AI summaryTeignbridge scrutiny committee approved the Play Parks Improvement Strategy Equalities Impact Assessment without amendment and referred it to full Council for decision in July 2026.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo amendments to EIA report
MoneyNot stated
What happens nextFull Council in July 2026Consider recommendations in report
Who it affectsPlay park users across districtTen Teignbridge settlements
What was decided
The Committee made no amendments to the Equalities Impact Assessment and referred it to Council unamended with the recommendations as set out in the report. [D]
The Committee adjourned for a short comfort break and then reconvened. [D]
Why
The assessment covered the One Teignbridge Play Parks Improvement Strategy 2025-2030, which aims to improve the quality, safety, accessibility and inclusivity of council-owned play parks using Section 106 and Community Infrastructure Levy funding. [1.1, P7] Report 1.1, P7
Officers identified likely positive impacts for children, young people, disabled users, parents and carers, and higher-need communities, alongside risks of uneven investment, temporary access loss and inconsistent accessibility. [P12, P27] Report P12, P27
The assessment concluded that overall the programme is expected to deliver significant community and organisational benefits and support the Public Sector Equality Duty. [P69, 4.1] Report P69, 4.1
What happens next
Full Council will consider the report and recommendations in July 2026. [2.5] Report 2.5
Officers will prepare a consultation and engagement plan by 1 July 2026 and contact ward members and town or parish councils in the ten affected settlements. [P72, 2.5] Report P72, 2.5
Officers will review equality impacts within 12 months of the first works completing and will include accessibility and inclusive design requirements in project briefs. [P72] Report P72
Options considered
Rejected: Make amendments to the EIA report before referral to Council. Committee chose to refer the report unamended with the recommendations as set out in the report. [D]
Chosen: Refer the EIA report to Council unamended
Implications
Equalities: Programme expected to improve access to safer, more inclusive play parks and reduce inequality in access to free local recreation, particularly for children, disabled users and higher-need communities. [P69] Report P69
Financial: Prioritising Community Infrastructure Levy for play park investment reduces flexibility in the use of CIL funding and may delay or displace other infrastructure projects. [4.1] Report 4.1
Risk: Risks include uneven investment outcomes, temporary park closures during refurbishment, perceptions of unfairness between communities, and pressure on staff capacity. [P27, 4.1] Report P27, 4.1
Staffing: Delivery of the programme places additional pressure on staff capacity and may divert resources from other priorities. [4.1] Report 4.1
Other: Asset transfers may reduce long-term costs to the council but could create additional burdens for town and parish councils. [4.1] Report 4.1
Who and where
Children, young people and families Report P31
Disabled users, parents and carers Report P35, P42
Communities in higher-need or deprived areas Report P12, P58
Older people, including dementia-friendly users Report P33
Women and girls using parks Report P38
Rural communities Report P60
Town and parish councils in Ashburton, Buckfastleigh, Chudleigh, Dawlish, Exminster, Heathfield, Kingsteignton, Newton Abbot, Starcross and Teignmouth Report 2.5
Timeline
21.05.26: EIA reviewed by Service Manager Report P78
10.6.2026: EIA signed off by Director of Place Report P78
16 June 2026: Overview and Scrutiny Committee considered the EIA
July 2026: Full Council to consider the report Report 2.5
Within 12 months of first works completing: Review of equality impacts Report P72
2025-2030: Programme period for the Play Parks Improvement Strategy Report P1
By 1 July 2026: Consultation and engagement plan to be prepared Report P72
Plain English for the jargon
EIA: Equality Impact Assessment, a structured assessment of how a proposal may affect people with protected characteristics.
CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure.
Section 106: Developer contributions for local infrastructure, under Section 106 of the Town and Country Planning Act 1990.
ASB: Anti-social behaviour.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED The Committee makes no amendments to the report, and it is referred to Council for consideration unamended with the recommendations as set out in the report. At this juncture the Committee adjourned for a short comfort break. The Committee reconvened.
Word for word from the decision Teignbridge published for this meeting.Source: democracy.teignbridge.gov.uk
Equality Impact Assessment Assessment of: One Teignbridge Council Teignbridge Play Parks Improvement Strategy, 2025-2030 Programme
☐ Policy ☐ Strategy ☐ Function ☐Service ☒ New ☒ Other - Project ☐ Already exists / review ☐ Changing Directorate: Place Assessment carried out by: Sammi Early
Service Area: Strategy and Partnerships Job Role: Strategic Infrastructure and Growth Officer
Version / Date of Sign Off by Director: Draft / May 2026
Step 1: What do we want to do? This assessment should be started at the beginning of the process by someone with a good knowledge of the proposal and service area, and sufficient influence over the proposal. It is good practice to take a team approach to completing the equality impact assessment. Please contact the Policy Officer early for advice.
1.1What are the aims and objectives/purpose of this proposal? Briefly explain the purpose of the proposal and why it is needed. Describe who it is aimed at and the intended aims / outcomes. Where known also summarise the key actions you plan to undertake. Please use plain English, avoiding jargon and acronyms. Equality Impact Assessments are viewed by a wide range of people including decision-makers and the wider public. The proposal is to deliver a district wide programme of improvements to Council owned play parks that are most in need of investment.
It aims to improve the quality, safety, accessibility and inclusivity of play provision for children, young people, families and local communities, using available Section 106 and Community Infrastructure Levy funding within the timescales attached to those funds.
Parks will be prioritised using evidence on condition, local need, accessibility, anti-social behaviour and gaps in provision, with works delivered either through direct investment, asset transfer arrangements or other agreed delivery routes.
1.2Who will the proposal have the potential to affect? ☒ Service users ☒ The wider community ☐ Teignbridge workforce
1.3Will the proposal have an equality impact? Could the proposal affect access levels of representation or participation in a service, or does it have the potential to change e.g., quality of life: health, education, or standard of living etc.? If ‘No’ explain why you are sure there will be no equality impact, then skip steps 2-4 and request review by your manager. If ‘Yes’ complete the rest of this assessment.
☒ Yes ☐ No
Yes. The proposal affects access to safe, inclusive and good quality play parks, and therefore has the potential to affect how different groups benefit from local provision. It is likely to have positive impacts for children and young people, disabled users, parents and carers, and communities in higher-need areas. Risks include uneven investment because of limited funding, inconsistent accessibility if inclusive design is not built in from the outset, and temporary loss of access while works are taking place.
Step 2: What information do we have?
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Update on task and finish groupsRESOLVED a) The MTFP Review group update be received and endorsed. b) Consideration of the draft Terms of Reference f...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.