Resolved – (1) That the Motion put forward at the Council meeting on the 11 th November 2010 seeking a review of signalised junctions, be noted. (2) That the issues associated with a review of the ongoing provision of traffic signalised junctions and signalised pedestrian crossings in Swindon, as referred to in the joint report, be noted. (3) That the Director of Planning and Transport be authorised to undertake a phased review of a selected number of traffic signal sites as part of the development of Local Transport Plan 3 (LTP3), and it be noted that this would comprise - Review of existing trials; Stage 1 Review, as set out in Appendix C to the joint report; and · Stage 2 Review as set out in Appendix C to the joint report. (4) That Cabinet Member for Sustainability, Strategic Planning, Property and Transport, in consultation with the Director of Planning and Transport, be authorised to determine the expediency of moving from one stage of the review process to the next. (5) That the Council be advised of the contents of the joint report and of the recommendations set out in (1) to (4) above in response to the Council Motion of 11 th November 2010. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: DR)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
REVIEW OF TRAFFIC SIGNALS (JUNCTIONS AND PEDESTRIAN CROSSINGS) CABINET Date: 20 April 2011
Author: Cabinet Member for Sustainability, Strategic Planning, Property and Transport, the Deputy Chief Executive and Group Director, Environment, Regeneration and Community
Parish / Wards Affected: All
Purpose
To advise the Cabinet of the issues associated with undertaking a review of the ongoing provision of traffic signalised junctions and signalised pedestrian crossings in Swindon, and to respond to the Motion at Council on 11th November 2010 on this issue.
Recommendation That Cabinet is requested to:
• Note the Motion put forward at the Council meeting on the 11th November 2010
"That this Council commences a review of all signalised junctions with a view of taking signals away wherever it is safe to do so and gives positive improvements in traffic flow and inherent cost savings".
• Note the issues associated with a review of the ongoing provision of traffic signalised junctions and signalised pedestrian crossings in Swindon.
• Authorise the Director of Planning and Transport to undertake a phased review of a selected number of traffic signal sites as part of the development of Local Transport Plan 3 (LTP3). This would comprise i) Review of existing trials ii) Stage 1 Review as set out in Appendix C iii) Stage 2 Review as set out in Appendix C.
• The Cabinet Member for Sustainability, Strategic Planning, Property and Transport, be authorised, in consultation with the Director of Planning and Transport, to determine the expediency of moving from one stage of the review process to the next.
• Advise the Council of the recommendations set out above in response to the Council Motion of 11th November 2010.
Further information on the subject of this report can be obtained from Robert Sanders on 466391 or Email [email protected]. REVIEW OF TRAFFIC SIGNALS (JUNCTIONS AND PEDESTRIAN CROSSINGS) CABINET Date: 20 April 2011
1. Reasons
1.1At the Council meeting on the 11th November 2010 the following Motion was put forward:
"That this Council commences a review of all signalised junctions with a view of taking signals away wherever it is safe to do so and gives positive improvements in traffic flow and inherent cost savings". (Minute 73 (d) refers).
1.2The item, which was moved by Councillor Stan Pajak and seconded by Councillor Jim Grant, stood deferred to Cabinet without discussion in accordance with Standing Order 9(1) due to its financial implications for the Council.
2. Details
2.1The highway network within Swindon is our largest and most valuable asset and is made up of a number of features including -
• 820 kilometres of road. • 1600 kilometres of footway and cycletrack. • 400 bridges and culverts. • 66 traffic signal controlled junctions (including two signalised roundabouts), with five more sites already planned to come into operation soon in Wichelstow. • 153 traffic signal controlled pedestrian and cyclist crossings. (Some of these crossings form part of traffic signal controlled junctions and some are staggered crossings).
2.2A plan showing the location of the traffic signal controlled junctions and the traffic signal controlled pedestrian and cyclist crossings is attached as Appendix A.
2.3All of these traffic signals operate continually on a 24-hour basis and the Council’s Traffic Signal Maintenance Budget for the 2010/11 Financial Year was set at £192,800 and the 2010/11 budget for the traffic signal energy costs is £77,100.
Why do we use traffic signals?
2.4The traffic signals in use in Swindon have been installed as a form of traffic management for variety of reasons including:
Further information on the subject of this report can be obtained from Robert Sanders on 466391 or Email [email protected]. REVIEW OF TRAFFIC SIGNALS (JUNCTIONS AND PEDESTRIAN CROSSINGS) CABINET Date: 20 April 2011
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.