Resolved

Resolved – That the Council be recommended to: - (a) Note the contents of the joint report, in response to the Motion at the Council meeting on 21 st July 2011, relating to “Sustainable Transport” and that requested the Cabinet Member to “bring a report to the Cabinet outlining in detail how this money will be used for the benefit of Swindon’s residents and what additional funds he is seeking from Government”. (b) Approve the Local Sustainable Transport Fund Programme Budget categories and allocations for 2011/12, as detailed in the Implementation Plan (Appendix 1 to the joint report), for inclusion in the Council’s Revenue Budget and Capital Programme. (c) Authorise the Director of Planning and Transport, in consultation with the Cabinet Member for Council Transformation, Sustainability, Transport and Strategic Planning, to (i) Prioritise schemes in accordance with the parameters set out in the Local Sustainable Transport Fund bid document; (ii) Vary allocations between the different Package Elements as appropriate; (iii) Approve variations in scheme costs; and (iv) Add/substitute schemes, provided expenditure is contained within the approved total budget. (d) Authorise the Director of Planning and Transport, in consultation with the Cabinet Member for Council Transformation, Sustainability, Transport and Strategic Planning to present a report to a future meeting of the Cabinet detailing a Local Sustainable Transport Fund Programme for 2012/13 and 2014/15. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: DR)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 8 pages

Appendix 1

Local Sustainable Transport Fund Year One Implementation Plan CABINET 14 December 2011

Local Sustainable Transport Fund Implementation Plan

Project aims and objectives

The Council’s transport policies are contained in the Local Transport Plan 2011-2026. These policies reflect wider local priorities in the Sustainable Communities Strategy, “One Swindon”, Central Area Action Plan and the draft Core Strategy. These policies and plan are based on the comprehensive evidence base produced for the Council Transport Strategy document agreed by Cabinet.

The Local Transport Plan (LTP) takes the Council’s policies and objectives for Transport and expresses these as individual schemes or proposals. These are prioritised on the basis of impact and funding available. The Local Sustainable Transport Fund (LSTF) provides an opportunity to add value to the LTP by providing an additional capital and revenue fund to enhance or add to existing schemes. In the longer term it will provide much needed additional capacity to the Council to the benefit of sustainable travel objectives.

The LSTF package of measures supports the delivery of the policies set out in the Local Transport Plan and, as a consequence supports the wider strategic aims of the wider community. The bid submitted by the Council is consistent with the LTP, was submitted within a tight timescale and based on what could reasonably be committed/delivered by 31st March 2012 (for year one proposals). To ensure that we have the best chance of securing this funding the Director of Planning and Transport has progressed the design of a number of schemes under the existing LTP. However, this has meant that a number of potential schemes have now progressed to a point where the LTP delivery plan needs to be amended to include the additional schemes. All proposals are consistent with previously agreed objectives and have not been the subject of detailed consultation because of this.

A number of proposals/projects may have local impacts where consultation is important. As a consequence these may no longer be deliverable within the timescales that now remain.

If agreed by Cabinet the use of LSTF monies for the schemes outlined in this report could release currently allocated LTP funding to address other LTP priorities across the Borough.

Year One Delivery Plan

This document sets out the indicative programme for the first year of the Local Sustainable Transport Fund (LSTF). The programme is a combination of revenue and capital schemes that build capacity and capability or are capable of being delivered quickly.

Further information on the subject of this report can be obtained from James Jackson on 466518 or Email [email protected]. Appendix 1

Local Sustainable Transport Fund Year One Implementation Plan CABINET 14 December 2011

Table 1 sets out the total four-year LSTF funding allocation from central government split between capital and revenue allocations as set out in the bid document.

Table 1 - LSTF Grant Allocations (£000) 2011/12 2012/13 2013/14 2014/15 Total Year Total allocation 930 1.210 1.252 1.080 4.472 Revenue 620 630 630 620 2.500 Capital 310 580 622 460 1.972

The funding for each year must be spent within that financial year. The funding agreement with the Department for Transport does not allow spending to be rolled forward into future years.

The LSTF project is a three and a half year programme of work from July 2011 to March 2015. The Implementation Plan for year one builds the foundation for the remainder of the project. Table 2 sets out, in broad terms, the overarching theme for each year. The Implementation Plan for each year will be derived from these themes and will include initiatives identified through the baseline surveys and stakeholder engagement in year one. The programme for year 2 onwards has more flexibility for consultation and fine tuning than the year one proposals which reflect a more pragmatic approach.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LSTF Swindon FINAL MASTER (2): Appendix 2Appendix 20 pages Download
PDF
LSTF Year One Implementation Final20111205Report 8 pages DownloadRead as text
PDF
Local Sustainable Transport Fund Programme (Minute for Confirmation)Report 5 pages Download
PDF
SwindonDftGrantLSFT201112: Appendix 3Appendix 12 pages Download

At this meeting

Whole meeting

Who was there

7 of 10 attended
RB
Councillor Roderick BluhChair, apologies
GP
Councillor Garry PerkinsVice-Chair, present
ME
Councillor Mark EdwardsMember, present
PG
Councillor Peter GreenhalghMember, present
RH
Councillor Russell HollandMember, present
CL
Councillor Colin LovellMember, apologies
BM
Councillor Brian MattockMember, present
NM
Councillor Nick MartinMember, present
DR
Councillor David RenardMember, present
KW
Councillor Keith WilliamsMember, apologies

On this subject at Swindon

Search all
  1. Local Sustainable Transport Fund Programme (Minute for Confirmation)This decision
  2. Local Sustainable Transport Fund ProgrammeApproved
  3. Local Sustainable Transport Fund Grant AwardApproved

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open