance to the Cabinet regarding Risk Management compliance.
1.3The risks within the Corporate Risk Register form a significant element of the Annual Governance Statement.
1.4The Council’s Internal Audit Annual Audit Plan is risk based and will therefore be driven by the significant risks identified through the Risk Management process.
2. Detail
2.1During August and September 2008 a new Corporate Risk Register was compiled by Corporate Board and other relevant senior officers reflecting Further information on the subject of this report can be obtained from Alex Bedford on 01793 464354 or Email [email protected]. Corporate Risk Register Status Report CABINET Date: 10th December 2008
the key strategic risks currently seen to be facing Swindon Borough Council. The Chief Executive signed off this register on 22nd September 2008, and Progress against Mitigating Actions was reported on at the Quarterly Business Review in October. 2.2 The Corporate Risk Register is attached as Appendix A. 2.3 The Cabinet are requested to consider and acknowledge the significant risks identified and monitored by Corporate Board, to assure itself that suitable and sufficient mitigation actions are being undertaken to safeguard the Council’s business and reputation, and endorse the Corporate Risk Register. 2.4 The Risk Management Strategy is in the process of being refreshed and will be rewritten and brought to the Cabinet at its meeting in January 2009. Alternative Options • Not Applicable
Risk Management Financial and Procurement Implications • None specific to this report. General Risk Management related costs to be absorbed by existing budgets.
Legal / Human Rights Implications • There are no direct legal implications. However, as part of the Accounts and Audit Regulations 2006, it is a statutory requirement that the Council maintains a robust, adequate and effective system of Risk Management in the management of its risks in delivery its core services.
Links to Corporate Plans and Policies (in particular to Swindon 2010 Promises) • The Corporate Risk Register, Risk Management and Performance monitoring are management processes that will help underpin the success of the Corporate Plan, Annual Operating Plan, Policies and Swindon 2010 Promises Consultees • The Director of Finance (Section 151 Officer) and the Director of Law and Democratic Services (Monitoring Officer) are consulted on all reports. • Director of Policy, Performance and Communications • Head of Internal Audit Background Papers and Appendices • Appendix A. Corporate Risk Register (To follow) Key Decision / Decision in Forward Plan • This is a key decision. This item is included in the Cabinet Forward Plan for December 2008.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.