Joint Transportation Board, Thursday 10 September 2026 at 7.00pm

Highways Forward Works Programme

Agreed Committee 6 papers

AI summaryThanet Joint Transportation Board notes Kent highways programme for 2024/25 and 2025/26, asks officers to investigate, and flags Vere Road crossing design work.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedBoard asked officers to look into report
MoneyNot stated
What happens nextVere Road crossing in design stageCrash cluster analysis underway, options considered
Who it affectsThanet road users and residentsHighways maintenance, safety and street works

What was decided

The Board noted the Highways Forward Works Programme report covering 2024/25 and 2025/26 and asked officers to investigate it. Report P24

Members asked that contractors collect warning boards and signs once roadworks are finished, and noted that utility companies leaving signs out beyond permit times face Section 74 charges.

The Board heard that an informal pedestrian crossing on Vere Road, Broadstairs is in the design stage after a crash cluster analysis, with options including a build-out and a refuge island under consideration.

Why

The report updates members on schemes approved for construction in 2024/25 and 2025/26, replacing earlier two-year programmes as Kent County Council moves to multi-year asset management. Report P6, P8, P9, P10

It covers planned road, footway and cycleway renewal, drainage, street lighting, transportation and safety schemes, developer funded works, bridge works, traffic systems, Member Highway Fund schemes, and road markings. Report P14, P15, P16, P17, P18, P19, P20, P21, P22

What happens next

Officers will investigate the report following the Board's request.

A new two-year programme covering 2024/25 to 2025/26 is in place, and work to revise the years three to five programme to cover 2026/27 to 2028/29 is in progress. Report P10, P11

The programme is under regular review and may change due to budget allocation, contract rates, inflation, conflicting works, shifting priorities, and engineering assessment during design. Report P12

Options considered

  • Rejected: Build-out at Vere Road, Broadstairs. One option being considered alongside others
  • Rejected: Refuge island at Vere Road, Broadstairs. One option being considered alongside others
  • Chosen: Section 74 charges on utility companies overrunning permit times. Existing enforcement tool, members urged to report specific locations

Implications

  • Risk: Programme content may shift as schemes are verified and as budget, inflation or engineering assessments change. Report P11, P12
  • Legal: Utility companies leaving signs out beyond their permit window can be charged under Section 74.
  • Other: Members were encouraged to report specific locations where utility signs have been left out beyond permit times.

Who and where

  • Motorists and road users in Thanet
  • Utility companies working in Thanet
  • Residents and pedestrians on Vere Road, Broadstairs
  • Thanet District Council and Kent County Council highways teams Report P2, P27

Timeline

  • Summer 2021: Kent County Council published its Highways Asset Management Plan with a five-year Forward Works Programme for 2021/22 to 2025/26. Report P9
  • October 2022: First two-year programme replaced with a programme covering 2022/23 to 2023/24. Report P10
  • 2024/25 to 2025/26: New two-year programme now covers these years. Report P10
  • 10th September 2026: Report presented to the Thanet Joint Transportation Board. Report P3

Plain English for the jargon

  • HAMP: Highways Asset Management Plan, Kent County Council's plan for managing road infrastructure over multiple years.
  • Section 74 charges: Charges that can be levied on utility companies when street works overrun the time allowed under their permit.
  • Combined Members Grant: Kent County Council funding allocated to county members for local highway improvements, also called the Member Highway Fund.
  • Casualty Reduction Measures: Road safety interventions designed to reduce collisions, often following analysis of crash clusters.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

It was agreed that officers would investigate this report. · A request was made to ensure contractors collect warning boards and signs once roadworks were finished to avoid motorist confusion. Utility companies leaving signs out beyond their permit times were subject to Section 74 charges, and councillors were encouraged to report specific locations. · The informal pedestrian crossing at Vere Road, Broadstairs, was in the design stage following a crash cluster analysis, and officers were looking into options such as a build-out and a refuge island. The Board NOTED the report.
Word for word from the decision Thanet published for this meeting. Source: democracy.thanet.gov.uk

Follow this further

Built from Thanet's papers

What the report saysPro

Report to Joint Transportation Board

To: Thanet Joint Transportation Board

By: KCC Highways and Transportation

Date: 10th September 2026

Subject: Highways Forward Works Programme: 2024/25 and 2025/26

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2024/25 and 2025/26.

In summer 2021 Kent County Council published a Highways Asset Management Plan (HAMP), which included, as Appendix C, a five-year Forward Works Programme for the years 2021/22 to 2025/26. This reflected the need to move away from annual programmes and to consider asset management activity as a multi-year one.

The first part of the programme concerned the two years 2021/22 - 2022/23. In October 2022 we replaced this with a programme covering the years 2022/23 - 2023/24, and we have now produced a new two-year programme covering the years 2024-25 – 2025-26. As before, most of the sites included in this programme have already been verified by our engineers.

The second part of our programme related to years three to five of our five-year programme (2023/24 - 2025/26). This too is in need of revision to cover the years 2026/27 - 2028-29 and the work required to do this is currently in progress. As before, our new years three to five programme will be largely based on data from our asset management systems, so may be subject to more changes as the schemes are verified.

This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, inflationary pressures such as material price increases, conflicting works, and to reflect our changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase, and additional sites may be added or others advanced if their condition deteriorates rapidly so that we need to react in order to keep the highway in a safe and serviceable condition.

Further information about how we manage our highway infrastructure, including our county- wide five-year forward works programme, may be found on our website: https://www.kent.gov.uk/about-the-council/strategies-and-policies/transport-and-highways- policies/managing-highway-infrastructure

In addition to planned maintenance of our highway assets, this report includes transportation and safety schemes, developer funded works, Combined Members Grant schemes, and planned maintenance of public rights of way. Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – see Appendix D  Casualty Reduction Measures  Externally Funded Schemes  Major Capital Programme

Developer Funded Works – see Appendix E

Bridge Works – see Appendix F

Traffic Systems – see Appendix G

Combined Members Grant – Member Highway Fund – see Appendix H

Road Markings – see Appendix I

Conclusion

1. This report is for Members’ information.

Contact Officers:

The following contact officers can be contacted on 03000 418181

Pauline Harmer Senior Highway Manager East Kent Paul Valek Thanet Highway Manager Alan Casson Strategic Asset Manager Carol Valentine Drainage Asset Manager Helen Rowe Structures Asset Manager Sue Kinsella Street Light Asset Manager Toby Butler Traffic Operations and Technology Manager Jamie Hare Development Agreements Manager Nikola Floodgate Road Safety and Active Travel Group Manager [email protected] Major Capital Programme Manager Jonathan Dean Highway Manager Special Projects/HSR/Signs & Lines

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 90 KB Download
PDF
Appendix 2Appendix 2 86 KB Download
PDF
Appendix 3Appendix 3 91 KB Download
PDF
Appendix 4Appendix 4 90 KB Download
PDF
Appendix 5Appendix 5 97 KB Download
PDF
Highways Forward Works ProgrammeReport 71 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 16 attended
KC
KCC Councillor John FinchCommittee Member, present
KP
Councillor Katie PopeVice-Chair, present
JB
Councillor Joanne BrightCommittee Member, apologies, sent representative
PC
Parish Councillor Derek Crow-BrownCommittee Member, absent
JD
Councillor John DavisCommittee Member, present
ED
Councillor Emma DawsonCommittee Member, present
MG
Councillor Mike GarnerCommittee Member, present
AN
Councillor Anne-Marie NixeyCommittee Member, present
HS
Councillor Harry ScobieCommittee Member, absent
KC
KCC Councillor Luke EvansCommittee Member, absent
KC
KCC Councillor Jamie HendersonCommittee Member, present
KC
KCC Councillor Terry MoleCommittee Member, present

All 16 on the meeting page

More from Thanet Joint Transportation Board

All decisions
MeetingDecisionOutcome
5 Jun 2025 KCC Highways Works Programme: 2024/25 and 2025/26RESOLVED to note the report. Noted Open
5 Jun 2025 Parking and Waiting Review - Thanet VariousRESOLVED to note the report. Noted Open
5 Jun 2025 Civil Enforcement UpdateRESOLVED to note the report. Noted Open
12 Jun 2014 Minutes of Previous MeetingIt was AGREED, on the proposal of Councillor K Gregory, seconded by Councillor D Saunders, that, subject to that amen... Agreed Open
27 Mar 2014 Minutes of Previous MeetingIt was AGREED that the minutes of the meeting held on 19 December 2013 be approved and signed by the Chairman. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies