CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swindon Borough Council
Audit Committee, Tuesday 27 June 2017

External Audit - progress and update report

Decided Finance 1 paper

Audit Committee decided this item on Tuesday 27 June 2017. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

Resolved – That the Update and Progress Report for the year ended 31 st March 2017 be accepted.
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Audit Committee

Audit Committee Progress and Update Report for Swindon Borough Council Year ended 31 March 2016 14 June 2017

Elizabeth Cave Director T 0117 3057855 E [email removed]

Chris Hackett Audit Manager T 0117 3057876 E [email removed]

Anna McWilliam Executive T 0117 3057611 E [email removed] Audit Committee progress report and emerging issues and developments – Swindon Borough Council

The contents of this report relate only to the matters which have come to our attention, which we believe need to be reported to you as part of our audit process. It is not a comprehensive record of all the relevant matters, which may be subject to change, and in particular we cannot be held responsible to you for reporting all of the risks which may affect your business or any weaknesses in your internal controls. This report has been prepared solely for your benefit and should not be quoted in whole or in part without our prior written consent. We do not accept any responsibility for any loss occasioned to any third party acting, or refraining from acting on the basis of the content of this report, as this report was not prepared for, nor intended for, any other purpose.

© 2017 Grant Thornton UK LLP. All rights reserved. 2 Audit Committee progress report and emerging issues and developments – Swindon Borough Council

Contents

Contents Page Introduction 4 Progress at June 2017 5 Technical matters 7

© 2017 Grant Thornton UK LLP. All rights reserved. 3 Audit Committee progress report and emerging issues and developments – Swindon Borough Council

Introduction

This paper provides the Audit Committee with a report on progress in delivering our responsibilities as your external auditors. Members of the Audit Committee can find further useful material on our website www.grant-thornton.co.uk, where we have a section dedicated to our work in the public Elizabeth Cave Chris Hackett sector. Here you can download copies of our publications including: Engagement Lead Manager • CFO Insights – reviewing council's 2015/16 spend (December T 0117 3057885 T 0117 3057876 2016); http://www.grantthornton.co.uk/en/insights/cfo-insights- M [phone removed] M [phone removed] reviewing-councils-201516-spend/ E [email removed] E [email removed]

• Fraud risk, 'adequate procedures', and local authorities (December 2016); http://www.grantthornton.co.uk/en/insights/fraud-risk- adequate-procedures-and-local-authorities/ • New laws to prevent fraud may affect the public sector (November 2016); http://www.grantthornton.co.uk/en/insights/new-laws-to- prevent-fraud-may-affect-the-public-sector/ • Brexit: local government – transitioning successfully (December 2016) http://www.grantthornton.co.uk/en/insights/brexit-local- government--transitioning-successfully/

If you would like further information on any items in this briefing, or would like to register with Grant Thornton to receive regular email updates on issues that are of interest to you, please contact either your Engagement Lead or Engagement Manager.

© 2017 Grant Thornton UK LLP. All rights reserved. 4 Audit Committee progress report and emerging issues and developments – Swindon Borough Council

Progress at 14 June 2017 2016/17 audit

Progress against plan Opinion and VfM conclusion Outputs delivered Fee letter, On track On Track accounts audit plan.

2016/17 work Completed Comments Fee Letter We issued the 'Planned' fee letter for 2016/17 in April 2016. April 2016

Accounts Audit Plan Reported to the April Audit Committee meeting We are required to issue a detailed accounts audit plan to the April 2017 Council setting out our proposed approach in order to give an opinion on the Council's 2016-17 financial statements.

We also inform you of any subsequent changes to our audit approach.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
External Audit: progress and update reportReport 9.4 MB DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. External Audit - progress and update reportThis decision
  2. External Audit Plan 2025/26Noted
  3. External Audit Progress Report and Sector UpdateNoted
  4. External Audit Plan and Progress ReportNoted
  5. External Audit PlanningDecided
  6. External Audit Progress ReportNoted

More from Swindon Audit Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 MinutesThat the minutes of the previous meeting held on 17 March 2026 be confirmed as true record and signed by the Chairman Decided Open
23 Jun 2026 Corporate Risk Management UpdateThat (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a furth... Decided Open
23 Jun 2026 Audit Committee Annual ReportThat the report be noted Noted Open
23 Jun 2026 Head of Internal Audit Annual Report 2025/26 and OpinionThat the report be noted Noted Open
23 Jun 2026 Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies