RESOLVED to endorse the recommendations to Cabinet as follows: That Cabinet: 1. Agree to accept the grant award of £1,410, 000 awarded to the Council from the Government’s Public Sector Decarbonisation Fund. 2. Approve the key decisions to award contracts for the design and the build of Air Source Heat Pumps, Cavity Wall Insulation and replacement windows at The Gateway in Cecil Street, Ramsgate and Hartsdown Leisure Centres and Kent Innovation Centre, following a procurement exercise. 3. Approve the spending of a further £1,842,434 can be spent by Thanet District Council from the approved capital budget to match fund the project over the next three financial years. 4. Agree that the Director of Place shall negotiate the final terms and sign the contract with the successful bidder. 5. Approve a General Fund capital budget virement of £108,000 in 2025/26, to transfer funding to this project from the discontinued Hartsdown Leisure Centre Solar Panels capital scheme, to allow works to begin in this financial year.
Word for word from the decision Thanet published for this meeting.Source: democracy.thanet.gov.uk
Public Sector Decarbonisation Scheme Fund Grant Award Meeting 15 July 2025
By Andreea Plant, Head of Property
Cabinet Portfolio Cllr Ruth Duckworth, Cabinet Member for Regeneration and Property
Key Decision Yes
Decision classification Unrestricted Ward: Garlinge, Margate Central, Central Harbour, St Peter’s
Purpose of the Report The purpose of this report is to invite members of the Overview and Scrutiny Panel to scrutinise, note and comment on the proposal that Cabinet approves officer to have permission to undertake the procurement and award of a building works contract to meet the requirements of the funding that was awarded to the council as part of the Public Sector Decarbonisation Scheme, along with the agreed council's match fund contribution as approved by the council's capital bid process.
Recommendation(s): Members of the Overview and Scrutiny Panel are asked to:
1. Note and scrutinise the report and consider any appropriate recommendations to Cabinet in advance of its meeting on the 24 July 2025.
2. Note and comment on the proposed recommendations to Cabinet, as follows:
i. Agree to accept the grant award of £1,410, 000 awarded to the Council from the Government’s Public Sector Decarbonisation Fund.
ii Approves the key decisions to award contracts for the design and the build of Air Source Heat Pumps, Cavity Wall Insulation and replacement windows at The Gateway in Cecil Street, Ramsgate and Hartsdown Leisure Centres and Kent Innovation Centre, following a procurement exercise. iii. Approves the spending of a further £1,842,434 can be spent by Thanet District Council from the approved capital budget to match fund the project over the next three financial years.
iv. Agrees that the Director of Place shall negotiate the final terms and sign the contract with the successful bidder.
iv. Approve a General Fund capital budget virement of £108,000 in 2025/26, to transfer funding to this project from the discontinued Hartsdown Leisure Centre Solar Panels capital scheme, to allow works to begin in this financial year.
1. Summary of Reasons
1.1 Following the development of heat decarbonisation plans (Appendix 1) by an organisation called Arthian (formerly Mabbett) for five buildings within Thanet District Council's Core Estate, an application was made by Thanet District Council to the Government's Public Sector Decarbonisation Scheme Fund to install energy efficiency measures at four chosen sites, the Gateway in Cecil Street, Kent Innovation Centre, Ramsgate and Hartsdown Your Leisure Centres.
1.2 Thanet District Council was successful in its bid and received a Grant Award from the fund in March 2025. The Grant Award requires a minimum recipient contribution (match fund) for the like-for-like replacement of the existing mechanical equipment. The amount that Thanet District Council must contribute to the project was calculated using a grant/carbon cost calculation. This was calculated by dividing the requested grant value by the direct carbon savings delivered by the measures.
1.3 The Grant Award, along with the required match funding, will go some way towards the Council fulfilling its commitment of achieving Net Zero by 2030, as outlined in the Corporate Plan 2024-2028, by reducing 257.73 tonnes of carbon emissions annually. Additionally, this project will lead to cost savings through improved energy-efficiency measures and will facilitate the replacement of existing mechanical services that are nearing the end of their lifespan.
1.4 The Grant Award must be spent by March 2028, with a number of key drawdown milestone dates set out in the Grant Award between May 2025 and the expected completion date of March 2028.
2. Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
25/014 - Health in All PoliciesRESOLVED to endorse the recommendations to Cabinet: To approve the adoption and implementation of the Health in All P...
26/008 - Draft 2026/27 HRA BudgetRESOLVED to endorse the recommendations as outlined in the report to Council as follows: The HRA budget for 2026/27 w...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.