Swindon Borough Council
Cabinet, Thursday 8 October 2026

Swindon 2028 Transformation Programme Update

Noted Executive 4 papers

AI summarySwindon Cabinet noted progress and next-phase priorities for the Swindon 2028 Transformation Programme, including a forecast £0.265m shortfall this year and £3.806m next year, mitigated by £5.865m of anticipated savings over four years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgress, governance and next-phase priorities
MoneyNot stated
What happens nextShift to delivery in 2026/27Integrated locality working planned from April 2027
Who it affectsCouncil services, residents, workforceStatutory services, digital, assets, community hubs

What was decided

Cabinet noted the progress made over the last year of the Swindon 2028 Transformation Programme, including £875k of savings delivered through Commissioning and Procurement and Housing and Health. Report 2.1, P18

Cabinet noted the programme design and progress across the workstreams, alongside the assurance, governance and Programme Management Office arrangements supporting delivery. Report 2.2, 2.3

Cabinet noted the priorities for the next phase, with increased focus on delivery, measurable outcomes, benefits realisation, financial sustainability, and closer alignment with the future Council Plan and Medium-Term Financial Plan. Report 2.4, 2.5

Why

The programme aims to improve outcomes for residents, modernise service delivery and create a more financially sustainable organisation through earlier intervention, better use of technology and assets, and a stronger workforce. Report P15, 3.3

The 2025/26 year focused on turning ambition into action and establishing the foundations, with the programme now judged to have moved beyond mobilisation into delivery. Report 3.1, 3.6

Initial analysis of the Resident Experience workstream identified approximately 573,000 phone calls a year, with around 65% bypassing the managed contact centre, indicating significant avoidable demand. Report P35, P36

What happens next

During 2026/27 the Council will develop a more integrated approach aligning transformation with the future Council Plan and Medium-Term Financial Plan, and strengthen outcome measurement and benefits realisation. Report 3.8, P90

Phased implementation of integrated locality working through Community Hubs is planned from April 2027, using a test, learn and grow approach. Report P44

Workforce planning, organisational redesign and the Resident Experience Programme will continue, with a Resident Experience business case already approved in April 2026. Report P34, P55, P54

The money

  • £875k Savings delivered via Commissioning and Procurement and Housing and Health Report P18
  • approximately £1 million a year (recurring) Potential financial benefits from the Resident Experience Programme Report P40
  • £0.265m Forecast programme shortfall this year Report P91, P93
  • £3.806m Forecast programme shortfall next year Report P91, P93
  • £5.865m Anticipated savings over the following four years to mitigate the shortfall Report P91, P93

Options considered

  • Chosen: Note progress, governance and next-phase priorities (as recommended). The case for change sets out the means of delivering savings, addressing budget pressures and redesigning services. Report 4.1

Implications

  • Financial: No direct financial implications from this report; programme-level financial implications will flow through future budget and MTFP work. Report 5.1
  • Financial: Programme currently forecasts a £0.265m shortfall this year and £3.806m next year, mainly from the At Our Best strand, with mitigation through Commissioning, Procurement and Contract Management savings. Report P91, P93
  • Legal: No specific legal implications arise from this report; legal advice will be sought on individual proposals as they are developed. Report 5.2
  • Equalities: Equalities Impact Assessments will be produced as part of planning for implementation. Report 5.5
  • Climate: Carbon reduction requirements and mitigations will be worked through as the implementation plan is developed and brought back for Cabinet Member consideration. Report 5.3
  • Risk: Each workstream will maintain a risk register and delivery controls, with accountability resting with Executive Sponsors and Senior Responsible Officers and oversight by the Strategic Transformation Board. Report 5.6
  • Staffing: Significant organisational redesign and improved workforce planning are underway to align structure, skills and resources to future priorities and financial sustainability. Report P22, P54, P55

Who and where

  • Residents of Swindon, who stand to benefit from redesigned services, Community Hubs, improved digital access and earlier intervention. Report P19, P37, P43
  • Council workforce, subject to new organisational values, the Swindon Commitment, refreshed performance and development approaches, and ongoing organisational redesign. Report P51, P52, P53, P22
  • Children, young people and families, through Children's Services improvement, SEND Local Area Improvement Programme and Families First Partnership reforms in 2026 and 2027. Report P66, P67, P68, P70
  • Council tenants, through the Housing improvement programme reported separately to Cabinet in July 2026. Report P71
  • Partners across education, health, care and the wider public sector, through strengthened partnership working and integrated locality arrangements. Report P19, P46, P68

Timeline

  • 2025/26: Last year of the Swindon 2028 programme, focused on turning ambition into action and establishing foundations. Report 3.1
  • April 2026: Resident Experience Programme business case approved by the Strategic Transformation Board. Report P34
  • October 2026: Cabinet considers this programme update. Report P9, 9.1
  • 2026/27: Further work to develop an integrated approach linking transformation with the future Council Plan and MTFP. Report 3.8
  • April 2027: Planned phased implementation of integrated locality working through Community Hubs. Report P44

Plain English for the jargon

  • Swindon 2028: The Council's long-term transformation programme covering multiple interconnected workstreams.
  • MTFP: Medium-Term Financial Plan, the Council's multi-year financial planning document.
  • Strategic Transformation Board: Governance body providing strategic direction and oversight of the transformation programme.
  • Programme Management Office (PMO): Team providing coordination, challenge and direct project support across the transformation portfolio.
  • Community Hubs: Local access points where residents can get advice, information and support closer to home, used to test prevention and early intervention approaches.
  • At Our Best: Workstream covering organisational values, the Swindon Commitment, leadership, performance, workforce development and organisational redesign.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

Non-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the progress made over the last year of the Swindon 2028 Transformation Programme be noted. (2) That the programme design and progress across the transformation workstreams be noted. (3) That the assurance, governance, and Programme Management Office arrangements in place to support delivery be noted. (4) That the priorities for the next phase of the programme, including an increased focus on delivery, measurable outcomes, benefits realisation and financial sustainability be noted. (5) That the intention to increasingly align the Council’s transformation programme with the development of the future Council Plan and Medium-Term Financial Plan, ensuring strategic priorities, transformation activity and financial planning are considered as part of a coherent approach be noted. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM:KT)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet

Recommendations

Cabinet is recommended to:

2.1Note the progress made over the last year of the Swindon 2028 Transformation Programme.

2.2Note the programme design and progress across the transformation workstreams.

2.3Note the assurance, governance, and Programme Management Office arrangements in place to support delivery.

2.4Note the priorities for the next phase of the programme, including an increased focus on delivery, measurable outcomes, benefits realisation and financial sustainability.

2.5Note the intention to increasingly align the Council’s transformation programme with the development of the future Council Plan and Medium-Term Financial Plan, ensuring strategic priorities, transformation activity and financial planning are considered as part of a coherent approach.

3. Detail

Delivery progress and assessment of the last year of the Swindon 2028 Transformation Programme

Further information on the subject of this report can be obtained from Danielle Maundrell, [email protected] . Swindon 2028 Transformation Programme Update Cabinet Date: 8th October 2026

3.1The last year (2025/26) of the Swindon 2028 Transformation Programme focused on turning ambition into action and establishing the foundations required to support long- term transformation.

3.2The programme made significant progress over the last year. The programme has established and put in place the foundations needed to support long-term transformation across the Council:

3.2.1 governance arrangements have been strengthened with the establishment of the Strategic Transformation Board, enhanced programme management arrangements, and clearer accountability for delivery across workstreams – all enabling robust oversight of progress, risks, dependencies and benefits across the programme

3.2.2 major programmes have been mobilised

3.2.3 several key initiatives have moved from strategy and design into implementation

3.2.4 The Swindon 2028 Transformation Programme is delivered through a series of interconnected workstreams. Each has its own objectives and delivery plan, and they are designed to work together to deliver the Council's wider ambition of improving outcomes for residents, modernising the way services are delivered and creating a more financially sustainable organisation.

3.3Progress in one workstream enables and supports progress in others. Together they are helping the Council shift towards earlier intervention, improve the experience of residents, strengthen organisational capability, make better use of technology and assets, and ensure resources are targeted where they can have the greatest impact.

3.4Notable delivery progress includes:

3.4.1 savings of £875k delivered via Commissioning and Procurement and Housing and Health

3.4.2 advancement of the Prevention and Early Intervention approach including development of Community Hubs within local communities, creating easier access to support and helping to test new approaches to prevention, partnership working and earlier intervention

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Digital Data Technology Strategy 2026-2029Appendix 1 3.4 MB Download
PDF
Finance Transformation ReportAppendix 2 46 KB Download
PDF
Resident Experience Business CaseAppendix 3 1.8 MB Download
PDF
Swindon 2028 Transformation Programme UpdateReport 345 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 16 attended
GS
Councillor Gary SumnerChair, expected
JC
Councillor Jake ChandlerVice-Chair, expected
MC
Councillor Matty CourtliffMember, expected
NG
Councillor Nick GardinerMember, expected
MH
Councillor Matt HintonMember, expected
VM
Councillor Vinay ManroMember, expected
KP
Councillor Kevin ParryMember, expected
KT
Councillor Kate TomlinsonMember, expected
MV
Councillor Matthew VallenderMember, expected
KW
Councillor Keith WilliamsMember, expected
KB
Kevin BurchallOfficer, expected
SM
Sam MowbrayOfficer, expected

All 16 on the meeting page

On this subject at Swindon

Search all
  1. Swindon 2028 Transformation Programme UpdateThis decision
  2. Swindon 2028 Transformation Programme - Update on Prevention, Early Intervention and Community HubsNoted
  3. Swindon 2028 Transformation Programme - UpdateNoted
  4. Swindon 2028 Transformation Plan - Case for ChangeAgreed
  5. Swindon's Transformation Plan for Children and Young People's Mental Health and Well Being - 2017 to 2020Noted
  6. NHS Swindon Clinical Commissioning Group Sustainability and Transformation PlanNoted

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open