- 1. That the allocation of the land at Bromley Close, detailed on the plan attached at Appendix 1 to the joint report, be approved as a future housing development site to be delivered through the HRA. 2. That the Head of Property Assets in consultation with the Chief Legal Office be delegated the authority to take all necessary steps to appropriate the land at Windmill Hill, detailed on the plan attached as Appendix 2 to the joint report, from the General Fund to the HRA at a value to be determined, to enable it to be developed through the HRA with potential collaboration with the Swindon Housing Company. 3. That a budget of £50K be approved, to be allocated from the HRA, to progress the detailed feasibility and design for the sites at Bromley Close and Windmill Hill, as well as the work to progress the development of Milverton and Torrington Courts The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: GS)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Affordable Housing Development and Regeneration Programme Cabinet Date: 4th December 2019
Author: Cabinet Member for Housing and Public Safety Corporate Director for Communities and Housing Wards: Walcot and Park North, Lydiard and Freshbrook Parishes Affected: Central Swindon South, West
1. Purpose and Reasons 1.1 The report seeks approval from Cabinet to allocate the proposed housing site at Bromley Close in order for the Council, through the Housing Revenue Account (HRA), to continue developing social housing for the residents of Swindon. The identified site has been selected following Member engagement and the initial undertaking of due diligence by the Council’s Planning Department in terms of constraints. 1.2 This report also serves to inform Cabinet of the intended development of the site at Windmill Hill and how this will be brought forward, as well as an update for Members on the intention of developing an options appraisal regarding a High- Rise strategy within the Walcot and Park North Wards. 1.3 The details of this report will continue to deliver towards the Council’s Priority 1: ‘To improve infrastructure and housing to support a growing, low carbon economy’ and contribute to delivering Pledge 6: ‘Ensure there is a range of good quality housing options in Swindon, including affordable opportunities to buy and rent’ and: ‘Through the Local Plan review, identify brown field and green field sites for housing to deliver homes…’ 2. Recommendations Cabinet is recommended to: 2.1 Approve the allocation of the land at Bromley Close, detailed on the plan attached at Appendix 1, as a future housing development site to be delivered through the HRA. 2.2 Delegate the Head of Property Assets in consultation with the Chief Legal Officer to take all necessary steps to appropriate the land at Windmill Hill, detailed on the plan attached as Appendix 2, from the General Fund to the HRA at a value to be determined, to enable it to be developed through the HRA with potential collaboration with the Swindon Housing Company. 2.3 Approve a budget of £50K, to be allocated from the HRA, to progress the detailed feasibility and design for the sites at Bromley Close and Windmill Hill, as well as the work to progress the development of Milverton and Torrington Courts.
Further information on the subject of this report can be obtained from Michael Ash, Director of Housing - [email protected]. Affordable Housing Development and Regeneration Programme Cabinet Date: 4th December 2019
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.