Resolved - (1) That the report and the detail of the presentation by the Head of Performance and Risk be noted. (2) That the detail of the Corporate Risk Register be accepted and that Members be invited to advise the Head of Performance and Risk outside the meeting of any significant risk areas that they feel have been overlooked. (3) That, in support of each function to review the Corporate Risk Register and the Council's management of risk, the Committee agreed that the individual "owners of risk" be invited to attend future meetings of the Committee to make a brief presentation and to discuss with Members the role of the particular department and how they link with the mitigation of risk. (4) That, with reference to (3) above, the Council's Emergency Planning Officer be invited to attend the next meeting of the Committee to discuss identified risks within his area of responsibility. (5) That copies of Risk Management Guidance Sheet for Managers be made available to Members of the Audit Committee and the Performance Advisory Group for information.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Head of Performance and Risk Wards Affected: All
Purpose To present Audit Committee with a summary report on Risk Management activity within Swindon Borough Council
Recommendation It is recommended that the contents of this report be noted It is recommended that Audit Committee discuss the Corporate Risk Register
1. Reasons 1.1 Audit Committee provides independent assurance to the Council on the effectiveness of the Council’s Risk Management, Internal Control and its overall assurance framework.
2. Detail
2.1Risk Management Strategy
2.1.1 The Risk Management Strategy has been refreshed and reviewed and is attached as Appendix 1. Feedback to date has been extremely positive.
2.1.2 The Corporate Risk Management Group has met a number of times during 2009 and is fulfilling a more strategic role in the embedding and dissemination of risk management across the Council. Two key deliverables from the Group have been a detailed analysis of the Corporate Risk Register with recommendations presented to Corporate Board and approval for the setting up of an Information Security Forum to help the Council address the risks around this area in a more joined up manner.
2.1.3 Risk management training has been carried out with Audit Committee, new Cabinet members and the Customer Services and Housing Directorate Management Teams. A series of Lunch and Learn training sessions for project personnel are also being run in conjunction with the Project Management Office with the next session to take on place on 23rd September already at capacity.
Further information on the subject of this report can be obtained from Alex Bedford 01793 464354 or Email [email protected] Risk Management Status Update
Audit Committee Date: 22nd September 2009
2.1.4 A Brief Guide to Risk Management at Swindon Borough Council has been produced. This is included in the Induction packs discussed at the corporate Induction days and is also given out at all training courses. The format and usability of the Guide has been very well received.
2.1.5 The Risk Management Intranet pages are in the process of being updated to ensure that clear and consistent information is available to all officers and members. A Risk Management Sharepoint site has also been developed and we will be working with Groups over the coming months to ensure this is populated with all relevant risk registers.
2.2Risk Registers
2.2.1 The Corporate Risk Register has continued to be regularly updated both formally through the Performance Framework and on other occasions as circumstances have changed and the need arisen.
2.2.2 Corporate Board considers the Corporate Risk Register formally at each Quarterly Business Review, the most recent of which took place at the end of July 2009. The Register is also discussed at meetings of the Corporate Risk Management Group and recommendations for improvement put forward to Corporate Board. Each review looks at whether mitigating actions are appropriate and robust and these are monitored and updated to ensure that risks are being responded to as effectively as possible. The Register is also updated when the need arises, for example with the onset on the swine flu pandemic a risk was added to the Register to reflect this.
2.2.3 The current Corporate Risk Register was endorsed by Cabinet on 9th September 2009 and reflects the key strategic risks currently seen to be facing Swindon Borough Council. The Register is attached at Appendix 2.
2.2.4 Group Directorates, Service Areas and Projects continue to update Risk Registers in line with the Council’s risk management strategy. The Head of Performance and Risk has advised key strategic projects on their risks including Single Status, Benefits, Wichelstowe and the Transformation Programme including New Ways of Working.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Risk Management UpdateThat (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a furth...
Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.