Resolved – That the revised build budget of £1.685m for the Hawthorns Short Breaks Scheme, be approved, with the Council's contribution of £1.264m to be met initially from borrowing, such borrowing to be repaid from the capital receipt realised from a future disposal of surplus land on the Hawthorns site. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: BM)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
SHORT BREAKS – HAWTHORNS SCHEME CABINET Date: 9th June 2010
Author: Cabinet Member for Housing, Community and Partnerships, Cabinet Member for Health and Adult Social Care and Director of Housing and Leisure
Parish / Wards Affected: Gorse Hill and Pinehurst.
Purpose
• To clarify the funding arrangements for the scheme in order that works can commence.
Recommendation Cabinet is requested to:
Approve the revised build budget of £1.685M, with the Council's contribution of £1.264M to be met initially from borrowing, such borrowing to be repaid from the capital receipt realised from a future disposal of surplus land on the Hawthorns site.
1. Reasons 1.1 The current short breaks sites at Oak House and Elsie Millin are no longer fit for purpose. The Care Quality Commission (CQC) have continued to support the registration of the current facilities on the understanding that the new provision of new accommodation is progressing.
1.2The project supports the Council’s objectives for Promise 30 to reduce the number of adults requiring long-term institutional care by 20% and Promise 32 to promote greater independence and promote choice for disabled people.
2. Detail 2.1 The Council and Swindon PCT are jointly funding the project on a 75/25% split respectively.
2.2The capital budget for the project agreed in 2008/09 was £1.455M, funded by £1.105M from the Council and £350K from Swindon Primary Care Trust (PCT). The intention was for Sarsen Housing Association (HA) to deliver this project within this budget but in early 2009 they terminated their appointment. The Council element of the budget was to be financed from the proceeds of the sale of surplus land on the Hawthorns site.
Further information on the subject of this report can be obtained from Lila Haracz on 01793 464480 or Email: [email protected] SHORT BREAKS – HAWTHORNS SCHEME CABINET Date: 9th June 2010
At the time the capital receipt was estimated at £2.3M. This receipt has not yet been realised but is still in the Council's disposals programme, at the reduced estimated value of £1.5M. The Council's contribution to the build budget would therefore need to be funded by borrowing until the receipt is realised.
2.3In autumn 2009 soft market testing indicated that the original budget for construction was no longer achievable and that a more realistic estimate would be around £1.685M. In order for this project to be delivered the shortfall needs to be found.
2.4It has been agreed, between the Council and PCT, that the shortfall in budget for the project will be shared on a 75/25% basis.
• SBC £1.685M x 75% = £1.264M less £1.1 05M (funding agreed in 2008/09) = £159K
• PCT £1.685M x 25% = £421K less £350k (funding agreed in 2008/09) = £71k
2.5The Council has identified its portion of the shortfall, £159k, from reprioritising some of the corporate resources from the Taw Hill Scheme that is no longer progressing. Swindon PCT have identified their portion of the shortfall, £71k, from capital funding earmarked for joint projects and paid to the Council in March 2009.
2.6A separate report on the agenda confirms that the property construction contract for the Hawthorns scheme has been included in the contract signed with Swindon Commercial Services Limited (SCS). SCS have agreed that this project is commissioned on an ‘open book’ basis, meaning that all detailed costings will be subject to close scrutiny by the Project Board and the Employer’s Agent.
Alternative Options If the new Hawthorns Scheme does not progress it is likely that the Care Quality Commission will serve notice to close down the existing facilities. This would be detrimental to the service users as an alternative provision would need to be found which is highly unlikely at short notice.
Further information on the subject of this report can be obtained from Lila Haracz on 01793 464480 or Email: [email protected] SHORT BREAKS – HAWTHORNS SCHEME CABINET Date: 9th June 2010
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.