Cabinet Members' Items - Report of the Economic Growth, Regeneration & Tourism Portfolio Holder - A.4 - Orwell Place Car Park and Event Space, Dovercourt: Post Project Review
DecidedExecutive1 paper
Cabinet decided this item on Friday 21 February 2025. Below is the council's own wording, with the papers it was decided on.
RESOLVED that Cabinet: a) notes this post project review of Orwell Place and endorses the learning points as set out in Appendix A of the Portfolio Holder’s report (A.4), to inform future capital projects; b) requests the Leader of the Council to ensure that key messages from the aforementioned Appendix A, are clearly documented within the Council’s Annual Governance Statement, as expected by the Best Value Duty Statutory Guidance; and c) invites the Overview and Scrutiny Committees to consider including the outcome of this review on their work programmes to provide additional scrutiny of the performance and lessons learnt.
Word for word from the decision Tendring published for this meeting.Source: tdcdemocracy.tendringdc.gov.uk
REPORT OF THE PORTFOLIO HOLDER FOR ECONOMIC GROWTH, REGENERATION AND TOURISM
A.4 ORWELL PLACE CAR PARK AND EVENT SPACE, DOVERCOURT: POST PROJECT REVIEW
PART 1 – KEY INFORMATION
PURPOSE OF THE REPORT To present a post project review of Orwell Place Car Park and Event Space for consideration by Cabinet, and to provide an update on the regenerated site in Dovercourt Town Centre since opening in September 2023.
EXECUTIVE SUMMARY Dovercourt suffered from a generic decline in the popularity of English seaside towns and therefore in 2018 the Council commissioned a regeneration plan for the town called ‘Dovercourt Revisited’ to set out a vision seeking to secure Dovercourt as: a thriving town with an attractive High Street, a range of shops and cafes and regular street markets: a town which is proud of its heritage but also able to respond to new opportunities. A town with a high-quality public realm and open spaces, stunning beaches and good connections – an attractive place to live, work, shop and visit.
Orwell Place Car Park is the first phase of the Dovercourt Revisited plan, supporting the town to grow to its full potential and will support future projects in the process of being developed which include.
1. Kingsway improvements: A major investment into the appearance of Dovercourt Town Centre. 2. Library project: The Adult Community Learning skills centre will return to the area within a refurbished library. 3. Milton Road: Demolish the out-of-date multi-storey car park at Milton Road and provide an attractive and safe ground level car park to compliment Orwell Place. 4. Victoria Street: Demolish a dangerous structure and redevelop 8 new social homes.
Further opportunities are currently being delivered through the High Street Accelerator Pilot Scheme (HSA) which has provided seed funding of £237,000 and green space funding of £500,000. Dovercourt High Street was chosen as one of ten high streets receiving funding from the HSA Pilot Programme which was announced in March 2023 as part of the Anti-Social Behaviour (ASB) Action Plan.
Schemes within the HSA include shop front grants, a pop-up shop, improved wayfinding, shop wrapping, a new website and events. The green spaces proposal currently being designed by a team of award-winning urban designers, will link the high street, beach and the Kingsway Improvements Projects enhancing the public realm offer to the community.
The ‘Starlings’ site redevelopment was advocated in Dovercourt Revisited, approved by Cabinet in July 2019. Dovercourt Revisited proposed a redevelopment of the with new animated public space, public toilets, and a surface car park with the capacity to accommodate 59 car parking spaces, with six of designated for disabled use.
On the 13 September 2019, Cabinet allocated £1.599m from existing Council resources to the redevelopment of the Starlings site in Dovercourt Town Centre and the demolition of the Milton Road Car Park and 15 parking spaces in Bagshaw Road. The delivery proposed redevelopment of the Starlings site first, to create new parking and then demolish Milton Road Car Park.
Following provisional completion of the project, Orwell Place Car Park was opened in September 2023 on the site of the former derelict Starlings Site in Dovercourt High Street with a revised 53 parking spaces in total; eight with electric vehicle charging, and eight disabled bays which host two of the electric chargers. Essex County Highways are still to sign off the entranceway and so completion of the final account with contractors remains outstanding, which will determine the final cost of the project. The Council has allocated a total of £2,541,050 to the project and there is currently a forecast underspend.
The project was completed during the post-pandemic surge in the cost of capital works, and significant ground contamination was discovered, as well as the following challenges:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Cabinet Members' Items: Report of the Economic Growth, Regeneration & Tourism Portfolio Holder: A.4: Orwell Place Car Park and Event Space, Dovercourt: Post Project ReviewReport
131Cabinet Members' Items - Report of the Economic Growth, Regeneration & Tourism Portfolio Holder - A.4 - Orwell Place Car Park and Event Space, Dovercourt: Post Project ReviewThis decision
Cabinet Members' Items - Report of the Economic Growth, Regeneration & Tourism Portfolio Holder - A.4 - Orwell Place Car Park and Event Space, Dovercourt: Post Project ReviewThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.