Item350
Resolved
Recommended to Council: 1. That the new capital schemes with a total cost of £3,185,500, as shown in Annex 2 to the report, be added to the 2022/23 to 2024/25 Capital Programme. 2. That the revised estimates and financing for the 2022/23 to 2024/25 Capital Programme, as shown in Annex 1 to the report, be approved. 3. That up to £80,000 be added to the revenue budget with effect from 2025/26 to reflect the anticipated costs of the East Anton sports facility.
Word for word from the decision Test Valley published for this meeting.
Source: democracy.testvalley.gov.uk