Resolved

Resolved – (1) That it be reaffirmed that there are no plans to conduct street light switch-off trials in the future. (2) That, in recognition of the benefits of the reduced off-peak delays to traffic and public support for the scheme, the part-time operation of the traffic signals at Mannington, Swindon, continues but it remain on a trial basis until a full 12 month review of driver behaviour is available for analysis in March 2013. (3) That it be noted that the Traffic Signal Review Stage 1 of all roundabouts, junctions and pedestrian crossings controlled by traffic signals in Swindon is now complete and that future decisions on individual signal installations arising from the Review will be undertaken through the agreed Local Transport Plan (LTP3) Implementation Plan process. (4) That, subject to approval by the Department for Transport, the Head of Highways and Transport be authorised to undertake a trial of Pedestrian Countdown Timers in Swindon. (5) That it be noted that work on Bruce Street Bridges and the Meads Roundabouts, Swindon, to improve junction efficiency and reduce delays has been prioritised within the Local Transport Plan (LTP3). (6) That the Council be advised of the recommendations set out above in response to the Council Motion of the 23rd February 2012. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: ME)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 5 pages

Street Lighting and Traffic Signals Review Cabinet Date: 5 September 2012

Author: Cabinet Member for Leisure and Strategic Transport Head of Highways and Transport Wards: All Wards Locality Affected: All Locality Areas Parishes Affected: All Parish Areas

1. Purpose and Reasons 1.1 This report has been prepared in response to a Motion (113) approved at Council on the 23rd of February 2012. “This Council welcomes the decision by the Administration to end the streetlight switch off trial scheme. This Council believes that this decision is a reflection of the Administration's willingness to listen to and engage with ward members and the general public. This Council requests that the Cabinet Member for Council Transformation, Sustainability, Strategic Planning and Transport note the success of making the traffic lights at Mannington roundabout only operate part time and develop a programme to convert other traffic lights at similar junctions. This programme should be presented to Cabinet within 6 months.” 1.2 This report is also provides an update on the Traffic Signal Review originally approved by Cabinet in April 2011. 2. Recommendations Cabinet is recommended to: 2.1 Reaffirm that there are no plans to conduct street light switch-off trials in the future. 2.2 Agree that in recognition of the benefits of the reduced off-peak delays to traffic and public support for the scheme, the part-time operation of the traffic signals at Mannington should continue but still on a trial basis until a full 12 month review of driver behaviour is available for analysis in March 2013. 2.3 Note that the Traffic Signal Review Stage 1 of all roundabouts, junctions and pedestrian crossings controlled by traffic signals in Swindon is now complete and that future decisions on individual signal installations arising from the review will be undertaken through the Local Transport Plan (LTP3) implementation Plan process.

Further information on the subject of this report can be obtained from Robert Sanders 466391, [email protected]. Street Lighting and Traffic Signals Review Cabinet Date: 5 September 2012

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Street Lighting and Traffic Signals Review (Minute for Confirmation)Report 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
RB
Councillor Roderick Bluh Leader of the Council, Chair of CabinetChair, present
DR
Councillor David Renard Deputy Leader, Vice-Chair and Cabinet Member for Children's ServicesVice-Chair, present
ME
Councillor Mark Edwards Cabinet Member for FinanceMember, apologies
FF
Councillor Fionuala Foley CLMember, present
DH
Councillor Dale Heenan Cabinet Member for Strategic Planning and SustainabilityMember, present
RH
Councillor Russell Holland Cabinet Member for One Swindon, Localities and HousingMember, present
BM
Councillor Brian Mattock Cabinet Member for Health and Adult Social CareMember, present
GP
Councillor Garry Perkins Cabinet Member for Regeneration and CultureMember, present
VT
Councillor Vera Tomlinson Cabinet Member for a Safer, Stronger BoroughMember, present
KW
Councillor Keith Williams Cabinet Member for Leisure and Strategic TransportMember, present
JG
Councillor Jim GrantCabinet Member attendee, in attendance
SW
Councillor Steve WakefieldCabinet Member attendee, in attendance

On this subject at Swindon

Search all
  1. Street Lighting and Traffic Signals Review (Minute for Confirmation)This decision
  2. LED Street Lighting InstallationNoted
  3. LED Street Lighting Conversion ProgrammeNoted
  4. Highways Street Lighting ProposalsNoted
  5. Street LightingDecided

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies