Resolved
Resolved – That the Committee thank the External Auditors for attending the meeting and note the as at November 2009.
Audit Committee noted this item on Tuesday 24 November 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the Committee thank the External Auditors for attending the meeting and note the as at November 2009.
Progress Report - November 20099 1
Progress Report - November 2009 Swindon BC
Audit 2009/1010
Swindon BC 2 Progress Report - November 20099
- Audit Commission descriptor to be inserted by Publishing-
Document Control
Author Peter Smith
Filename Progress report Nov 2009.doc
Status of our reports The Statement of Responsibilities of Auditors and Audited Bodies issued by the Audit Commission explains the respective responsibilities of auditors and of the audited body. Reports prepared by appointed auditors are addressed to non-executive directors/members or officers. They are prepared for the sole use of the audited body. Auditors accept no responsibility to: any director/member or officer in their individual capacity; or any third party.
Copies of this report If you require further copies of this report, or a copy in large print, in Braille, on tape, or in a language other than English, please call 0845 056 0566.
.
Swindon BC Progress Report - November 20099 │ 3
Audit progress summary
Area of work Audit Plan Date Lead Officers Date Comment reporting date reported reported to to Officers Audit Committee
2009/10
Audit fees letter April 2009 April 2009 AC Peter Smith June 2009 Fee letter sent to Chief Executive in April.
Interim audit April 2010 SBC Darren Stevens/ System walkthroughs are being Nick Hobbs undertaken at present to be (if required) AC Paul Benfield completed by Christmas. Controls testing to be undertaken in March. This is to enable us to place reliance on Internal Audits work. Significant control issues will be reported on an exception basis in April 2010. If no material issues are identified a summary of findings will be reported within the ISA 260 governance report.
Connecting People June 2010 Set up work is planned for January 2010, with on site work expected to
Swindon BC 4 Progress Report - November 2009 │
connecting places be in March 2010.
Use of Resources July 2010 SBC Stewart Mckellar Planning and initial documentation AC Peter Smith has been started, with discussions with officers planned for February to April 2010. Indicative scores will be submitted to the Audit Commission by 21st April 2010 with final submission for Quality Review process being the 30th July 2010.
Opinion fee review May 2010 SBC Gavin Jones Not yet started AC Peter Smith
Opinion September 2010 SBC Stewart Mckellar Not yet started AC Peter Smith Post statements audit testing to be undertaken in July - August 2010 Audit Committee date for approval of accounts has not yet been agreed.
VFM Conclusion September 2010 SBC Stewart Mckellar Not yet started AC Peter Smith
Annual Audit Letter November 2010 SBC Stewart Mckellra Not yet started AC Peter Smith
Swindon BC Progress Report - November 20099 │ 5
2010/11
Audit Plan March 2010 SBC Gavin Jones Work is underway. to review the AC Peter Smith Council's internal risk registers to identify any significant changes to business risks affecting our Code responsibilities.
Swindon BC
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
External Audit Progress ReportReport | 5 pages | DownloadRead as text |
Follow Audit Committee at Swindon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jun 2026 | MinutesThat the minutes of the previous meeting held on 17 March 2026 be confirmed as true record and signed by the Chairman | Decided | Open |
| 23 Jun 2026 | Corporate Risk Management UpdateThat (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a furth... | Decided | Open |
| 23 Jun 2026 | Audit Committee Annual ReportThat the report be noted | Noted | Open |
| 23 Jun 2026 | Head of Internal Audit Annual Report 2025/26 and OpinionThat the report be noted | Noted | Open |
| 23 Jun 2026 | Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.