Resolved – (1) That the inclusion of a total of twenty seven new Council homes in the Capital Programme, be approved, with a budget of £3,520,918 with £1,760,459 of Homes and Communities Agency grant funding and the balance being funded by debt wholly serviced by the net rental streams of the homes. (2) That the Director of Housing and Leisure be authorised to deliver the homes at locations at: · Marlowe Avenue, · Beech Avenue, and · one further site to be identified by the Director of Housing and Leisure, in consultation with the Cabinet Member for Housing, Community and Partnerships. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: DR)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Marlowe Avenue Capital Programme CABINET Date: 9 June 2010
Author: Cabinet Member for Housing, Community Partnerships and the Group Director, Housing and Social Care
Parish / Wards Affected: Walcot
Purpose
To seek formal approval for the project to deliver new Council homes at Marlowe Avenue, Beech Avenue and one other site to be identified.
Recommendation Cabinet is requested to 1. Approve the inclusion of a total of 27 new Council homes in the capital programme with a budget of £3,520,918 with £1,760,459 of Homes and Communities Agency grant funding and the balance funded by debt wholly serviced by the net rental streams of the homes 2. Authorise the Director of Housing and Leisure to deliver the homes at locations at: • Marlowe Avenue, • Beech Avenue, and • one further site to be identified by the Director of Housing and Leisure, in consultation with the Cabinet Member for Housing, Community and Partnerships.
1. Reasons 1.1 To formally include a total of 27 new Council homes at Marlowe Avenue, Beech Avenue and one other site to be identified in the Council’s capital programme.
2. Detail 2.1 Housing bid in the Homes and Communities Agency (HCA) Local Authority New Build bid round in October 2009 to construct 27 Council homes at Marlowe Avenue and Beech Avenue at Code for Sustainable Homes Level 4. In February, the Council discovered that the bid had been successful and are now in the process of working towards a successful planning application and starts on site in late summer 2010.
2.2The 27 homes were intended to be split between 25 homes at Marlowe Avenue on the retail site that is due to be demolished and 2 homes at Beech Avenue as a replacement for the homes that were demolished to
Further information on the subject of this report can be obtained from Alan Wylde on 01793 464356 or Email [email protected]. Marlowe Avenue Capital Programme CABINET Date: 9 June 2010
allow access for construction traffic for the Academy which should be no longer required by Autumn 2010.
2.3It became clear during the planning process that it would not be possible to include 25 homes on the Marlowe Avenue site as per the original outline planning permission and only 23 are currently planned. Housing are examining other Housing Revenue Account (HRA) sites to assess their potential to accommodate the 2 homes it was not possible to include on Marlowe Avenue. This site will be the subject of a Cabinet Member Briefing Note following consultation with the local community.
2.4A separate report on the agenda confirms that the property construction contract for the Marlowe Avenue and Beech Avenue schemes has been included in the contract signed with Swindon Commercial Services Limited (SCS). SCS have agreed that this project is commissioned on an ‘open book’ basis, meaning that all detailed costings will be subject to close scrutiny by the Project Board and the Employer’s Agent.
Alternative Options To not include the project on the capital programme and return the grant to the HCA.
Risk Management Financial and Procurement Implications • The Council received an allocation of £1,760,459 from the HCA for the 27 homes which will be match funded from HRA borrowing that is fully serviced by net rental income. • The income from the new homes generates a surplus for the HRA from the beginning of the scheme but does not take into account the loss of revenue from the rents received from the flats, shops and garages currently on the site which is approximately £67,500 per year
Legal / Human Rights Implications The content of the report does not give rise to any specific legal implications and it is not anticipated that there are any direct implications for human rights that need to be considered.
Links to Corporate Plans and Policies (in particular to Swindon 2010 Promises) • Promise 42 – We will provide an additional 300 affordable homes per year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.