Resolved – (1) That the forecast capital expenditure set out in Table 1 & 2 of the main report and Appendices 1 and 2 be noted; (2) That the variances detailed at paragraph 3.2 be noted ; (3) That the changes detailed at paragraph 3.3 be approved; and (4) That the new reporting requirements regarding the 2019-20 Community Infrastructure Levy (CIL) publishing requirements detailed at paragraph 3.4 of the main report and the contents of Appendix 3 be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: CM)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Monitoring Quarter 3 2019/20 Cabinet Date: 22nd April 2020
Authors: Cabinet Member for Finance, Education and Skills Corporate Director of Finance and Assets Wards: All Parishes Affected: All
1. Purpose and Reasons 1.1 This report presents the third quarter’s monitoring position for the Council’s capital programme and some proposed changes to the programme. 1.2 The effective management of financial resources through robust financial management processes underpins the Council’s ability to achieve its plans and priorities. 2. Recommendations Cabinet is recommended to: 2.1 Note the forecast capital expenditure set out in Table 1 & 2 and Appendices 1 and 2; 2.2 Note the variances detailed at paragraphs 3.2; 2.3 Approve the changes detailed at paragraph 3.3; and 2.4 Note the new reporting requirements regarding the 2019-20 Community Infrastructure Levy (CIL) publishing requirements detailed at paragraph 3.4 and the contents of Appendix 3. 3. Detail Capital Programme – 2019/20 monitoring 3.1 Table 1 below shows the current status of the 2019/20 capital budget and forecast outturn position. The significant budget movements are detailed in paragraph 3.2 below. Table 2 shows how the capital programme is being funded. The capital programme report includes items that were agreed at Council on 20th February 2020 (draft Council Minute .80, 2019/20 refers)
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Quarter 3 2019/20 Cabinet Date: 22nd April 2020
Table 1 - Budget Forecasts and Variances
Total Projected Projected Projected Scheme Service Area Out-turn Overspends Underspends Budget £000's £000's £000's £000's Resources 79,735 79,735 Economy 131,328 131,328 Children Services 31,642 31,558 (83) Adult Services 15,587 15,587 Communities & Housing 141,602 142,282 680 Total General Fund 399,894 400,490 680 (83) HRA 73,736 73,736 Completed Schemes 46,272 45,954 (319) Total Existing Programme 519,902 520,180 680 (402)
Table 2 - Capital Programme funding
Funded Total Funding Additional Revised to Funding still Funding Total 31/3/19 Required required Required Funding £000's £000's £000's £000's £000's Capital Receipts 7,294 5,014 2,280 (650) 6,644 Section 106 Deposits 24,361 7,474 16,887 650 25,011 Grant Funding 180,173 38,427 141,746 (83) 180,090 Revenue Contributions 2,054 127 1,927 2,054 HRA balances 78,752 24,629 54,123 78,752 Salix funding (Interest free loan) 6,972 6,972 6,972 Invest to save borrowing repaid 5,916 5,916 5,916 from future revenue budgets Increase in Borrowing 214,380 47,012 167,368 361 214,741 Requirement Total to be financed 519,902 122,683 397,219 278 520,180
Projected Variances 3.2 Cabinet is asked to note the following new variances to projects within the capital programme. Appendix 1 contains a summary of the current capital programme & Appendix 2 contains the details of the individual schemes in the capital programme, together with their forecast closing position.
Further information on the subject of this report can be obtained from Ian Burbidge on Direct Dial No. [phone removed] or Email [email protected] Capital Monitoring Quarter 3 2019/20 Cabinet Date: 22nd April 2020
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.