- 1. That an increase in the budget for units 7/9/11 of £530,000 funded through borrowing be approved, of which the debt charges will be financed from the existing capital financing budget in year 1, and from rental income beyond that. 2. That it be agreed that a budget of £480,000, funded through borrowing, for additional works to the undercroft as set out at paragraph 3.5 of the joint report. Further, that it be agreed that resulting debt charges will be financed from the existing capital financing budget in year 1, and from rental income beyond that. 3. That it be approved that £0.9m of the total revised budget to be released in advance of prelets . The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: MP, GS)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Carriage Works Regeneration – Phase II Cabinet Date: 4th December 2019
Author: Cabinet Member for Town Centre Head of Town Centre Development Wards: Central Parishes Affected: Central Swindon South
1. Purpose and Reasons 1.1 In 2017 Cabinet approved capital investment of £3.6m for the refurbishment of units 7/9/11 on the basis that the works would only proceed on a pre-let basis. 1.2 This report seeks approval for an uplift in the previously agreed budget to £4.6m as well as approval for funds for major structural works to units 7/9 to be released in advance of pre-lets. 1.3 The investment would support the regeneration of the Carriage Works (Priority 1, Pledge 3 and Priority 3, Pledge 15) and facilitate the creation of a new higher education institution (Priority 2, Pledge 10). 2. Recommendations Cabinet is recommended to: 2.1 Authorise an increase in the budget for units 7/9/11 of £530,000 funded through borrowing, of which the debt charges will be financed from the existing capital financing budget in year 1, and from rental income beyond that. 2.2 Agree a budget of £480,000, funded through borrowing, for additional works to the undercroft as set out at paragraph 3.5. Resulting debt charges will be financed from the existing capital financing budget in year 1, and from rental income beyond that. 2.3 Approve that £0.9m of the total revised budget to be released in advance of pre- lets. 3. Detail 3.1 In 2017 Cabinet approved a total budget of £3.6m for phase 2 of the Carriage Works regeneration, comprising units 7/9/11 (Cabinet Minute 56, 2017/18 refers). 3.2 Unit 11 (upper ground floor) has been pre-let to Royal Agricultural University (RAU). Construction works started in June 2019 and are expected to be completed early next year. 3.3 The refurbishment of unit 11 – and subsequently units 7/9 – requires major structural works at lower ground floor level which were not envisaged within the original budget approval and are essential to deliver units 7/9.
Further information on the subject of this report can be obtained from Paul Chamberlain, Direct Dial [phone removed], [email protected]. Carriage Works Regeneration – Phase II Cabinet Date: 4th December 2019
3.4As a result of these works, the development potential of phase 2 would increase resulting in additional lettable floorspace (compared to assumptions made in the 2017 business case). However, this requires an additional investment of £530,000 which would increase the budget from £3.6m previously approved to £4.13m. This amount also includes some allowance for cost-price inflation since 2017. 3.5 In addition, the requirement for major structural works at lower ground level has identified the potential to deliver further lettable space as set out in the table below. This does require a further £480,000 of capital investment however. Floorspace Oct 2017 Sep 2019 (Cabinet Approval) (new potential) Location Upper ground floor Upper and lower ground floor Unit 11 5,300 sqft 6,876 sqft Units 7/9 11,000 sqft 11,594 sqft Undercroft - 2,400 sqft Total 16,300 sqft 20,870 sqft
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.