RESOLVED to endorse the following recommendation to Cabinet: 1. To approve the virement of £957k from the 2025/26 Vehicle Replacement Programme budget to the Infrastructure Improvement Project budget (the budget for the Manston Road Depot Environmental Compliance Works). 2. To approve the key decision to award a contract for the delivery of the with an estimated value of £1.761 million.
Word for word from the decision Thanet published for this meeting.Source: democracy.thanet.gov.uk
Purpose of the Report Manston Road Depot is the operational base for the council's cleansing service and vehicle fleet. This report describes a funding gap that exists in relation to the Manston Road Depot, Environmental Compliance Project. This project is necessary to meet strict environmental permitting requirements for a part of the depot which is designated as a Household, Commercial and Industrial Waste Transfer Station. The project includes civil engineering works to improve waste storage provision and surface water drainage.
The required works cannot be delivered within the budget available and the report proposes the reallocation of funding from the Vehicle Replacement Programme to this project. The report also includes a recommendation that will be made to Cabinet to commit funds to the works which will exceed the £250k key decision threshold.
Recommendation(s): That the Overview and Scrutiny Panel note and scrutinise the report and consider any representations to Cabinet in advance of its meeting on 28 August 2025.
That the Overview and Scrutiny Panel note and comment on the proposed recommendations to Cabinet, as follows:
1. To approve the virement of £957k from the 2025/26 Vehicle Replacement Programme budget to the Infrastructure Improvement Project budget (the budget for the Manston Road Depot Environmental Compliance Works).
2. To approve the key decision to award a contract for the delivery of the Manston Road Depot Environmental Compliance Works with an estimated value of £1,761k. 1. Summary of Reasons
1.1 The depot at Manston Road is the operational base for the council's Cleansing Service and vehicle fleet. The service is responsible for household waste and recycling collections, street cleansing, public toilets and other functions such as garden, bulky and clinical waste collections.
1.2 Part of the depot site is the subject of a waste management permit. The budget virement recommended in this report will enable an existing works project to be taken forward to meet strict environmental permitting requirements. The project includes civil engineering works to improve waste storage provision and surface water drainage at the depot.
2. Background
2.1 A £1,320k capital budget was approved by council on 9 February 2023 as part of the budget report for the 2023/24 financial year to improve infrastructure at Manston Road Depot. This budget is also required to deliver four other infrastructure projects or activities in addition to the Environmental Compliance Project. The required Environmental Compliance Project cannot be delivered within the value of the remaining budget. Without a budget virement the council would not be able to undertake the required works which would lead to a high risk of enforcement action by the Environment Agency (EA) and would impact on statutory service provision by the council.
3. Relevant Issues
3.1 Thanet District Council holds an Environmental Permit (formerly a waste management licence) administered by the EA in compliance with the Environmental Permitting Regulations 2010 and the Environmental Protection Act 1990. The permit is for the keeping and handling of controlled waste within a designated boundary at Manston Road Depot in Margate.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
25/014 - Health in All PoliciesRESOLVED to endorse the recommendations to Cabinet: To approve the adoption and implementation of the Health in All P...
26/008 - Draft 2026/27 HRA BudgetRESOLVED to endorse the recommendations as outlined in the report to Council as follows: The HRA budget for 2026/27 w...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.