Thanet District Council
Overview & Scrutiny Panel, Tuesday 16 September 2025 at 7.00pm

Walpole Coast Protection - Coping Replacement

Approved Scrutiny 6 papers

Overview & Scrutiny Panel approved this item on Tuesday 16 September 2025. Below is the council's own wording, with the papers it was decided on.

Item163

Resolved

RESOLVED to endorse the following recommendations: 1. Cabinet approves the key decision to award a contract with a value in excess of £250k, and up to the value of the Environment Agency grant of £1,169,000 to the successful bidder, following a procurement exercise for capital works to replace a dilapidated section of sea wall between Hodges Gap and Newgate Gap. 2. Agree that the Director of Environment, having sought advice from legal services, agree the final terms of any contract award and sign the contract with the successful bidder.
Word for word from the decision Thanet published for this meeting. Source: democracy.thanet.gov.uk

Follow this further

Built from Thanet's papers

What the report saysPro

Report to Overview & Scrutiny Panel

WALPOLE COAST PROTECTION - COPING REPLACEMENT Overview and Scrutiny​ 16 September 2025

By​ Tony Marmo, Head of Coastal and Public Realm

Cabinet Member​ Cllr Steve Albon, Cleansing and Coastal

Key Decision​ Yes

Decision classification​ Unrestricted ​ Call in status​ Yes

Ward:​ Cliftonville East

Purpose of the Report The purpose of this report is to invite members of the Overview and Scrutiny Panel to scrutinise, note and comment upon the request to Cabinet for a decision to undertake the procurement and award of a contract for the Walpole Coast Protection project. The project is 100% grant funded capital works to replace a dilapidated section of sea wall between Hodges Gap and Newgate Gap. The estimated value of the contract will be £1m.

Recommendation(s): 1.​ That the Overview and Scrutiny Panel note and scrutinise the report and consider any representations to Cabinet in advance of its meeting on 25 September 2025.

2.​ That the Overview and Scrutiny Panel note and comment on the proposed recommendation to Cabinet, as follows:

a)​ Cabinet approves the key decision to award a contract with a value in excess of £250k, and up to the value of the Environment Agency grant of £1,169,000 to the successful bidder, following a procurement exercise for capital works to replace a dilapidated section of sea wall between Hodges Gap and Newgate Gap. b)​ Agree that the Director of Environment, having sought advice from legal services, agree the final terms of any contract award and sign the contract with the successful bidder.

1.​ Summary of Reasons 1.1​ As part of the Environment Agency Flood and Coast Erosion Risk Management (FCERM) programme delivered in Thanet by the Coast and Engineering Service, an erosion study focussing on the area between Walpole Bay and Newgate gap was commissioned and consequently an application for grant funding was made to the Environment Agency. 1.2​ A grant with a value of £1.169m has been secured to undertake the construction phase of the Walpole Coast Protection project. The project is 100% grant funded and does not require additional funding from the Council.

1.3​ The construction scheme objectives are to stabilise the existing sea wall structure and replace some sections to ensure its continued serviceable life. The absence of this project would eventually lead to a significant reduction in protection afforded to the cliffs by the sea defences to the point that the frontage would be undefended.

2.​ Background 2.1​ The existing precast concrete coping blocks along the frontage of Newgate Gap to Hodges Gap are routinely moving seaward and, in some cases, falling to the foreshore, due to the failure of the steel dowel bars that secure them to the sea wall. The frontage is at risk from coastal erosion if the sea wall fails.

2.2​ Failure of the seawall coping has led to a successful application to the Environment Agency for grant funding to study the frontage. The study identified that the sea wall coping along the frontage of Newgate Gap to Hodges Gap requires replacement. The policy in this area is to hold the line thus the requirement to replace the coping.

2.3​ The business case created from the study allowed for a further application for construction phase grant funding. The application was successful and the Council was awarded a £1.169m grant to undertake the works in the financial year 2024/25/26.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 179 KB Download
PDF
Appendix 2Appendix 2 2.6 MB Download
PDF
Appendix 3Appendix 3 2.2 MB Download
PDF
Appendix 4Appendix 4 2.7 MB Download
PDF
Appendix 5Appendix 5 3.8 MB Download
PDF
Walpole Coast Protection: Coping ReplacementReport 1.8 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 14 attended
PF
Councillor Phil FellowsChair, present
DG
Councillor David GreenVice-Chair, present
TA
Councillor Tricia AustinCommittee Member, present
JB
Councillor Joanne BrightCommittee Member, present
LB
Councillor Leo BritcherCommittee Member, present
HC
Councillor Helen CrittendenCommittee Member, present
AC
Councillor Alan CurrieCommittee Member, present
JD
Councillor John DavisCommittee Member, present
RF
Councillor Roopa FarookiCommittee Member, apologies
PM
Councillor Paul MooreCommittee Member, absent
JP
Councillor Jack PackmanCommittee Member, apologies
KP
Councillor Katie PopeCommittee Member, present

All 14 on the meeting page

More from Thanet Overview & Scrutiny Panel

All decisions
MeetingDecisionOutcome
18 Aug 2026 26/045 - Corporate Plan 2024-28, mid-term progress reviewIt was agreed that specific job target queries would be passed back to relevant heads of service, and members noted t... Agreed Open
18 Aug 2026 Quarter 4 Corporate Performance ReportRESOLVED to note the report. Noted Open
18 Aug 2026 25/014 - Health in All PoliciesRESOLVED to endorse the recommendations to Cabinet: To approve the adoption and implementation of the Health in All P... Approved Open
18 Aug 2026 Forward Plan and Exempt Cabinet Report listRESOLVED to note the Forward Plan and Exempt Cabinet Report List. Noted Open
3 Feb 2026 26/008 - Draft 2026/27 HRA BudgetRESOLVED to endorse the recommendations as outlined in the report to Council as follows: The HRA budget for 2026/27 w... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies