Resolved – That the process of bidding for Government funding to build new Council housing in Swindon be approved, and the Group Director, Housing and Social Care, be authorised in consultation with the Cabinet Member for Health, Housing and Adult Social Care, to: (a) Apply to become approved recipients of Homes and Community Agency grant through the Pre-Qualification Questionnaire process; (b) Appoint NPS as development partners on the scheme as an exception to Standing Orders but below OJEU limits; (c) Bid on the basis of level 5 of the Code for Sustainable Homes to maximise the chances of being successful in the bidding process; (d) Use up to £829,245 of Section 106 monies as matched funding for the bid, as referred to in the joint report, or prudential borrowing supported by the expected income stream if the former approach is not permitted by the Homes and Communities Agency ; (e) Note the consultation processes with local Members and residents on the Lyndhurst Crescent former depot site in Park North, Swindon; (f) Ensure Best Value is achieved for the Council, by way of challenging on the cost, design and use of sustainable technology for the overall project delivery. The reasons for the decision and any alternative options considered are as set out in the report to the meeting.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Building New Low Carbon Council Housing CABINET Date: 22 July 2009
Author: Cabinet Member for Health, Housing and Adult Social Care and Director of Housing and Leisure
Parish / Wards Affected: PARS
Purpose To seek approval for submitting a bid to the Homes and Community Agency (HCA) for funding to support the building of up to 12 new low carbon homes at Lyndhurst Crescent, Park North, Swindon.
Recommendation Cabinet is requested to : Approve the process of bidding for Government funding to build new Council housing in Swindon, and to authorise the Group Director, Housing and Social Care, in consultation with the Cabinet Lead Member for Health, Housing and Adult Social Care to: a) Apply to become approved recipients of HCA grant through the Pre- Qualification Questionnaire process. b) Appoint NPS as development partners on the scheme as an exception to standing orders but below OJEU limits. c) Bid on the basis of level 5 of the Code for Sustainable Homes to maximise the chances of being successful in the bidding process d) To use up to £829,245 of s106 monies as matched funding for the bid e) note the consultation processes with local Members and residents on the Lyndhurst Crescent former depot site in Park North.
1. Reasons 1.1 To seek approval for bidding for HCA funding to develop new Council housing in Swindon.
2. Detail 2.1 Swindon Borough Council owns over 10,000 properties in the Borough but has not built new housing in significant numbers since the mid 1980s. This was due to changes in financial rules that made it very difficult for local authorities to arrange the necessary credit finance for building the homes and have sufficient unencumbered income from the rental stream to service such loans due to the national Housing Revenue Account (HRA) subsidy system.
Further information on the subject of this report can be obtained from Alan Wylde on 464356 or Email [email protected]. Building New Low Carbon Council Housing CABINET Date: 22 July 2009
2.2In the 2009 Budget on April 22nd, the Chancellor announced a £100m funding stream to be made available to local authorities to allow them to build highly environmentally sustainable Council housing once more. The funding was split into £50m for direct grant and £50m prudential borrowing carried out by the Council itself and was hoped to achieve 900 homes nationally. The bidding guidance has set out the intention that all homes constructed through this scheme will be outside the HRA subsidy system but will be subject to Right to Buy. An internal working group involving Property, Planning (inc Highways), Lettings, Housing Management, Housing Finance and Enabling was set up to explore this opportunity further. The Housing Enabling team will act as project managers due to the nature of the work involved. On June 29th a further £250m was announced in addition for the same programme.
2.3The process requires the local authority to obtain approval to become a grant recipient with the HCA through the completion of its Pre-Qualification Questionnaire Process which examines all aspects of the organisations performance with regard to developing and managing affordable housing.
2.4Due to the period of time that has passed since last the Council developed significant numbers of Council housing, the skills required to manage the development process are lacking especially when the requirement for a high level of the Code for Sustainable Homes is taken into account.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.