Resolved – (1) That the Director of Housing be authorised to design and carry out a consultation to complete the construction of 64 units at Windmill Hill site at an estimated cost of £15.1 million, (2) That the Director of Housing be authorised to complete the construction of the Queens Drive Regeneration at a cost of £34 million, (3) That the Director of Housing be authorised to design and carry out a consultation on a development on land at Bromley Close . The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: MP)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Affordable Housing Development Programme Cabinet Date: 22nd April 2020
Author: Cabinet Member for Housing & Public Safety Director of Housing Wards: Lydiard and Freshbrook, Liden, Eldene, and Park South, Walcot and Park North Parishes Affected: Central Swindon South, West
1. Purpose and Reasons 1.1 The report sets out the current position of the Affordable Housing Development Programme and emerging projects and to seek approval for the Director of Housing to be authorised to use Housing Revenue Account resources to develop sites set out in the report. 1.2 This supports the strategic priorities of making the best use of Swindon’s resources inside the Borough. 1.3 These developments links to Priority One to improve infrastructure and housing to support a growing, low carbon economy and Pledge 6f “Ensure that there is a range of good quality housing options in Swindon, including affordable opportunities to buy and rent”. 2. Recommendations Cabinet is recommended to: 2.1 The Director of Housing is authorised to design and carry out a consultation to complete the construction of 64 units at Windmill Hill site at an estimated cost of £15.1 million 2.2 The Director of Housing is authorised to complete the construction of the Queens Drive Regeneration at a cost of £34 million 2.3 The Director of Housing is authorised to design and carry out a consultation on a development on land at Bromley Close. 3. Detail Windmill Hill 3.1 Approval for the allocation of the land at Windmill Hill was previously agreed at Cabinet (Cabinet Minute 51, 2019/20 refers) 3.2 Following further feasibilities an indicative scheme has been produced. The scheme comprises of 64 units. 15 x 1 bed flats, 15 x 2 bed flats, 7 x 1 bed bungalows and 27 x 3 bed houses.
Further information on the subject of this report can be obtained from Mike Ash, Direct 01793 464402, [email protected]. Affordable Housing Development Programme Cabinet Date: 22nd April 2020
3.3The total estimated cost is £15.1m. £10.9m of this is construction costs. The remainder is made up of client costs, design fees, site clearance costs and a HRA client contingency of £1.5m. The estimated cost also includes a provision of £0.98m to cover inflation based on BCIS Indices. The Building Cost Information Service, known as BCIS is a provider of cost and price information for the UK construction industry. The BCIS Indices are used for adjusting estimates and budgets to different dates. 3.4 The current Government Shared Ownership and Affordable Housing Programmes expires in March 2021, however the Government is highly likely to continue the programme beyond 2021. The Council will therefore apply for grant to development these homes. 3.5 Subject to approval at Cabinet, a Planning Application will be submitted in February 2021, with approval in July 2021. Start on site is expected in December 2021, with completion in May 2023. 3.6 The table below shows the funding model and the payback period for the Windmill Hill development. The model requires additional funding in terms of the use of existing services and the conversion of existing social rented properties to affordable rents. This is due to rentals from the new units not being sufficient to cover the additional borrowing needed to build them.
HRA Reserves £2,000,000.00
Homes England Grant & Sales £4,873,100.00
Borrowing £8,226,900.00
Total £15,100,000.00
No.of conversions to Affordable 40 Rent
Payback period in years 41
Queens Drive 3.7 Approval for the regeneration of Queens Drive was previously agreed at Cabinet (Cabinet Minute 87 2017/18 refers). 3.8 The revised total estimated cost is £34m. £28m of this is construction cost. The remainder is made up of client costs, design fees, demolition costs and a HRA client contingency of £2m. The estimated cost also includes a provision of £1.5m to cover inflation (BCIS Indices
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.