Resolved – (1) That the position of the 2010/11 Capital Programme be noted. (2) That the changes to the Council’s Capital Programme, as detailed in paragraphs 2.8 to 2.17 of the joint report, be noted and approved. (3) That the work being undertaken to improve the financial management of the Council’s Capital Programme, as detailed in paragraph 2.2 of the joint report, be noted. (4) That a budget of £117,000 relating to work at Coate Water Park, as detailed at paragraphs 2.18 to 2.20 of the joint report, be approved. (5) That, the Group Director, Business Transformation be authorised to enter into a joint procurement exercise with Wiltshire Council to improve fast broadband infrastructure in Swindon, as referred to in paragraph 2.21 of the joint report. (6) That, further to the decision in (5) above, the Group Director, Business Transformation be requested to report back to a future meeting of the Cabinet with further details of the proposed scheme and the financial implications for the Council. (7) That, the proposed framework, as set out under paragraph 2.27 of the joint report, against which bids for additional Capital schemes are to be considered by the Council in February 2012, be approved. (8) That the Treasury Management performance from April 2011 to September 2011 as referred to in Section 3 of the joint report, be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: PG)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance and Director of Finance
Parish/ Wards Affected: All
Purpose • To present the latest position on delivery and funding of the Council’s current approved Capital Programme • To provide Cabinet with a summary of mid-year Treasury Management performance for 2011/12 • To agree a framework for consideration of additional capital schemes for inclusion within the 2012/13 + capital programme
Recommendation That Cabinet: • Notes the position of the 2011/12 Capital programme; • Approves the changes to the Capital Programme detailed at paragraphs 2.8 to 2.17; • Notes the work being undertaken to improve financial management of Capital Schemes, set out under paragraph 2.2 ; • Approves a budget of £117k relating to work at Coate Water Park as detailed at paragraphs 2.18 to 2.20; • Authorises the Group Director, Business Transformation to enter into a joint procurement exercise with Wiltshire Council to improve fast broadband infrastructure in Swindon, as referred to in paragraph 2.21 of this report, and requests that he reports back to a future meeting of Cabinet in due course with further details of the proposed scheme and the financial implications; • Approves the framework set out under paragraph 2.27 against which bids for additional schemes will be considered in February 2012; • Notes the Treasury Management performance from April 2011 to September 2011detailed at section 3.
1. Reasons 1.1 To update the Cabinet on the current projected 2011/12 Capital Programme out-turn position. The information provided is as at the end of October 2011.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme & Treasury Management
Cabinet Date: 14th December 2011
1.2To update the Cabinet on changes made to the Capital Programme since it was last brought to Cabinet in September 2011. 1.3 To propose an approach for the consideration of additional schemes to be included in the capital programme in February 2012. 1.4 To update Cabinet on Treasury Management Performance in the first half of the financial year April - September 2011.
2 Detail
CAPITAL PROGRAMME 2011/12
2.1The Capital Programme for 2011/12 is summarised in table 1 below.
Table 1: Capital Expenditure and Forecasts 2011/12
2011/12 Current Projected Actual Budget Forecast Variance to Date Group £'000 £'000 £'000 £'000 Children's Services 19,869 16,040 (3,829) 6,125 Environment & Regeneration 29,079 22,964 (6,115) 7,963 Housing Leisure Libraries & Cult 11,397 11,257 (140) 3,819 Adult Social Care 2,246 2,163 (83) 1,009 Business Transformation 18,819 16,963 (1,856) 7,495 Service Totals 81,410 69,387 (12,023) 26,411
Table 2 below, gives a breakdown of the projected variance by service area:
Table 2: Variance by Service Area Forecast Potential Potential Net Re- Projected Savings Overspends Phasing variance Group £'000 £'000 £'000 £'000 Children's Services (283) 1,573 (5,119) (3,829) Environment & Regeneration (277) 692 (6,530) (6,115) Housing Leisure Libraries & Cult. (25) 15 (130) (140) Adult Social Care (83) - - (83) Business Transformation & Corp. (49) - (1,807) (1,856) Totals (717) 2,280 (13,586) (12,023)
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No. 463976 or Email [email protected] Capital Programme & Treasury Management
Cabinet Date: 14th December 2011
Details of Projected Variance 2.2 The forecast 2011/12 underspend against budget of (£3.829m) for Children’s Services is made up of: 2.2.1 (£283k) of potential savings including: o (£125k) Westlea Primary School – replacement of temporary accommodation; o (£45k) Isambard School technology room; and o (£113k) several smaller savings on various other capital schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.