Major Transport Schemes - Outline Business Case Update
ApprovedCommittee7 papers
Swindon & Wiltshire Local Transport Body approved this item on Thursday 17 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved – That the Swindon & Wiltshire Local Transport Body: (1) Approves the Outline Business Case (including the OBC Addendum 1: Revised Option A – Bumpers Farm) for the A350 Chippenham Bypass Improvements scheme. (2) Approves the progression of the A350 Chippenham Bypass Improvements – Bumpers Farm scheme to Full Business Case. (3) Notes the progress updates on the development of Outline Business Cases for the M4 J15 Improvement and M4 J16 Improvement schemes. (4) Approves the proposed proportionate approach to the development of the Outline Business Case for the A350 Yarnbrook and West Ashton Relief Road scheme.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Programme update Insert programme Single option OBC FBC/Detailed Construction selection Design complete SOBC programme Early 2014 Spring 2014 Spring 2016 2018/2019 Current forecast Autumn 2014 Spring 2015 Spring 2016 2018/2019 Variance 6 months 12 months None None Comment: A single scheme option has been developed and can be taken forward for agreement and costing. The scheme requires minor amendments to that originally proposed as part of the planning permission.
Outline Business Case Development Update Strategic Case • This case was largely set out in the strategic outline business case (SOBC), the scheme has a strong connection with the Swindon growth agenda. • The approved S106 scheme does not provide capacity benefits for the A346 arm, which are required to support the strategic case. • A single scheme has been developed to provide a complete scheme for the Local Transport Body and is not significantly different from that already proposed within the Section 106 agreement. Economic Case • Transport modelling work has identified the need for additional capacity on the A346 arm of the junction. Thus design work is being undertaken and the resultant scheme design may affect scheme cost. • Transport modelling work has shown transport user benefits for a core scenario with sensitivity testing, (including low growth/increased scheme costs), would result in a very high benefit to cost ratio. This is to be confirmed when costs are more certain. Commercial case • There are a number of procurement options for this scheme. However this cannot be confirmed until the management case (in particular the identification of the delivery agent) is confirmed. Work to date indicates there will be an acceptable procurement route. Financial case • Whilst there is a scheme with the consented Commonhead development, changes to the scheme design and refinement of scheme costs will affect the financial and delivery cases. • The LTB funding of £3.70 million has been allocated to the scheme on the basis that the Commonhead developer delivers the scheme. • Scheme costs are to be confirmed when the design is refined to meet the scheme objectives. Management case • The Commonhead developer will need to sign up to delivering the scheme within the timeline agreed with the LTB and DfT. • To secure LTB funding, there needs to be a legal agreement between the Commonhead developer and the LTB regarding risk and liability.
Risk and Issue Log
Risk and Issue description Resultant RAG Scheme costs/design to date is based on conceptual design. Design work Amber is required on agreed single option. Modelling work shows transport user benefits are sufficiently high to Green ensure a very high BCR (4 or above). However scheme costs are to be refined, thus BCR may be affected. The Commonhead developer financial contribution needs to align with Amber the LTB scheme programme and will need to be agreed within a formal agreement. The organisation delivering the scheme will be working at risk on the Green scheme development work until LTB funding is fully secured. Technical approval is required by the Highways Agency on the final Green scheme design. The scheme is located on the border of four management areas Green (Highways Agency Area 2, Area 3, A419 DBFO and Swindon Borough Council), hence multi party agreements are required.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Swindon & Wiltshire Local Transport Body at Swindon and we tell you when its next papers are published, before the meeting rather than after it.
Major Transport Schemes - UpdatesResolved – That this Transport Body: (1) Approves the Outline Business Case (OBC) for the M4 J16 Improvement scheme; ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.