To agree Option 1 to progress to complete the project at Leavesden Country Park, and in so doing to agree to increase the budget for this project by £45,197.01, utilising S106 funding from budget code 0193 – Reserve S106 Horsefield – Abbots Langley (Open Space), and for this to be resolved through use of the Council’s urgency procedure.
Word for word from the decision Three Rivers published for this meeting.Source: moderngov.threerivers.gov.uk
1.1The purpose of this report is to outline work to date to widen the main entrance at Leavesden Country Park and the additional budget required, should members wish to progress the project to full completion.
2 Details
2.1Planning permission to widen and enhance the main entrance into Leavesden Country Park was agreed at 18 April 2024 Planning Committee (23/1916/FUL).
2.2This followed advice from the Hertfordshire County Council (HCC) Highways team prior to submitting the planning application. The HCC Highways team advised Three Rivers District Council to commission extensive road safety audits, technical drawings including visibility splay (a drawing plan that visualises the angle and distance from which drivers emerging from an access can see and be seen by drivers proceeding along the priority road) along with a swept path analysis (the calculation and analysis of the movement and path of different parts of a vehicle when that vehicle is undertaking a manoeuvre). These were all completed and formed part of the planning application.
2.3The works to the entrance included restoration of the heritage railings, new columns and pier caps to mark the entrance, a new combined automatic vehicle height barrier and gate to improve access into the site, along with a wider entrance to improve visibility for vehicles entering and exiting the site.
2.4The total budget allocated for this project was £191,256, which is being funded from the Leavesden Country Park S106 budget.
2.5Following approval for the works, Officers procured a contractor and completed the required paperwork to progress the project. An initial Section 50 was submitted to Hertfordshire County Council (HCC) Highways in early August, which was paid for on 9 August 2024 and dates agreed for the work to be carried out in early September.
2.6A Section 50 application is: Under the New Roads and Street Works Act Section 50, licences are needed in order to lay new or maintain existing apparatus in the public highway. Any contractors who want to carry out roadwork excavations in the highway must apply for and be granted a Section 50 licence before work starts.
2.7However, at a site meeting on 8 August 2024, the contractor and Three Rivers District Council (TRDC) Officers identified other major road works taking place at either end of College Road. A decision was therefore taken by TRDC Officers and the contractors to delay the work to avoid additional disruption to the local community.
2.8A further Section 50 was submitted (dated 29 August 2024) for new dates, however, this second one was rejected and the contractor advised to submit a Section 38 to HCC Highways. When questioned by TRDC officers as to the reason for the change in requirements, HCC Highways for the ensuing period failed on numerous occasions to provide clear requirements for the progression of the application or the reasons for the change.
2.9A Section 38 agreement (or S38) is: a section of the Highways Act 1980 that can be used when a developer proposes to construct a new estate road for residential, industrial or general-purpose traffic that may be offered to the Highway Authority for adoption as a public highway.
2.10There have been ongoing discussions between TRDC and HCC officers regarding the work as TRDC officers made every effort to gain the permissions and to understand the increasing additional fees which HCC Highways wish to charge for that permission. This has been escalated to senior officer level with Lead Member input.
2.11Hertfordshire County Council (HCC) have stated that they expect the following additional costs to be paid by Three Rivers District Council:
Description Estimated Fee
Development Management Design £3,145 Review Activities
Services Support £1,625
Construction Activities £3,353
Stage 3 Road Safety Audit by HCC £2,300 Auditors, or Stage 4 if over a year
Sub-total £10,423
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Monitoring Report to 30 June 2026· That the revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4. 1. 4 be approved and in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.