Swindon Borough Council
Cabinet, Wednesday 4 February 2026

Swindon 2028 Transformation Programme - Update

Noted Executive 1 paper

AI summarySwindon Cabinet noted the design and progress of the six-workstream Swindon 2028 Transformation Programme, with a first Community Hub prototype due in February 2026 and £8.9m further savings proposed for 26/27 to 27/28.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSix workstreams now in mobilisation or delivery
Money£8.9m proposed savings 26/27-27/28Set out in the budget report on this Cabinet agenda
What happens nextNot stated
Who it affectsCouncil workforce and Swindon residentsSix workstreams cover culture, services, digital, assets

What was decided

Cabinet noted the Transformation Programme Design, covering six workstreams aligned to the Future Operating Model and Swindon 2028 Plan. Report 2.1

Cabinet noted the implementation of the refreshed governance framework and Programme Management Office arrangements supporting programme delivery.

Cabinet noted progress to date across the six workstreams and the planned next steps for the coming months.

Why

Since the Case for Change was agreed in summer 2025, the programme has moved at pace from concept into mobilisation and early implementation. Report 3.1

At Our Best is delivering under the strategy approved by Cabinet in December 2025, and the first Community Hub prototype is due to launch in February 2026. Report P6

The Council has savings plans totalling over £230m since 2010, so further service budget reductions alone are not expected to have sufficient impact.

What happens next

Launch the first prototype Community Hub at Park Library in February 2026 using a shape, test and learn approach with communities and partners.

Move Resident Experience workstream delivery at pace from February 2026, alongside foundational data and digital work supporting all workstreams.

Each workstream will present opportunities, savings and enabling requirements to the Transformation Board, with full visibility for Cabinet.

The money

  • £15.8 million Indicative target savings identified in the original Case for Change Report 5.2
  • £3m Additional investment to deliver the programme, approved at Cabinet on 12th February 2025 Report 5.2
  • £1.426m Agreed 2025/26 savings targets for approved Housing Care and Homelessness and Commissioning, Procurement and Contract Management business cases Report 5.7
  • £8.9 million Further proposed savings over 26/27 and 27/28, set out in the Budget report on this agenda Report 5.7
  • £55m Estates and Assets capital receipts Report P73
  • (0.8) (0.8) Indicative savings profile for Housing, Care and Homelessness (in £m) Report P67, 5.5
  • (0.6) (1.0) (1.0) (2.6) Indicative savings profile for Commissioning, Procurement and Contract Management (in £m) Report P69, 5.5
  • (2.5) (2.7) (5.2) Indicative savings profile for At Our Best or Future Council (in £m) Report P70, 5.5

Options considered

  • Chosen: Deliver the transformation programme as set out. It is the means of delivering savings to address budget pressures and redesigning services to meet resident needs. Report 4.1, 3.1
  • Rejected: Pursue further reductions to service budgets rather than transform. With savings plans totalling over £230m since 2010, further reductions in this way are not expected to have sufficient impact.

Implications

  • Financial: No financial implications arise from this report; financial implications of Swindon 2028 will be included in budget development and future reports. Report 5.1
  • Staffing: The Council is reshaping the organisation and reducing overall workforce costs during 2026, while protecting essential frontline services. Report 3.13, P12
  • Risk: Each workstream will maintain a clear risk register and delivery controls, with accountability on Executive Sponsors and Senior Responsible Officers and oversight by the Strategic Transformation Board. Report 5.12
  • Equalities: EQIAs will be produced as part of the planning process for the implementation plan. Report 5.11
  • Climate: Officers will work through carbon reduction requirements and bring mitigating proposals to the Cabinet Member as part of future business cases. Report 5.9
  • Legal: No specific legal implications arise from this report; legal advice should be sought on individual proposals as they are developed. Report 5.8
  • Other: All other implications (staff, sustainability, health, rural, crime and disorder) of the implementation plan will be considered as they are developed. Report 5.10

Who and where

  • Swindon Borough Council workforce, through right-sizing and the At Our Best strategy Report 3.13, P12, P13
  • Residents of Swindon, through redesigned services and Community Hubs Report P16, P20, P24
  • Children, adults and families using integrated Community Hub support, including the Family First Partnership and Best Start offer Report P16
  • Users of Children's Social Care, SEND and Housing services within the Improving Core Services workstream Report P26
  • Suppliers and partners engaging with Commissioning, Procurement and Contract Management Report P39

Timeline

  • 11th December 2024: Original Case for Change for Swindon 2028 presented to Cabinet Report 5.2
  • 12th February 2025: Cabinet approved £3m additional investment to deliver the programme Report 5.2
  • Summer 2025: Cabinet considered the Case for Change Report 3.1
  • July 2025: Case for Change agreed by Cabinet
  • December 2025: At Our Best strategy approved by Cabinet Report P6
  • February 2026: First prototype Community Hub due to launch at Park Library
  • 2026: Phased delivery of workforce reshaping under the At Our Best workstream Report 3.13

Plain English for the jargon

  • PMO: Programme Management Office, providing standards, processes and assurance across the programme
  • SRO: Senior Responsible Officer, leading operational delivery of a workstream
  • PEI: Prevention and Early Intervention, the workstream developing Community Hubs
  • SEND: Special Educational Needs and Disabilities
  • EQIA: Equality Impact Assessment, to be produced as the implementation plan develops
  • One SBC: A consistent framework for culture, leadership, skills and colleague experience set out in the At Our Best strategy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item64

Resolved

Non-key Decision Following consideration of the report Cabinet resolved: (1) That the Transformation Programme Design, including the six workstreams aligned to the Council’s Future Operating Model and Swindon 2028 Plan, be noted. (2) That the implementation of the refreshed governance framework and Programme Management Office arrangements supporting programme delivery be noted. (3) That the progress to date across the six workstreams and the planned next steps for the coming months be noted. The reasons for the decision and alternative options are as set out in the report to the meeting.
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 11 pages

Recommendations

Cabinet is recommended to:

2.1Note the Transformation Programme Design, including the six workstreams aligned to the Council’s Future Operating Model and Swindon 2028 Plan. 2.2 Note the implementation of the refreshed governance framework and Programme Management Office arrangements supporting programme delivery. 2.3 Note progress to date across the six workstreams and the planned next steps for the coming months.

3. Detail

Swindon 2028 Programme design

3.1Since Cabinet considered the Case for Change in summer 2025, the Swindon 2028 Transformation Programme has moved at pace from concept into mobilisation and early implementation. A clear programme design is now in place, supported by refreshed governance and Programme Management Office arrangements, providing the structure, discipline and assurance needed to deliver change at scale across the Council. 3.2 Real progress has been made in the programme’s early priority areas. At Our Best is now actively reshaping how the Council is organised, led by the strategy approved by Cabinet

Further information on the subject of this report can be obtained from Sonia Grewal, [email protected]. Swindon 2028 Transformation Programme - Update Cabinet Date: 4th February 2026

in December 2025, with delivery underway to strengthen culture, leadership, skills and workforce alignment. In parallel, Prevention and Early Intervention has moved into delivery, with the Community Hub model developed and the first prototype hub launching in February 2026. Together, these workstreams demonstrate a clear shift towards a more prevention-focused, resident-centred and financially sustainable way of working. 3.3 The programme provides a clear and coherent framework for delivering the Council’s Future Operating Model, which underpins the ambitions set out in the Swindon 2028 Plan – a fairer, better, greener borough for all. Building on the Case for Change agreed by Cabinet in July 2025, Swindon 2028 is now translating that intent into coordinated, Council-wide delivery focused on stronger financial resilience and improved outcomes for residents.

Fig 1 – Swindon 2028 programme design

3.4The programme is organised into six workstreams. Each workstream has a defined purpose and scope, describing what will be different for residents and how services and supporting functions need to change to enable those improvements. The six workstreams are: 3.5 At Our Best:

• The At Our Best workstream is focused on developing an organisation and workforce that is structured, resourced and supported in a way that enables high- quality, affordable services for residents.

Further information on the subject of this report can be obtained from Sonia Grewal, [email protected]. Swindon 2028 Transformation Programme - Update Cabinet Date: 4th February 2026

• This includes work to right-size the Council through a review of workforce structure, ensuring teams are designed around resident needs and priorities, rather than legacy arrangements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Swindon 2028 Transformation Programme: UpdateReport 11 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Swindon

Search all
  1. Swindon 2028 Transformation Programme - UpdateThis decision
  2. Swindon 2028 Transformation Programme UpdateNoted
  3. Swindon 2028 Transformation Programme - Update on Prevention, Early Intervention and Community HubsNoted
  4. Swindon 2028 Transformation Plan - Case for ChangeAgreed
  5. Swindon's Transformation Plan for Children and Young People's Mental Health and Well Being - 2017 to 2020Noted
  6. NHS Swindon Clinical Commissioning Group Sustainability and Transformation PlanNoted

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open