Resolved
Noted the action taken.
Policy and Resources Committee noted this item on Monday 6 December 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Noted the action taken.
1.1To advise Members that an exemption to the Procurement process was approved by the Shared Director of Finance under the Exceptional Circumstances exemption as permitted by the Council’s Constitution.
2 Details
2.1An exemption may be considered by the Chief Executive or a Director in exceptional circumstances. This applies in the case of the Livestreaming/Hybrid meetings.
2.2Once approved, a report to the Policy and Resources Committee must detail the actions taken. This report is for information only to comply with the requirements of the Constitution.
2.3The exemption was given to award the contract to Carillion. The cost of the work to be able to livestream/hold hybrid meetings will be met from a Grant of £60k which was successfully obtained from the Hertfordshire Health Protection Board.
2.4Carillion submitted a quote as required by the Council’s Contracts Procedures Rules, along with two other companies. The company were identified as the best choice for the work as they already supply the sound system and associated services within the Penn Chamber. As these systems link together it makes sense for a single supplier to carry out all the support and maintenance. From an officer perspective there is a single point of contact and one contract to manage. Training and a comprehensive support package are included.
2.5The Committee should note that two other quotes were obtained which were comparable to the Carillion quote. On examination of them, it became apparent that the benefit of using the existing supplier was a strong option given the need for the new system to link into existing systems and would be extremely beneficial. It would also reduce the risks of managing the systems in the future. The feedback from officers who attended the presentations on the quotes was very positive about the proposals hence it became clear that this was by far the most advantageous route to a supplier contract and that all the circumstances justified this exemption.
2.6Officers are progressing the work in order that the Council can livestream/hold hybrid meetings as soon as possible although it is not legally possible at the current time for Councillors making a decision at a public meeting to attend the meeting remotely.
3 Options and Reasons for Recommendations
3.1The Constitution requires that a report is taken to the Policy and Resources Committee on the action taken in the event that an exemption to the procurement process is approved.
4 Policy/Budget Reference and Implications
Page 1 of 2 4.1 The recommendations in this report are set out in Part 4 of the Council’s Constitution.
5.1There are no costs to the Council in installing the required equipment as the cost is being met by the grant from the Hertfordshire Health Protection Board
5.2The yearly maintenance cost of £2,000 will be met within existing budgets
6 Legal, Equal Opportunities, Staffing, Environmental, Community Safety, Public Health, Customer Services Centre, Communications & Website, Risk Management and Health & Safety Implications
6.1None Specific.
7.1That the Policy and Resources Committee note the action taken.
Report prepared by: Sarah Haythorpe, Principal Committee Manager Data Quality Data sources: not applicable Data checked by James Baldwin, Solicitor to the Council, Tracy Langley, Facilities Manager and Emma Tiernan Head of ICT. Background Papers The Council’s Constitution: Part 4 – Contracts Procedure Rules APPENDICES / ATTACHMENTS None
Page 2 of 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EXEMPTION FROM PROCUREMENT PROCEDURE RULES: LIVESTREAMING/HYBRID MEETINGSReport | 21 KB | DownloadRead as text |
Follow Policy and Resources Committee at Three Rivers and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Oct 2026 | Budget Monitoring Report to 30 June 2026· That the revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4. 1. 4 be approved and in... | Noted | Open |
| 8 Oct 2026 | Planning Committees and the National Scheme of Delegation of Planning FunctionsThat Policy and Resources recommend to Council: · To agree the process and procedure detailed in Appendix 4, with min... | Agreed | Open |
| 8 Oct 2026 | Business Solar Panel GrantThat: · Policy and Resources Committee approve the revised terms of the Solar PV and Battery Grant Scheme: o Increasi... | Approved | Open |
| 8 Oct 2026 | Aquadrome Project - Match Funding RequestThat: · The Policy and Resources Committee recommends to Full Council that £165,000 of capital funds be allocated to ... | Decided | Open |
| 8 Oct 2026 | Cemetery Rules and RegulationsThat: · The Committee approves the revised attached at Appendix A. · The Committee authorises officers to implement t... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.