Resolved – (1) That the forecast out-turn position of the Capital Programme 2012/13, as detailed in paragraphs 3.1 to 3.5 of the joint report, be noted. (2) That the ( a) Housing Repairs and Maintenance Programme, as set out in Appendix 1 of the report of the Board Director, Service Delivery (b) Housing Capital Repairs and Improvement Programme, as set out in Appendix 2 of the report of the Board Director, Service Delivery, and (c) the Non-Core Works Programme, as set out in Appendix 3 of the report of the Board Director, Service Delivery, be adopted, and (d) officers be authorised to make applications to utility companies for grant funding to support the delivery of energy efficiency programmes of work. (3) That the decision set out in Minute 46 of the Housing Advisory Forum concerning the Housing Repairs and Improvement Programme, be noted and endorsed. (4) That the changes to the 2012/13 Capital Programme, as detailed in paragraph 4.2 of the joint report, be approved. (5) That the use of Capital Receipts to fund Council Equal Pay costs in 2012/13, as detailed in paragraphs 5.1 to 5.3 of the joint report, be approved. (6) That the change to the cash investment limits, as detailed in paragraphs 6.1 to 6.3 of the joint report be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: KW / GP)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Author: Cabinet Member for Finance Board Director Resources Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report sets out the 2012/13 Capital Programme position as at the end of December 2012. 2. Recommendations Cabinet is recommended to: 2.1 Note the 2012/13 Capital Programme position as detailed at paragraphs 3.1 to 3.5 2.2 Approve the detailed HRA Capital Programme for 2013/14 as referred to at paragraph 4.1 and included at Appendix 3, subject to any comments from the Lead Member for One Swindon, Localities and Housing following discussion at the Housing Advisory Forum. 2.3 Approve the changes to the 2012/13 Capital Programme detailed at paragraph 4.2 2.4 Approve the use of Capital Receipts to fund Equal pay costs in 2012/13 as detailed at paragraphs 5.1 to 5.3 2.5 Note the change to the cash investment limits as detailed at paragraphs 6.1 to 6.3 Detail 3. Capital Programme 2012/13 3.1 Table 1 below provides a summary of the forecast out-turn position by group compared with the approved total scheme budgets as at the end of December 2012.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring 3rd Quarter 2012/13
3.2Table 2 provides a summary of current spend against each budget forecast, providing expenditure in 2012/13 (April 2012 to December 2012) as well as previous years spend to provide a total spend to date figure over all years. Appendix 1 provides a full scheme-by-scheme breakdown of these figures. Table 2 – Expenditure to date
Total Budget Spend to 12/13 Spend to Group Forecast 31.3.12 Spend Dec 12 £’000’s £’000’s £’000’s £’000’s Adult Social Care 3,823 2,785 26 2,811 Business Transformation 58,578 36,389 8,675 45,064 Children’s Services 27,119 7,814 5,747 13,561 Environment & Regeneration & 65,633 21,704 8,600 30,304 Communities (ERC) Housing Revenue Account (HRA) 16,151 0 1,986 1,986 Leisure Libraries & Culture 1,691 209 435 644 S106 funded schemes 19,454 3,402 1,557 4,959 Service Totals 192,449 72,303 27,026 99,329
3.3The variances shown in Table 1 relate to: 3.3.1 Childrens Services – a net forecast overspend of £50k due to a combination of variances on school schemes, as detailed at Appendix 1.
Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring 3rd Quarter 2012/13
Cabinet Date: 20th March 2013
3.3.2 ER&C - forecast net underspend of £411k relates to a combination of forecast overspends and underspends. Total overspends of £449k relates to the following projects:
• £130k for finalising the cremators works but hoped that this will reduce through price negotiations, and partly offset by £50k savings on the refurbishment scheme detailed at 3.3.3 below
• £255k on non-LTP maintenance, but which is offset by the underspend on traffic signals • £64k on safe and warm where additional budget has been approved by the project board 3.3.3 Underspends totalling £860k relate to the following projects:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.