Resolved
It was AGREED that the minutes of the meeting of the Group held on 18 July 2013 be approved and signed by the Chairman as a correct record.
Pleasurama Site Development Review Task & Finish Group agreed this item on Thursday 29 August 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
It was AGREED that the minutes of the meeting of the Group held on 18 July 2013 be approved and signed by the Chairman as a correct record.
PLEASURAMA SITE DEVELOPMENT REVIEW TASK & FINISH GROUP
Minutes of the meeting held on 18 July 2013 at 7.00 pm in the Council Chamber, Council Offices, Cecil Street, Margate, Kent.
Present: Councillor Hornus (Chairman); Councillors Binks, Campbell, Driver, Harrison, Marson and Nicholson
In Attendance: Councillors D Green and E Green
1. ELECTION OF CHAIRMAN
[name removed], Corporate & Regulatory Services Manager, presided over the election of the Chairman by calling for nominations from Members.
Councillor Campbell proposed, Councillor Marson seconded and Members agreed that Councillor Hornus be the Chairman of the Pleasurama Site Development Task & Finish Group.
Councillor Hornus in the Chair.
2. APOLOGIES FOR ABSENCE
There were no apologies received at this meeting.
3. DECLARATIONS OF INTEREST
There were no declarations made at this meeting.
4. ESTABLISHING THE PLEASURAMA SITE DEVELOPMENT REVIEW TFG WORK PROGRAMME FOR 2013/14
[name removed] advised that Members could recommend amendments to the terms of reference to the Overview & Scrutiny Panel. Councillor Driver proposed that the Task & Finish Group (TFG) considers including the following to the terms of reference:
“To consider the stability of the sea cliff wall and a flood risk assessment for the site, including seeking external professional advice.”
Some Members were concerned that these proposed additions would increase the cost of undertaking the review. Members requested that the due diligence information be made available to Members of the Group. [name removed] confirmed that Members would be given access to the due diligence details. He also said that members of the public could be called to give evidence if the TFG so wished to collect evidence from the public. [name removed] advised that the issue regarding the carrying out a flood risk assessment was not part of the current planning permission requirements. Other Members indicated that the Council would be responsible for future maintenance of the cliff face. An assessment would help carry out maintenance more effectively.
[name removed], Director of Operational Services said that there were no current significant concerns regarding the overall stability of the cliff face. Additional remedial work had been carried out and there was no expectation to undertake significant maintenance work in the near future. He said that conducting a flood risk assessment would be an extremely costly exercise, which would be similar in size to the one carried out for the Margate flood defence project, and would have to be funded by the council. 2
Councillor Harrison moved, Councillor Campbell seconded and Members agreed that the draft terms of reference as reflected in Annex 1 to the report be adopted. These are as follows:
1. To review due diligence undertaken by the Council on the current developer;
2. To consider the options available to the Council with regard to the future of the development agreement with SFP Ventures (UK) Ltd;
3. To assess the commercial and legal implications of these options using external professional advice if necessary;
4. To consider future options for the Pleasurama site in general and make recommendations to Cabinet;
5. To produce a final report with recommendations for submission to the Overview and Scrutiny Panel and then to Cabinet.
Some Members requested that officers provide a clear definition of due diligence to include the issues that were considered in coming up with the due diligence report. Other Members expressed the view that Members had been advised that the then Chairman of the Overview & Scrutiny Panel would be given sight of the due diligence report in 2012/13. They wanted confirmation that the Chairman had been given access to that document. Members said that it was only by looking at the due diligence report, that Council could determine the worth of a proposed developer.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of previous meetingMinutes | 57 KB | DownloadRead as text |
Follow Pleasurama Site Development Review Task & Finish Group at Thanet and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Aug 2013 | To agree a work programme for 2013-2014It was AGREED: 1. THAT the S. 151 Officer be invited to attend the next meeting of the Group in order to answer quest... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies