Resolved – That the report be noted. (ii) Audit Committee Update Chris Hackett (Grant Thornton) presented a report advising the Committee of the External Auditors’ progress, as at 23 rd February 2016, in respect of the delivery of their audit responsibilities. The report also included a summary of key emerging national issues and developments that might be of interest to the Committee. Resolved – That the report and supporting papers be noted.
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Introduction Each year we certify certain claims and returns submitted by the Councils where we are the appointed auditor. This is not formally included within our appointment to audit your accounts but fits closely with that work. This certification typically takes place six to nine months after the claim period (usually the financial year) and represents a final but important part of the process to confirm the Council's entitlement to funding.
We have certified three claims and returns for Swindon Borough Council (the Council) for the financial year 2014/15 including: - Housing Benefit Subsidy (HB) - Teachers Pensions contributions - Pooling of Housing Capital Receipts return relating to expenditure of £75.396 million.
This report summarises our overall assessment of the Council’s management arrangements in respect of the certification process and the significant matters arising from our work.
Approach and context to certification This year the arrangements for certification of the HB claim were prescribed by the Audit Commission and set out in their Certification Instruction agreed with the Department for Work and Pensions before the Audit Commission demised. The approach to auditing the other two returns were agreed directly with the Department for Communities and Local Government (DCLG) and the Teachers Pensions Agency.
Key messages The key messages from our certification work are summarised in the table below.
Aspect of certification Key Messages RAG arrangements rating
Submission & certification All claims were submitted by the authority to the Government body in line with the timetable. All audit Green work was completed by the deadline. The HB and Teachers pensions return were submitted by the auditor in advance of the deadline. The Pooling Housing Capital Receipts return is submitted via a DCLG computer system which crashed in November preventing all Council auditors from submitting the return. The return was submitted after the deadline of November 30th. DCLG confirmed there was no penalty to Councils due to late submission. Accuracy of claim forms The claims submitted for audit were accurate with only minor issues arising from our work. The Green submitted to the auditor Council's arrangements for preparing the claims and returns are sound. (including amendments & qualifications)
Supporting working papers Working papers to support the claims were generally good. This is the first year the Pooled Housing Green Capital Receipts claim was done outside of the Audit Commission regime, and the work specified by the DCLG was more extensive, requiring more audit work. This also required additional requests for working papers and information compared to previous years.
Corporate Risk Management UpdateThat (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a furth...
Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.