A09 - F/TH/18/0071 - Land Fronting Marina Esplanade, Ramsgate

Approved Planning 1 paper

Planning Committee approved this item on Wednesday 20 June 2018. Below is the council's own wording, with the papers it was decided on.

Item342

Resolved

“THAT the officer’s recommendation be adopted, namely: ‘That the application be APPROVED subject to the following conditions: 1 The development hereby permitted shall be begun before the expiration of three years from the date of this permission. GROUND In accordance with Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Purchase Act 2004) 2 The proposed development shall be carried out in accordance with the submitted application as amended by the revised drawings numbered 3600_505 received 05 February 2018, 3600_105, 3600_404, 3600_409, 3600_410, 3600_411 and 3600_604 received 28 February 2018, 3600_700 and 3600_701 received 01 March 2018, 3600_104, 3600_400, 3600_402, 3600_402a and 3600_406 received 15 May 2018 and 3600_414 received 23 May 2018. GROUND To secure the proper development of the area. 3 No development shall take place until a Construction Environmental Management Plan, which shall include the following details: o timing/programme of works of construction o mitigation for the construction phase of the development including, noise, dust and lighting control measures, pollution incident control and site contact details. o traffic movements to and from the site and any necessary traffic management measures o areas for parking, loading, turning and unloading by site personnel, visitors and delivery vehicles o wheel washing facilities has been submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details. GROUND: To ensure pollution prevention measures are in place for all potentially polluting activities during construction in accordance within National Planning Policy Framework paragraph 109 and in the interests of highway safety 4 The development shall take place in the spring and summer months (April through to September) and avoiding work one hour either side of high tide in order to prevent disturbance to the Golden Plover and Turnstone which are Special Protected Area bird species. GROUND: In the interests of the essential protection of internationally important roosting birds in accordance with the advice contained within the National Planning Policy Framework. 5 The groyne extension and ramp hereby approved shall be finished using a roughened surface as agreed by the applicant in correspondence dated 28 March 2018. GROUND; In the interests of biodiversity conservation and enhancement in accordance with the advice contained within the National Planning Policy Framework.’”
Word for word from the decision Thanet published for this meeting. Source: democracy.thanet.gov.uk

Follow this further

Built from Thanet's papers

What the report saysPro

Report to Planning Committee

A09 F/TH/18/0071

PROPOSAL: Erection of a flood defence wall, improvements to existing sea wall, raising of ground levels and installation of flood gate LOCATION: together with extension of groyne.

Land Fronting Marina Esplanade RAMSGATE Kent

WARD: Eastcliff

AGENT: No agent

APPLICANT: [name removed]: Approve

Subject to the following conditions:

1 The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

GROUND In accordance with Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Purchase Act 2004)

2 The proposed development shall be carried out in accordance with the submitted application as amended by the revised drawings numbered 3600_505 received 05 February 2018, 3600_105, 3600_404, 3600_409, 3600_410, 3600_411 and 3600_604 received 28 February 2018, 3600_700 and 3600_701 received 01 March 2018, 3600_104, 3600_400, 3600_402, 3600_402a and 3600_406 received 15 May 2018 and 3600_414 received 23 May 2018.

GROUND To secure the proper development of the area.

3 No development shall take place until a Construction Environmental Management Plan, which shall include the following details:

o timing/programme of works of construction o mitigation for the construction phase of the development including, noise, dust and lighting control measures, pollution incident control and site contact details. o traffic movements to and from the site and any necessary traffic management measures o areas for parking, loading, turning and unloading by site personnel, visitors and delivery vehicles o wheel washing facilities has been submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details.

GROUND: To ensure pollution prevention measures are in place for all potentially polluting activities during construction in accordance within National Planning Policy Framework paragraph 109 and in the interests of highway safety

4 The development shall take place in the spring and summer months (April through to September) and avoiding work one hour either side of high tide in order to prevent disturbance to the Golden Plover and Turnstone which are Special Protected Area bird species.

GROUND: In the interests of the essential protection of internationally important roosting birds in accordance with the advice contained within the National Planning Policy Framework.

5 The groyne extension and ramp hereby approved shall be finished using a roughened surface as agreed by the applicant in correspondence dated 28 March 2018.

GROUND; In the interests of biodiversity conservation and enhancement in accordance with the advice contained within the National Planning Policy Framework.

INFORMATIVES

Please be aware that obtaining planning permission and complying with building regulations are separate matters - please contact building control on 01843 577522 for advice on building regulations

It is the responsibility of the applicant to ensure, prior to the commencement of the development hereby approved, that all necessary highway approvals and consents where required are obtained and that the limits of highway boundary are clearly established in order to avoid any enforcement action being by the Highway Authority. The applicant must also ensure that the details shown on the approved plans agree in every aspect with those approved under such legislation and common law. It is therefore important for the applicant to contact KCC Highway and Transportation to progress this aspect of the works prior to commencement on site

SITE, LOCATION AND DESCRIPTION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A09: F/TH/18/0071: Land Fronting Marina Esplanade, RamsgateReport 93 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 17 attended
BG
Councillor Bob GroveChair, present
CM
Councillor Carol MessengerVice-Chair, apologies
AA
Councillor Ash AshbeeCommittee Member, present
JB
Councillor John BuckleyCommittee Member, present
KC
Councillor Keith Coleman-CookeCommittee Member, present
TC
Councillor Terry ConnorCommittee Member, present
RE
Councillor Robin EdwardsCommittee Member, present
PE
Councillor Peter EvansCommittee Member, present
JF
Councillor Jeremy FairbrassCommittee Member, present
MF
Councillor Michelle FennerCommittee Member, present
JM
Councillor Jennifer MatterfaceCommittee Member, present
DS
Councillor David SaundersCommittee Member, present

All 17 on the meeting page

More from Thanet Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 A04 FH/TH/26/0502 9 High Street Minster Kent CT12 4BUAGREED, subject to the following conditions: 1 The development hereby permitted shall be begun before the expiration ... Agreed Open
15 Jul 2026 A01 F/TH/26/0260 Theatre Royal Addington Street Margate Kent CT9 1PWAGREED, Subject to the following conditions: 1 The development hereby permitted shall be begun before the expiration ... Agreed Open
17 Jun 2026 A01 F/TH/26/0306 Windmill House, The Avenue Margate Kent CT9 2STAGREED, Subject to the following conditions: 1 The proposed development shall be carried out in accordance with the s... Agreed Open
20 May 2026 A02 F/TH/24/1167 Little Cliffsend Farm Chalk Hill Ramsgate Kent CT12 5HPAGREED, subject to the following conditions: 1 The development hereby approved shall be carried out in accordance wit... Agreed Open
20 May 2026 A01 F/TH/25/0925 2 - 12 Harold Road Margate KentAGREED, Subject to the following conditions: 1 The development hereby permitted shall be begun before the expiration ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies