Major Transport Schemes - Prioritisation Process and Provisional Programme

Approved Committee 6 papers

Swindon & Wiltshire Local Transport Body approved this item on Monday 8 July 2013. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Resolved – That the Local Transport Body approves: (1) the provisional prioritised scheme programme shown in Table 5 of the report. (2) the provisional contingency scheme programme shown in Table 6 of the report. (3) the provisional development scheme programme shown in Table 7 of the report. (4) that the officers, supporting the Local Transport Body be requested, in liaison with relevant partners, seek to address the uncertainties and risks identified in the prioritised and contingency scheme assessments and present reviewed assessments at the next SWLTB meeting. (5) that the Head of Commissioning, Economy and Attainment, Swindon Borough Council, in consultation with the members of the Local Transport Body to finalise the submission of the provisional scheme programmes to the Department for Transport by the 31 July 2013.
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Swindon & Wiltshire Local Transport Body, 10 pages

Swindon and Wiltshire Local Transport Body 8 July 2013

Subject: Major Transport Schemes - Prioritisation Process and Provisional Programme Agenda Item: 6

1. Purpose and Reasons 1.1 To approve the provisional major transport scheme programme for submission to the Department for Transport (DfT) by 31 July 2013. 2. Recommendations The Swindon & Wiltshire Local Transport Body (SWLTB) is recommended to: 2.1 Approve the provisional prioritised scheme programme shown in Table 5. 2.2 Approve the provisional contingency scheme programme shown in Table 6. 2.3 Approve the provisional development scheme programme shown in Table 7. 2.4 Request that officers, in liaison with relevant partners, seek to address the uncertainties and risks identified in the prioritised and contingency scheme assessments and present reviewed assessments at the next SWLTB meeting. 2.5 Authorise the Head of Commissioning, Economy and Attainment, Swindon Borough Council, in consultation with the full members of the SWLTB to finalise the submission of the provisional scheme programmes to the DfT by the 31 July 2013. 3. Detail 3.1 The DfT is to devolve funding for major transport schemes to Local Transport Bodies (LTBs) from April 2015 onwards. In the Swindon and Wiltshire Local Enterprise Partnership (SWLEP) area this funding is anticipated to be £16.9m over the period April 2015 to March 2019 (subject to confirmation as part of a future government spending review). Given the indicative nature of the funding allocation, the DfT has stated that LTBs should plan for 33% more and less than this figure in provisional scheme programmes. 3.2 The DfT has requested that provisional scheme programmes are developed and submitted to them by end of July 2013 in order to inform early consideration of future government spending reviews and to ensure that a deliverable programme will be in place in time to receive the devolved major scheme funding from April 2015.

Further information on the subject of this report can be obtained from James Jackson at Swindon Borough Council (Tel. No.: 01793 466518; Email: [email protected] and Robert Murphy at Wiltshire Council (Tel. No.: 01225 713458; Email [email protected]) Swindon and Wiltshire Local Transport Body 8 July 2013

3.3The agenda item on ‘Major Transport Schemes - Initial Scheme Assessment and Sifting’ outlined how the long list of potential major transport schemes was reduced to a more manageable shortlist for prioritisation by Swindon Borough Council and Wiltshire Council. Outline of Prioritisation Process 3.4 The DfT’s guidance states that: “We recognise that the identification of a prioritised and affordable list of schemes by [July] 2013 will be likely to be conducted on the basis of a limited set of criteria. At that stage we do not expect most schemes to have a fully developed business case or a WebTAG appraisal completed”. “However, the Department believes that, as a minimum, value for money, deliverability, environmental and society/distributional impacts should always be among the factors taken into consideration”. 3.5 To ensure that the above requirements are met and to increase the robustness of the prioritisation process, an assessment broadly equivalent to a Strategic Outline Business Case (see Table 1) has been completed for each of the shortlisted schemes. Table 1: Business Case Stages

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 142 pages Download
PDF
Appendix 2Appendix 2 1 pages Download
PDF
Appendix 3Appendix 3 1 pages Download
PDF
Appendix 4Appendix 4 18 pages Download
PDF
Appendix 5Appendix 5 3 pages Download
PDF
Major Transport Schemes: Prioritisation Process and Provisional ProgrammeReport 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
DH
Councillor Dale HeenanMember, present
KW
Councillor Keith WilliamsChair, present
FD
Councillor Fleur de Rhe-Philipe Wiltshire CouncilMember, present
TS
Councillor Toby Sturgis Wiltshire CouncilMember, present
IT
Iain TuckerSecretary, in attendance
CC
Catherine CambellPublic, present
RO
Richard OrmerodPublic, present
MR
Martin RevillPublic, present

On this subject at Swindon

Search all
  1. Major Transport Schemes - Prioritisation Process and Provisional ProgrammeThis decision
  2. Major Transport Schemes - UpdatesApproved
  3. Major Transport Schemes - Outline Business Case UpdateApproved
  4. Devolved Major Transport Scheme Funding - Establishment of the Swindon and Wiltshire Local Transport BodyNoted

More from Swindon Swindon & Wiltshire Local Transport Body

All decisions
MeetingDecisionOutcome
1 May 2015 Ratification of MinutesResolved – (1) That the minutes of the meeting held on 29 th October 2014 be accepted as a correct record. (2) That t... Decided Open
21 Apr 2015 A350 Yarnbrook and West Ashton Relief Road Outline Business CaseResolved – That had the SWLTB been in a position to do so, it would have: (1) Approved the Outline Business Case for ... Approved Open
21 Apr 2015 A350 Chippenham Bypass Improvements (Bumpers Farm) Full Business CaseResolved – That had the SWLTB been in a position to do so, it would have: (1) Approved the Full Business Case for the... Approved Open
29 Oct 2014 Major Transport Schemes - UpdatesResolved – That this Transport Body: (1) Approves the Outline Business Case (OBC) for the M4 J16 Improvement scheme; ... Approved Open
17 Jul 2014 Appointment of ChairResolved – That Councillor Fleur de-Rhe Philipe be appointed Chair of this Transport Body for the Municipal Year 2014... Decided Open