A01 F/TH/25/0961 Land West Of Thanet Offshore Wind Port Of Ramsgate Royal Harbour Approach Ramsgate Kent

Agreed Planning 1 paper

AI summaryThanet District Council's Planning Committee has approved its own application for a Green Campus business incubator at the Port of Ramsgate, comprising three buildings for training, workshops, offices and conference use, subject to 25 planning conditions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to 25 planning conditions covering drainage, noise, highways, biodiversity, lighting and contamination.
MoneyNot stated
What happens nextDevelopment must start within 3 years
Who it affectsNot stated

What was decided

The committee approved the erection of a three-storey building (Sui Generis use), two two-storey buildings (Use Class B2 and E(c)(ii)), a substation, with access, landscaping and parking, to be developed in two phases. Report P2, P76

Approval is granted to Thanet District Council's own Regeneration team as applicant, with HMY LLP as agent, with the development to be known as the Green Campus. Report P5, P6, P74

Blocks A and B are restricted to general industrial (B2) or commercial office (E(c)(ii)) use only, with no other use permitted including other purposes within Class E. Report P54, P55

Why

Officers recommended approval, concluding that the Conservation Officer raised no significant heritage concerns due to the site being set far from listed structures and outside the Conservation Area. Report P7, P89, P90, P91

The Tree Officer found the coastal plant palette appropriate, with only minor suggestions on watering, salt spray mitigation, wind exposure and tree pit drainage. Report P92, P93, P94, P95, P96, P97

KCC Ecology and Biodiversity confirmed sufficient information had been provided, including a +560.19% area habitat net gain, and accepted the shadow HRA conclusions. Report P222, P223, P226

What happens next

A detailed sustainable surface water drainage scheme must be submitted and approved before any phase of development begins, with verification required before occupation of any building. Report P13, P16

Off-site highway works, vehicle access arrangements, the zebra crossing, visibility splays, EV charging points, cycle parking and a Travel Plan must all be completed before first use of the site. Report P39, P43, P48, P50, P52

A Biodiversity Gain Plan must be submitted and approved before development begins, and habitat creation measures must be photographed and submitted before first use. Report P30, P32, P56, P57, P58

Options considered

  • Chosen: Approve the application subject to conditions. Officer recommendation; Conservation Officer raised no significant heritage concerns; KCC Ecology confirmed sufficient information; site seen as acceptable departure from Thanet Local Plan policies SP11, E05 and E06. Report P7, P55, P89, P223

Implications

  • Legal: Biodiversity Gain Plan required under Schedule 7A to the Town and Country Planning Act 1990 before any development begins, as no statutory exemptions apply. Report P56, P57, P58
  • Equalities: Concerns raised about accessibility: the most direct walking route to bus stops includes steps and is unavailable for wheelchair and pushchair users; step-free route adds around 700m. Report P196
  • Climate: Drainage scheme must accommodate surface water up to and including the climate change adjusted critical 100 year storm, with no increase in flood risk on or off site. Report P13
  • Risk: KCC Highways raised concerns about Military Road narrowings and traffic calming if Ramsgate Port reopens in future, and about HGV access arrangements to the adjacent Vattenfall site. Report P164, P168, P214, P215, P218
  • Other: Material Management Plan required before commencement, meeting requirements of the Site Investigation Report dated 20 December 2024, to deal with potential contamination. Report P112, P113
  • Other: Conference and event activities restricted to 07:00 to 23:00 Monday to Saturday and 07:00 to 19:00 Sundays and bank holidays, with amplified music not to exceed 50dB 1min LAeq at 1 metre from any speaker. Report P21, P23, P105, P107

Who and where

  • Thanet District Council (Regeneration team) as applicant and landowner Report P6
  • Vanttenfall (wind farm operator) whose buildings lie immediately to the east of the site Report P67, P163
  • Users of the former port terminal building and remaining port berths to the south Report P67
  • Residents and visitors above the chalk cliffs to the north, including the Ramsgate Conservation Area and Grade I and II listed buildings such as St Augustine's Abbey and The Grange Report P68
  • Royal Harbour (Grade II* listed) and associated listed buildings including the Clock House and Obelisk Report P68
  • Highway users of Military Road, including HGVs, with road narrowed, speed limit proposed to reduce from 30mph to 20mph, and shuttle working build-outs Report P147, P195, P202, P203

Timeline

  • 2024-10-02: Previous application F/TH/24/1154 returned for similar Green Campus scheme. Report P72
  • 2025-09-15: Current application validated. Report P192
  • 2026-03-03: Transport Statement, Travel Plan, Construction Environmental Management Plan and Stage 1 Road Safety Audit received. Report P145, P151
  • 2026-03-12: TDC Environmental Health updated comments received confirming EV charging and CEMP. Report P98, P100
  • 2026-04-10: KCC Ecology and Biodiversity final comment confirming sufficient information. Report P221
  • 2026-04-14: KCC Highways final comments received. Report P133
  • 2026-04-22: Planning Committee decision to approve, date of this permission.
  • Within 3 years of permission: Development must begin, otherwise the permission expires. Report P9

Plain English for the jargon

  • Use Class Sui Generis: Uses that do not fall within any of the standard use classes in the Town and Country Planning (Use Classes) Order 1987, treated on their own merits.
  • Use Class B2: General industrial use.
  • Use Class E(c)(ii): Commercial, business and service use, specifically research and development or industrial processes.
  • SuDS: Sustainable Drainage System, a method of managing surface water runoff that mimics natural drainage.
  • Biodiversity Net Gain: An approach requiring development to leave biodiversity in a better state than before, measured using a biodiversity metric and secured through a Biodiversity Gain Plan.
  • EVC / EVCP: Electric Vehicle Charging Point.
  • HRA (Shadow HRA): Habitats Regulations Assessment, an assessment of likely effects on protected European sites such as the Thanet Coast SAC.
  • CEMP: Construction Environmental Management Plan, setting out measures to control environmental effects during construction.
  • TRO: Traffic Regulation Order, the legal mechanism used to change speed limits or parking restrictions.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4a

Resolved

AGREED, subject to the following conditions: 1 The development hereby permitted shall be begun before the expiration of three years from the date of this permission. GROUND: In accordance with Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Purchase Act 2004). 2 The development hereby approved shall be carried out in accordance with the submitted drawings numbered 0120 Rev P01 received 08/04/2026, 0130 Rev P07, 0131 Rev P07, 0132 Rev P07, 0133 Rev P06, 0100 Rev P04 received 20/03/2026, RAMS-TFCGC-00-D-L-1001 Rev P10 received 17/03/2026, ECO-3288-XT-001 Rev 02, EDS-073102.01 Sht 1 of 3 Rev A, EDS-07-3102.01 Sht 2 of 3 Rev A, EDS-07-3102.01 Sht 3 of 3 Rev A GROUND: To secure the proper development of the area. 3 Development shall not begin in any phase until a detailed sustainable surface water drainage scheme for the site has been submitted to (and approved in writing by) the local planning authority. The submitted scheme shall demonstrate compliance with the required technical standards at the time of submission and shall demonstrate that the surface water generated by this development (for all rainfall durations and intensities up to and including the climate change adjusted critical 100 year storm) can be accommodated and disposed of without increase to flood risk on or off-site. The drainage scheme shall also demonstrate (with reference to published guidance): · that silt and pollutants resulting from the site use can be adequately managed to ensure there is no pollution risk to receiving waters. · appropriate operational, maintenance and access requirements for each drainage feature or SuDS component are adequately considered, including the proposed arrangements for future ongoing management and maintenance. The drainage scheme shall be implemented in accordance with the approved details. GROUND: To ensure the development is served by satisfactory arrangements for the disposal of surface water and to ensure that the development does not exacerbate the risk of on/off site flooding. These details and accompanying calculations are required prior to the commencement of the development as they form an intrinsic part of the proposal, the approval of which cannot be disaggregated from the carrying out of the rest of the development. 4 No building on any phase (or within an agreed implementation schedule) of the development hereby permitted shall be occupied until a Verification Report, pertaining to the surface water drainage system and prepared by a suitably competent person, has been submitted to and approved by the Local Planning Authority. The Report shall demonstrate that the drainage system constructed is consistent with that which was approved. The Report shall contain information and evidence (including photographs) of details and locations of inlets, outlets and control structures; landscape plans; full as built drawings; information pertinent to the installation of those items identified on the critical drainage assets drawing; and, the submission of an operation and maintenance manual for the sustainable drainage scheme as constructed. GROUND: To ... view the full minutes text for item 4a
Word for word from the decision Thanet published for this meeting. Source: democracy.thanet.gov.uk

Follow this further

Built from Thanet's papers

What the report saysPro

Report to Planning Committee

A01 F/TH/25/0961

PROPOSAL: Erection of 1no three storey building (Use Class Sui Generis) 2no two storey buildings (Use Class B2 and E(c)(ii)), and a substation, together with associated access, landscaping and parking

LOCATION: Land West Of Thanet Offshore Wind Port Of Ramsgate Royal Harbour Approach Ramsgate Kent

WARD: Central Harbour

AGENT: HMY LLP

APPLICANT: Thanet District Council (Regeneration)

RECOMMENDATION: Approve

Subject to the following conditions:

1 The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

GROUND: In accordance with Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Purchase Act 2004).

2 The development hereby approved shall be carried out in accordance with the submitted drawings numbered 0120 Rev P01 received 08/04/2026, 0130 Rev P07, 0131 Rev P07, 0132 Rev P07, 0133 Rev P06, 0100 Rev P04 received 20/03/2026, RAMS-TFC- GC-00-D-L-1001 Rev P10 received 17/03/2026, ECO-3288-XT-001 Rev 02,, EDS-07- 3102.01 Sht 1 of 3 Rev A, EDS-07-3102.01 Sht 2 of 3 Rev A, EDS-07-3102.01 Sht 3 of 3 Rev A

GROUND; To secure the proper development of the area.

3 Development shall not begin in any phase until a detailed sustainable surface water drainage scheme for the site has been submitted to (and approved in writing by) the local planning authority. The submitted scheme shall demonstrate compliance with the required technical standards at the time of submission and shall demonstrate that the surface water generated by this development (for all rainfall durations and intensities up to and including the climate change adjusted critical 100 year storm) can be accommodated and disposed of without increase to flood risk on or off-site.

The drainage scheme shall also demonstrate (with reference to published guidance): o that silt and pollutants resulting from the site use can be adequately managed to ensure there is no pollution risk to receiving waters. o appropriate operational, maintenance and access requirements for each drainage feature or SuDS component are adequately considered, including the proposed arrangements for future ongoing management and maintenance. The drainage scheme shall be implemented in accordance with the approved details

GROUND: To ensure the development is served by satisfactory arrangements for the disposal of surface water and to ensure that the development does not exacerbate the risk of on/off site flooding. These details and accompanying calculations are required prior to the commencement of the development as they form an intrinsic part of the proposal, the approval of which cannot be disaggregated from the carrying out of the rest of the development.

4 No building on any phase (or within an agreed implementation schedule) of the development hereby permitted shall be occupied until a Verification Report, pertaining to the surface water drainage system and prepared by a suitably competent person, has been submitted to and approved by the Local Planning Authority. The Report shall demonstrate that the drainage system constructed is consistent with that which was approved. The Report shall contain information and evidence (including photographs) of details and locations of inlets, outlets and control structures; landscape plans; full as built drawings; information pertinent to the installation of those items identified on the critical drainage assets drawing; and, the submission of an operation and maintenance manual for the sustainable drainage scheme as constructed.

GROUND: To ensure that flood risks from development to the future users of the land and neighbouring land are minimised, together with those risks to controlled waters, property and ecological systems, and to ensure that the development as constructed is compliant with and subsequently maintained pursuant to the requirements of paragraph 182 of the National Planning Policy Framework.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A01 F/TH/25/0961 Land West Of Thanet Offshore Wind Port Of Ramsgate Royal Harbour Approach Ramsgate KentReport 667 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 16 attended
HC
Councillor Helen CrittendenChair, present
PM
Councillor Pat MakinsonVice-Chair, apologies, sent representative
SA
Councillor Steve AlbonCommittee Member, apologies, sent representative
MB
Councillor Martin BoydCommittee Member, present
JB
Councillor Joanne BrightCommittee Member, present as substitute
KB
Councillor Kristian BrightCommittee Member, apologies, sent representative
LB
Councillor Leo BritcherCommittee Member, present as substitute
MG
Councillor Mike GarnerCommittee Member, present
DG
Councillor David GreenCommittee Member, expected
JM
Councillor Jennifer MatterfaceCommittee Member, present
PM
Councillor Paul MooreCommittee Member, present
JP
Councillor Jack PackmanCommittee Member, apologies, sent representative

All 16 on the meeting page

On this subject at Thanet

Search all
  1. A01 F/TH/25/0961 Land West Of Thanet Offshore Wind Port Of Ramsgate Royal Harbour Approach Ramsgate KentThis decision
  2. D04 - F/TH/19/0289 - Land West Of Hazeldene Ramsgate Road, SarreApproved
  3. A03 - OL/TH/17/1795 - Land West Of Hazeldene, Ramsgate Road, SarreApproved
  4. A01 R/TH/15/0250 Land North Of Haine Road Broadstairs And West Of Nash, Road MARGATE KentApproved
  5. A03 - F/TH/15/0865 - Land East Of 40 Canterbury Road West, RamsgateApproved
  6. A05 - f/th/15/0377 - land rear of 2 to 6, elm grove, westgate on seaApproved

More from Thanet Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 A04 FH/TH/26/0502 9 High Street Minster Kent CT12 4BUAGREED, subject to the following conditions: 1 The development hereby permitted shall be begun before the expiration ... Agreed Open
15 Jul 2026 A01 F/TH/26/0260 Theatre Royal Addington Street Margate Kent CT9 1PWAGREED, Subject to the following conditions: 1 The development hereby permitted shall be begun before the expiration ... Agreed Open
17 Jun 2026 A01 F/TH/26/0306 Windmill House, The Avenue Margate Kent CT9 2STAGREED, Subject to the following conditions: 1 The proposed development shall be carried out in accordance with the s... Agreed Open
20 May 2026 A02 F/TH/24/1167 Little Cliffsend Farm Chalk Hill Ramsgate Kent CT12 5HPAGREED, subject to the following conditions: 1 The development hereby approved shall be carried out in accordance wit... Agreed Open
20 May 2026 A01 F/TH/25/0925 2 - 12 Harold Road Margate KentAGREED, Subject to the following conditions: 1 The development hereby permitted shall be begun before the expiration ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies