Swindon's Energy Future - Part 2

Approved Executive 6 papers

Cabinet approved this item on Wednesday 23 April 2014. Below is the council's own wording, with the papers it was decided on.

Item114

Resolved

Resolved – (1) That Common Farm, Wroughton and Chapel Farm Landfill Site, Blunsdon be endorsed as suitable sites for solar development, as referred to in paragraph 3.3 of the joint report. (2) That the Head of Property Assets be authorised to negotiate the necessary arrangements to enable Swindon Commercial Services (SCS) Ltd. to progress the solar farm developments on Council land and the Director of Law and Democratic Services, in consultation with the Cabinet Member for Strategic Planning and Sustainability and the Head of Property Assets, be authorised to conclude any necessary documentation to implement such arrangements on such terms as he considers best to protect the Council’s interests. (3) That the Board Director, Service Delivery, be authorised to request Swindon Commercial Services (SCS) Ltd. to progress the relevant technical work, planning applications, following community engagement, and grid connection applications for the Common Farm and Chapel Farm sites on the Council’s behalf. (4) That the on-going development by the Board Director Resources, in consultation with the Cabinet Member for Finance, of a flexible business model which facilitates investment in such solar farms by Swindon Borough Council, local communities and the private sector, be approved, with any such investment ... view the full minutes text for item 114. (CM: BM)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet

A419 SWINDON SOLAR NOISE BARRIER

FEASIBILITY STUDY

April 2014

Sound Barrier Solutions Limited Registered Office: The Coach House, 97 Northampton Road, Market Harborough, Leicestershire, LE16 9HD Tel / Fax : +44 (0)1858 432667 Email: [email removed] Registered in Cardiff No. 3577151 CONTENTS 1. Executive Summary

2. Aim of study

3. Introduction 3.1. Western Fences and Gaps 3.2. Eastern Villages 3.3. Benefits of Solar Noise Barriers

4. Acoustic Design Criteria 4.1. Design Criteria for Existing Communities (West of A419) 4.2. Design Criteria for New Developments (Eastern Villages)

5. Measurement Approach 5.1. Measurement Locations 5.2. Measurement Apparatus 5.3. Weather Conditions

6. Method of Analysis 6.1. “Mithra” Computer Noise Model 6.2. Do Nothing / Do Something 6.3. Traffic Flows (2013/2028) 6.4. Environmental Barrier Degradation

7. Solar Noise Barrier Options 7.1. Noise Barrier Specifications 7.2. Solar Noise Barrier Options 7.3. Choosing an Optimum Solar / Noise Barrier Design

8. Discussion of Results - I : Existing Fences 8.1. Do Nothing : Existing Fence Performance (2013/2028) 8.2. Do Something : Upgraded Fence to Noise Barrier Performance of (2028)

9. Discussion of Results - II : Gaps on the Western side 9.1. Liden Lagoon – (Solar) Noise Barrier (2013/2028) 9.2. Merlin Way – (Solar) Noise Barrier (2013/2028) 9.3. Watermead – (Solar) Noise Barrier (2013/2028) 9.4. Retingham Way – (Solar) Noise Barrier (2013/2028)

2 10. Discussion of Results - III : Eastern Villages 10.1. 3m Solar T-Piece Noise Barrier (2028) 10.2. 4.5m Solar Bund (2028) 10.3. 4m Brennar Style Solar Noise Barrier (2028)

11. Cost-Benefit Analysis 11.1. Cost-Benefit to Upgrade Existing Fences to Noise Barriers 11.2. Cost-Benefit for New West side Noise Barriers 11.3. Cost-Benefit for the Eastern Villages Solar Noise Barrier 11.4. Overall Cost-Benefit for the Scheme

12. Conclusions and Recommendations 12.1. Recommended Hybrid Design, Predicted Costs and Revenues 12.2. Detailed Design Considerations 12.3. M4 Wichelstowe

Tables Table 1: Summary of Measured Averaged Weekly Noise Levels Table 2: Noise Exposure for Houses behind Existing Fences (2013/2028) Table 3: Noise Exposure for Houses behind Upgraded Fences (2028) Table 4: Cost of Upgrade of Existing Fences to Noise Barriers Table 5: Liden Lagoon Noise Barrier Mitigation Performance (2013/2028) Table 6: Merlin Way Noise Barrier Mitigation Performance (2013/2028) Table 7: Watermead Noise Barrier Mitigation Performance (2013/2028) Table 8: Retingham Noise Barrier Mitigation Performance (2013/2028) Table 9: Cost of Noise Barriers for Western side of A419 Table 10: Cost-Benefit of Noise Barriers for Western Side of A419 Table 11: Cost of Solar Noise Barriers for Eastern Villages Table 12: Cost-Benefit of Solar Noise Barriers for Eastern Villages

Figures Figure 1: Commonhead Existing Fence locations Figure 2: St Pauls Drive Existing Fence location Figure 3: Gifford Road Existing Fence location Figure 4: Boundary Close Existing Fence location Figure 5: Liden Lagoon – Proposed (Solar) Noise Barrier Location Figure 6: Merlin Way – Proposed (Solar) Noise Barrier Location Figure 7: Watermead – Proposed (Solar) Noise Barrier Location Figure 8: Retingham Way – Proposed (Solar) Noise Barrier Location Figure 9: Watermead – Average Hourly Noise Levels Figure 10: Merlin Way – Average Hourly Noise Levels 3 Figure 11: Brockley Rise – Average Hourly Noise Levels Figure 12: Commonhead Upper Existing Fence (Photo) Figure 13: St Pauls Drive Existing Fence (Photo) Figure 14: St Pauls Drive Existing Fence (Photo) Figure 15: Eastern Villages – Solar Noise Barrier Location

Appendix A: Noise Barrier Element Specification

Appendix B: Traffic Data

Appendix C: Noise Barrier Types/Options

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Common Farm: PlanAppendix 1 451 KB Download
PDF
Chapel Farm: PlanAppendix 2 313 KB Download
PDF
A419 PVNB Report Executive SummaryAppendix 3 8 KB Download
PDF
Letter from Department of Energy and Climate ChangeAppendix 4 140 KB Download
PDF
Background Information: A419 PVNB Feasibility Study ReportReport 1.8 MB DownloadRead as text
PDF
Swindon's Energy Future: Part 2Report 85 KB Download

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Swindon's Energy Future - Part 2This decision
  2. Invest and Save for a Low Carbon Swindon - Swindon's Energy Future - Motion at CouncilNoted
  3. Swindon's Energy FutureApproved
  4. Swindon's Energy Future - Solar Barrier Along A419 - Motion at Council. (Oral)Noted
  5. Q & A - Operation of Waste to Energy (Managing Director Swindon Commercial Services Limited)Decided
  6. Swindon Sustainable Energy Delivery PlanNoted

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies