Swindon Borough Council
Audit Committee, Tuesday 21 February 2017

Internal Audit report - Contract management of the delivery of the Housing capital programme

Noted Finance 3 papers

Audit Committee noted this item on Tuesday 21 February 2017. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

Resolved – (1) That the report, and the initial management response to the audit review recommendations, be noted. (2) That the positive response to the audit recommendations be welcomed and that, to ensure continued progress, a further audit review be carried out before November 2017 and the outcomes of that audit be reported to the Committee for consideration.
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Audit Committee

Internal Audit report – Contract management of the delivery of the Housing capital programme

Audit Committee Date: 21st February 2017

Author: Head of Internal Audit Wards: None Locality Affected: None Parishes Affected: None

1. Purpose and Reasons 1.1 The Council’s Audit Committee has a strategic role to ensure that the Council’s assurance framework is operating effectively. To this end it should seek assurance that key areas that contribute to this framework are operating effectively. 1.2 Members requested that at least one individual audit report be presented to each meeting of the Committee. The Internal Audit report on the contract management arrangements regarding the delivery of the Housing capital programme, that identified significant risk, was selected to be presented to this Committee meeting. 1.3 The initial report was finalised in October 2017. Internal Audit has since carried out a follow-up review to establish progress in implementing agreed recommendations so that Members had an up-to-date position regarding the service. 2. Recommendations 2.1 It is recommended that the contents of the report be noted. 3. Detail Background 3.1 The annual Housing capital programme budget for 2016/17 is £16.9m. In addition to this there was a £9m underspend carried forward from 2015/16. The Council is responsible for maintaining approximately 10,300 domestic properties. 3.2 The capital programme has been prioritised with the aim to deliver major aids and adaptations for tenants with special needs, maintain stock to the Government’s Decent homes Standard and to commence a programme of structural repairs and improvement work. The programme of works is intended to reduce the demand for responsive repairs, improve the thermal comfort and security of homes and enhance the local environment. Original audit: finalised October 2016 3.3 Internal Audit carried out an audit of the contract management arrangements for the delivery of the Housing capital programme. The report was finalised in October

Further information on the subject of this report can be obtained from Nick Hobbs, Direct Dial Telephone Number: 01793 463940, [email protected]. Internal Audit report – Contract management of the delivery of the Housing capital programme

Audit Committee Date: 21st February 2017

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit report: Contract management of the delivery of the Housing capital programmeReport 293 KB DownloadRead as text
PDF
original reportAppendix 1 632 KB Download
PDF
follow-up reportAppendix 2 512 KB Download

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Internal Audit report - Contract management of the delivery of the Housing capital programmeThis decision
  2. Head of Internal Audit Annual Report 2025/26 and OpinionNoted
  3. Internal Audit CharterApproved
  4. Internal Audit Strategy and PlanApproved
  5. Head of Internal Audit & Corporate Fraud Progress ReportNoted
  6. 2026/27 Internal Audit Planning ProcessApproved

More from Swindon Audit Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 MinutesThat the minutes of the previous meeting held on 17 March 2026 be confirmed as true record and signed by the Chairman Decided Open
23 Jun 2026 Corporate Risk Management UpdateThat (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a furth... Decided Open
23 Jun 2026 Audit Committee Annual ReportThat the report be noted Noted Open
23 Jun 2026 Head of Internal Audit Annual Report 2025/26 and OpinionThat the report be noted Noted Open
23 Jun 2026 Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies