that the Committee · Noted that the Internal Audit Progress Report for the period to 8 March 2024. · Approved amendments to the Audit Plan as at 8 March 2024. · Agreed changes to the implementation date for 4 audit recommendations (paragraph 2.5) for the reason set out in Appendices 3 to 7. · Agreed removal of implemented audit recommendations (Appendices 3 to 7)
Word for word from the decision Three Rivers published for this meeting.Source: moderngov.threerivers.gov.uk
Members are recommended to: Note the Internal Audit Progress Report for the period to 8 March 2024 Approve amendments to the Audit Plan as at 8 March 2024 Agree changes to the implementation date for 4 audit recommendations (paragraph 2.5) for the reason set out in Appendices 3 to 7 Agree removal of implemented audit recommendations (Appendices 3 to 7) Contents
1 Introduction and Background 1.1 Purpose of Report 1.2 Background
2 Audit Plan Update 2.1 Delivery of Audit Plan and Key Findings 2.3 Audit Recommendations 2.6 Proposed Audit Plan Amendments 2.7 Audit Plan Delivery Progress
Appendices 1 Progress against the 2023/24 Audit Plan 2 2023/24 Audit Plan Projected Start Dates 3-7 Progress against Outstanding Internal Audit Recommendations 8 Assurance and Priority Levels
1 1. Introduction and Background Purpose of Report
1.1This report details:
a) Progress made by the Shared Internal Audit Service (SIAS) in delivering the Council’s annual audit plan for 2023/24 as at 8 March 2024. b) Proposed amendments to the approved 2023/24 Annual Audit Plan. c) Implementation status of all previously agreed audit recommendations from 2019/20 onwards. d) An update on performance management information as at 8 March 2024.
Background
1.2The work of internal audit is required to be reported to a Member Body so that the Council has an opportunity to review and monitor an essential component of corporate governance and gain assurance that its internal audit provision is fulfilling its statutory obligations. It is considered good practice that progress reports also include proposed amendments to the agreed annual audit plan.
1.3The 2023/24 Annual Audit Plan was approved by Audit Committee on 28 March 2023.
1.4The Audit Committee receives periodic updates on progress against the Annual Audit Plan from SIAS, the most recent of which was brought to this Committee on 30 November 2023.
2. Audit Plan Update Delivery of Audit Plan and Key Audit Findings
2.1At 8 March 2024, 88% of the 2023/24 Audit Plan days had been delivered (calculation excludes unused ‘To Be Allocated’). Appendix A provides a status update on each individual deliverable within the audit plan.
2.2The following 2023/24 final reports have been issued since the November 2023 Audit Committee.
Audit Title Date of Assurance Number and Issue Level Priority of Recommendations IT Operations Dec ‘23 Reasonable Two Medium One Medium Safeguarding Jan ‘24 Reasonable Two Low Watersmeet Theatre Feb ‘24 Reasonable Four Low
2 All Priority Audit Recommendations
2.3Members will be aware that a Final Audit Report is issued when agreed by Management. This includes an agreement to implement the recommendations made. It is SIAS’s responsibility to bring to Members’ attention the implementation status of recommendations; it is the responsibility of officers to implement the recommendations by the agreed date.
2.4The table below summarises progress in implementation of all outstanding internal audit recommendations as at 8 March 2024, with full details given in appendices 3 to 7:
Year Number of Implemented Not Outstanding % Recommendations yet & request implemented due made for extended time or no update provided 2019/20 37 36 0 1 97% 2020/21 25 24 0 1 96% 2021/22 36 35 1 0 97% 2022/23 44 41 3 0 93% 2023/24 6 2 2 2 33%
2.5Since 30 November 2023 Audit Committee, extension to implementation dates have been requested by action owners for 4 recommendations as follows:
One from the 2019/20 Property (Rent and Lease Administration) audit, with a revised target date of 31 August 2024 (was 31 January 2024). One from the 2020/21 Debtors audit, with a revised target date of 31 March 2024 (was 31 December 2023) and, Two from the 2023/24 Taxi Licensing audit, with revised target dates of 28 June 2024 (was 30 April 2024).
Proposed 2023/24 Audit Plan Amendments
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal Audit Annual Report 2025/26Recommendation Members are recommended to: Note the Annual Assurance Statement and Note the results of the self-asses...
Statement of Accounts Update 2025/26Recommendation To note the update in relation to the 2025/26 Statement of Accounts timeframes. To review the draft Ac...
Statement of Accounts Update 2025/26To note the update in relation to the 2025/26 Statement of Accounts timeframes. To review the draft Accounting Polici...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.