CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swindon Borough Council
Audit Committee, Tuesday 28 June 2016

External Audit Reports

Noted Finance 2 papers

Audit Committee noted this item on Tuesday 28 June 2016. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

Resolved – That the Update and Progress Report for the year ended 31 st March 2016 be accepted. Chris Hackett (Grant Thornton) presented a report advising the Committee of the External Auditors’ progress, as at June 2016, in respect of the delivery of their audit responsibilities. The report also included a summary of key emerging national issues and developments that might be of interest to the Committee. Resolved – That the report and supporting papers be noted.
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Audit Committee, 4 pages

oS Grant Thornton

An instinct for growth

Mt

Stuart McKellar

Board Director Resources

Swindon Borough Council

Civic Centte feet romfon ee

Euclid Street Victoria Street

Swindon Bristol BS1 6FT

SN1 2JH T +44 (0)117 3057600 ‘www.grant-thornton.co.uk

7 April 2016

Dear Stuart

Planned audit fee for 2016/17: Swindon Borough Council

The Local Audit and Accountability Act 2014 provides for the introduction of a new framework for local public audit. Under these ptovisions, the Audit Commission closed in Match 2015 and the Secretary of State for Communities and Local Government delegated some statutory functions from the Audit Commission Act 1998 to Public Sector Audit Appointments Limited (PSAA) on a transitional basis.

PSAA will oversee the Commission's audit contracts for local govetnment bodies until they end in 2018, following the announcement by the Department for Communities and Local Government (DCLG) that it will extend transitional arrangements until 2017/18. PSAA's responsibilities include setting fees, appointing auditors and monitoring the quality of auditors' work. Further information on PSAA and its tesponsibilities ate available on the PSAA website.

Scale fee

PSAA prescribes that 'scale fees ate based on the expectation that audited bodies ate able to provide the auditot with complete and materially accurate financial statements, with supporting working papers, within agreed timescales’.

There ate no planned changes to the overall work programme for local government audited bodies for 2016/17, bar the adoption of new measurement requirements for the Highways Network Asset.

CIPFA/LASAAC is expected to confirm, subject to consultation, that the 2016/17 Code of Practice on Local Authority Accounting in the United Kingdom will adopt the measurement requirements of the CIPFA Code of Practice on Highways Network Asset.

PSAA have determined that there is no reliable and equitable way of establishing the volume of additional audit work, and therefore fees requited, at each applicable local authority to gain assutance over the new financial reporting requirements. Therefore, fees for the additional work identified by auditors in 2016/17 will be subject to approval by PSAA under the normal fee vatiations process. PSAA expect that 'the additional fees for a highway authotity will be in the range of £5,000 to £10,000, where authorities ate able to provide the information tequited, and the auditor is able to rely on central assurance of the models in use.

Chartered Accountants:

Grant Thornton UK LLP is a limited liability partnership registered in England and Wales No 00307742. Registered office: Grant Thornton House, Malton Street, Euston Square, London NW1 2EP. Allst of members is available from our registered office. Grant Thornton UK LLP is authorised and regulated by the Financlal Conduct Authority.

Grant Thorton UK LLP is a member firm of Grant Thomton Intemational Ltd (GTIL). GTIL and the member firms are not a worldwide partnership. Services are delivered by the member firms. GTIL and its member firms are not agents of, and do not obligate, one another and are not liable for one another's ads or omissions. Please see grantthomton.co.uk for further details, PSAA have proposed that 2016/17 scale audit fees (excluding work completed on the Highways Network Asset) ate set at the same level as the scale fees applicable for 2015/16. The Council's scale fee for 2016/17 has been set by PSAA at £128,378.

The audit planning process for 2016/17, including the tisk assessment, will continue as the yeat ptogtesses and fees will be reviewed and updated as necessary as our work progresses.

Scope of the audit fee

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
External Audit ReportsReport 4 pages DownloadRead as text
PDF
Swindon BC Audit Committee Update JuneReport 9 pages Download

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. External Audit ReportsThis decision
  2. External Audit Plan 2025/26Noted
  3. External Audit Progress Report and Sector UpdateNoted
  4. External Audit Plan and Progress ReportNoted
  5. External Audit PlanningDecided
  6. External Audit Progress ReportNoted

More from Swindon Audit Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 MinutesThat the minutes of the previous meeting held on 17 March 2026 be confirmed as true record and signed by the Chairman Decided Open
23 Jun 2026 Corporate Risk Management UpdateThat (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a furth... Decided Open
23 Jun 2026 Audit Committee Annual ReportThat the report be noted Noted Open
23 Jun 2026 Head of Internal Audit Annual Report 2025/26 and OpinionThat the report be noted Noted Open
23 Jun 2026 Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies