Resolved
Resolved - That the risk management approach and the risks captured in the Corporate Risk Register be endorsed.
Audit Committee decided this item on Tuesday 6 June 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - That the risk management approach and the risks captured in the Corporate Risk Register be endorsed.
The Committee is recommended to:
2.1Endorse the risk management approach and the risks captured in the Corporate Risk Register.
3. Detail
3.1Appendix One is a copy of the Corporate Risk Register May 2023 and is the basis of discussion for this report.
3.2Since the last report to Audit Committee in July 2022 the Corporate Risk Register has been refreshed in terms of content. There have been a number of internal updates including a risk workshop in November 2022, a full update in March 2023 and an updated in May 2023 which forms the basis of discussion for this report.
3.3Risk continues to be an intrinsic part of the monthly discussions focussing on risk and performance in the context of the Corporate Management Team’s focus on improvement.
3.4Council wide and Directorate scorecards capture in one document the key performance and risk information. Corporate Directors present their scorecards to Corporate Management Team monthly which ensures that there is peer scrutiny on discussions around performance and risk. The focus is on mitigating actions to reduce the risk and the efficacy of those actions.
Further information on the subject of this report can be obtained from Martin Bell, [phone removed], [email protected]. Corporate Risk Management Update Audit Committee Date: 6 June 2023
3.5Corporate and Directorate risks are identified from an understanding of risks at service level.
3.6Discussions also take place between Internal Audit and Risk. The Internal Audit team requests copies of risk registers to inform their audits. Audit findings can then be captured in the Corporate Risk Register. Audits of concern are presented on the scorecards at all levels so that they form a part of discussions around performance and risk.
3.7The Corporate Risk Register focusses on key corporate risks. All risks are owned by a Director which reinforces accountability for risk.
3.8In line with the Council Plan 2022 – 2025, the Corporate Risk Register covers risks by Priority One to Six then Modern, Efficient & Effective and supporting strategies. As a result in change of Administration after the local elections in May 2023, the Priorities and Pledges will be updated in line with the new Administration’s manifesto and the risk register will be updated to reflect these when it is next brought to Audit Committee.
3.9Risk is assessed by both Likelihood and Impact. The risk register then has mitigating actions that will reduce the likelihood and impact and covers the progress that the Council is making with those actions.
3.10Table 1: Corporate Risk Register ratings
July 2022 Rating May 2023 Rating
Risk Area Previous Previous Impact Current Current Likelihood Rating Rating Likelihood Impact Rating Rating
Priority One – Build High High High High an economy that works for you
Priority Two – Medium Medium Medium Medium Protect and enhance our heritage, cultural and leisure facilities
Priority Three – High High High High Deliver sustainable growth
Further information on the subject of this report can be obtained from Martin Bell, [phone removed], [email protected]. Corporate Risk Management Update Audit Committee Date: 6 June 2023
July 2022 Rating May 2023 Rating
Risk Area Previous Previous Impact Current Current Likelihood Rating Rating Likelihood Impact Rating Rating
Priority Four – High High High High Equip all our young people with the education and skills they need
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Risk Register: May 23Appendix 1 | 865 KB | Download |
PDF |
Corporate risk registerReport | 288 KB | DownloadRead as text |
Follow Audit Committee at Swindon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jun 2026 | MinutesThat the minutes of the previous meeting held on 17 March 2026 be confirmed as true record and signed by the Chairman | Decided | Open |
| 23 Jun 2026 | Corporate Risk Management UpdateThat (i) the risk management approach and the risks escalated in the Corporate Risk Register be endorsed (ii) a furth... | Decided | Open |
| 23 Jun 2026 | Audit Committee Annual ReportThat the report be noted | Noted | Open |
| 23 Jun 2026 | Head of Internal Audit Annual Report 2025/26 and OpinionThat the report be noted | Noted | Open |
| 23 Jun 2026 | Audit Committee Terms of ReferenceThat (i) the revised terms of reference attached at appendix 1 to the report be approved. (ii) The enhanced responsib... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.