Resolved – (1) That the projected outturn for the Revenue Budget, as set out in Table 1 to the joint report, as at 31 st March 2010, be noted. (2) That the proposed Revenue Virements, as set out in Appendix 3 to the joint report, be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: ME)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance and Benefits and Director of Finance
Purpose This report presents the first Budget Monitoring report for 2009/10 in order that Cabinet is aware of the latest year end forecasts and the work being undertaken to ensure that a balanced budget is delivered at the end of the year.
Recommendation That Cabinet: Notes the current projected outturn set out in Table 1 and supports Corporate Board in the action being put in place to reduce the forecast overspend; Agrees the revenue virements set out in Appendix 3.
1 Reasons General Fund Revenue Account 1.1 To update Cabinet on the current forecast position of the Council’s Revenue Budgets. The forecasts are based on data as at the end of May 2009.
2 Detail 2.1 The General Fund revenue forecast outturn for 2009/10 based on the May monitoring is shown in Table 1 below with a more detailed analysis shown at Appendix 1. Mitigating actions are already being identified and implemented to ensure that the out-turn from the current year does not have a negative impact on the 2010/11 budget.
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2009/10
Cabinet Date: 22nd July 2009
Table 1: General Fund Forecast Budget Forecast Forecast Movement 2009/10 Outturn Over/ Since Underspend February Cabinet £’000 £’000 £’000 £’000 Children Services 28,115 28,792 677 677 Housing & Social Care 46,847 48,214 1,367 1,367 Environment & 32,124 32,798 674 674 Regeneration Business Transformation 18,466 18,966 500 500 Swindon Commercial -1,936 -1,861 75 75 Services Chief Executive & 4,270 4,270 0 0 Corporate Sub Total 127,886 131,179 3,293 3,293 General Contingency 1,420 1,420 0 0 Fund Total 129,306 132,599 3,293 3,293
2.2It is clear that the impact of the recession is continuing to put significant strain on the Council’s finances with dramatically increased workloads within the Benefits service and further losses of income within services over and above that allowed for within the 2009/10 Budget. In addition, a number of savings initiatives are proving difficult to implement in the timescales originally envisaged, These issues are set out in more detailed in Appendix 2, along with mitigating actions being progressed by individual Group Directorates to bring their budgets back into balance. Members should note that the figures in Table 1 exclude the impact of funding the costs of Single Status (project costs and pay protection) which are still being evaluated, some provision for which has been made in closing the 2008/09 accounts. 2.3 Although challenging, it should be noted that the position in Swindon is not dissimilar to that being faced in other unitary authorities across the country, with some predicting potential overspends at this early stage in the year of an even greater magnitude. 2.4 However, due to the scale of the potential overspend (£1.873m if the contingency is called upon to support the current issues being reported rather than held against other as yet unknown risks), Corporate Board has already approved a number of actions to drive down the net expenditure of the Council as follows:-
Further information on the subject of this report can be obtained from Kirsty Cole on Direct Dial No. 464610 or Email [email protected] Revenue Budget Management 2009/10
Cabinet Date: 22nd July 2009
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.